Traffic Management Plan

Attached to the e-mail Operational Works Application OPW21/0212 - 31 Bottlebrush Ave, - DA Form 1 - Civil & Landscaping Plans - Construction Management Plan - Qleave - Project Management Plan - Traffic Management Plan - cover letter.

of 8
                                   TRAFFIC GUIDANCE SCHEME/S (TGS) COVER SHEETS – 31 BOTTLEBRUSH AVE – NOOSA HEADS
                                        GENERAL INFORMATION, NOTES AND TRAFFIC MANAGEMENT CONSIDERATIONS

                                                CLIENT:                                      COLE PROJECTS                       PROJECT DESCRIPTION:            RESIDENTIAL CONSTRUCTION
                                                CLIENT CONTACT:                              CAMERON COLE                        WORKS LOCATION:                 31 BOTTLEBRUSH AVE – NOOSA HEADS
                                                POSITION:                                    PROJECT MANAGER                     NEAREST SIDE STREETS:           BERRIMA ROW
  TRAFFIC MANAGEMENT DESIGNER:                  CLIENT CONTACT PHONE:                        0407 593 956                        ROAD CONFIGURATION:             TWO WAY
GUY HALLIDAY – TMD CERT. # OP-259               SITE CONTACT:                                STEVE COLE                          ORIGINAL POSTED SPEED:          50Km/H
TRAFFIC MANAGEMENT & PLANNING                   SITE CONTACT PHONE:                          0412 552 971                        WORKSITE SPEED:                 50KM/H
DESIGN DATE: 31/05/2021                         NOMINATED TRAFFIC CONTROL CO:                TBA                                 PROPOSED START DATE:            TBA
REVISION: ORIGINAL DOCUMENT                     NOMINATED TRAFFIC OFFICER:                   TBA                                 DURATION OF WORKS               8 MONTHS
MUTCD: PART 3 – NINTH ISSUE, 2019               N.T.O CONTACT PHONE:                         TBA                                 TGS DIAGRAMS COVERED:           CP-BOTT-TGS1, 1A, 2
CLAUSE 1.5 – MUTCD – RESPONSIBILITY FOR SAFETY AT WORK SITES:
Organisations and individuals responsible for works in accordance with this Part of the Manual need to be aware of their responsibilities for any injury to road users or damage to property as a result of such operations.
There is an equally important obligation to provide a safe workplace environment that minimises, as far as practicable, the likelihood of injury to workers by traffic within or adjacent to the work area.
Principals and contractors need to be aware of the requirements of OHS legislation and implement them as they apply to this obligation.
Supervisory personnel carrying out construction, maintenance or other works that require the use of a Traffic Guidance Scheme shall give attention to the following:
a) Be mindful of their responsibility to provide, as far as practicable, a safe workplace for personnel and plant under their control, and safe and convenient travelling conditions for road users.
b) Ensure that personnel under their control are, at all times, courteous to road users. Personnel should not allow themselves to become distracted by provocation from members of the public.
c) Ensure that personnel are competent to perform the roadwork signing task (See Clause 1.4.3).
d) Ensure that all personnel at a work site are aware of their responsibilities.
e) Ensure that Traffic Controllers are appropriately trained and informed of their duties and that they are regularly relieved from their duty (see Clause 4.10.5).
f) Be familiar with, and act, as far as is practicable, in accordance with the provisions of this Part of the Manual.
                           SITE LOCATION OVERVIEW MAP

                                                                                                                         • Setting out and recovery of devices
                                                                                                                            Existing signs and traffic control devices which are inappropriate to, or conflict
                                                                                                                            with, the temporary worksite situation shall be fully covered or removed.
                                                                                                                           Before work commences, signs and devices at the approaches to and within the
                                                                                                                           work area should be set out in accordance with the traffic guidance scheme in the
                                                                                                                           following sequence:
                                                                                                                           (a) Advance warning and regulatory signs (including temporary speed zone signs).
                                                                                                                           (b) All intermediate advance warning and regulatory signs and devices required in
                                                                                                                               advance of the taper or start of the work area.
                                                                                                                          (c) All delineating devices required to form the taper including the illuminated
                                                                                                                              flashing arrow sign at the end of the taper where required.
                                                                                                                          (d) Delineation of the work area or side-track.
                                                                                                                          (e) All other required warning and regulatory signs including termination and end of
                                                                                                                              temporary speed zone signs.

                                                                                                                        • Defining and protecting the work area
                                                                                                                          The travelled path on the approaches and past the work area shall be delineated
                                                                                                                          so as to properly define which part of the roadway is available to road users, or the
                                                                                                                          path that traffic is required to follow, under all reasonably expected weather and
                                                                                                                          atmospheric conditions, day or night as applicable.
TGS OVERVIEW
The objective of this document is to provide the client, subcontractors and Traffic                                        Delineating devices (e.g. traffic cones, bollards, post mounted delineators) should
Management personnel carrying out works at this location with a specified                                                  generally be placed 1 m clear of the travelled path where practicable. However,
arrangement for the signing and delineation of construction and maintenance works                                          traffic cones and bollards may also be used to define the edge of the travelled path
which will promote the safety of both workers and the public at the work site.                                             or to separate opposing traffic.

This Traffic Guidance Scheme has been developed based on the brief of information                                          In addition to providing adequate traffic control and guidance at a static work site
provided by the client, as well as a risk assessment of the location and its observed                                      the safety of road users will be enhanced by ensuring that the work site is
and/or interpreted risks and associated hazards. The TGS diagram/s detail the traffic                                      managed in such a way as to cause the minimum amount of inconvenience to
control signs, devices and control measures to be applied at the relevant work sites                                       traffic movement. Works
in order to warn traffic and guide it through, past or around the work area.                                               should be arranged to minimise -
                                                                                                                            (i) disruption of established traffic movements and patterns;
The purpose of this Traffic Guidance Scheme is to ensure the safety of all workers                                          (ii) interference with traffic at peak movement periods;
within the work site, as well as the general public.                                                                        (iii) interference with public transport services; and
                                                                                                                            (iv) the amount of road closed to traffic at any one time.
GENERAL TRAFFIC MANAGEMENT PRINCIPLES
• A TMR certified Traffic Management Implementation (TMI) Officer must implement                                        • Risk management
  (or directly supervise the implementation of) the TGS. Approval for erection or                                         Risk management entails the identification and analysis of all safety risks likely to
  removal of regulatory traffic control devices shall be obtained from the Department                                     arise during works on road including the setting up, operating, changing and
  of Transport and Main Roads or appropriate road authorities before implementing                                         ultimate dismantling of a Traffic Guidance Scheme, followed by the determination
  this Traffic Guidance Scheme.                                                                                           of appropriate measures to mitigate those risks. The process is appropriate at all
                                                                                                                          levels of planning and operation. In each case the process should be carried out
• Risk management - Risk management entails the identification and analysis of all                                        by first identifying all the hazards likely to arise, evaluating them in terms of
  safety risks likely to arise during works on road including the setting up, operating,                                  likelihood of occurrence and adverse consequences using historical data,
  changing and ultimate dismantling of a Traffic Guidance Scheme, followed by the                                         experience or other means. The proposed procedural statement or Traffic
  determination of appropriate measures to mitigate those risks. The process is                                           Guidance Scheme should then be checked in detail to ensure that adequate
  appropriate at all levels of planning and operation. In each case the process                                           means of controlling or reducing those risks found to be significant, are in place.
  should be carried out by first identifying all the hazards likely to arise, evaluating
  them in terms of likelihood of occurrence and adverse consequences using                                              • Traffic Controllers
  historical data, experience or other means. The proposed Traffic Guidance                                               The regulation provides that the function of a traffic controller is to direct traffic in a
  Scheme should then be checked in detail to ensure that adequate means of                                                way stated in the MUTCD and the TCASAP.
  controlling or reducing those risks found to be significant, are in place.
                                                                                                                           Traffic controllers shall be relieved from their duty after not more than 2 hours for a
• Positioning of devices                                                                                                   period of rest or “other duties” of at least 15 minutes. [NOTE: “Other duties” does
  Signs and devices should be positioned and erected so that–                                                              not include operation of a STOP/SLOW bat to control traffic or any duties involving
  a) they are properly displayed and securely mounted (see Clause 3.3 - MUTCD);                                            standing in one position or controlling traffic with a traffic control device].
  b) they are within the line of sight of the intended road user;
  c) they cannot be obscured from view (for example, by vegetation or parked cars);                                        Approach speeds to locations where Traffic Controllers are operating shall be
  d) they do not obscure other devices from the line of sight of the intended road                                         controlled to 60 km/h or less by means of appropriate devices and advance signs
      user;                                                                                                                including a temporary speed zone.
  e) they do not become a possible hazard to workers, pedestrians, or vehicles;
  f) they do not deflect traffic into an undesirable path;                                                                 Traffic controllers must ensure that they have a clear escape path to a non-traffic
  g) they do not restrict sight distance for drivers entering from side roads or streets,                                 (closed) section of the roadway, shoulder, footpath or median. Traffic controllers
      or private driveways; and                                                                                            must stand facing the traffic but just outside the projected travel path. A traffic
  h) they are not installed using supports that could be a hazard if struck by a                                           controller must ensure that they are not partially hidden by signs and/or devices
  vehicle.                                                                                                                 and they do not obstruct a driver's view of such signs and/or devices. Traffic
                                                                                                                           controllers shall also be provided, if necessary, to control the movement of plant
                                                                                                                           and / or pedestrians through, past or within the trafficable area.



                                                                                                                                                                                                                               1

Log in to download the original (Traffic Management Plan.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 7 pages

Page 2

 • Signs warning of works personnel
   The Workers (symbolic) sign is used to give warning of personnel engaged in                    • Provision for pedestrians and bicycles
   works on or adjacent to the travelled path as specified in Clause 4.7.2(a). As this              Where pedestrians, including school children and people with disabilities or visual
   sign is used to warn of the presence of personnel, it shall only be displayed when               impairment, have to move through, past or around a work site or to cross the road
   they are actually working, or are visible to traffic, or both, and shall be removed or           within a work site, they shall be provided with and directed to suitably constructed
   covered when workers have left the work area or are no longer visible to traffic.                and protected temporary footpaths and crossing points, or formal pedestrian
                                                                                                    crossings, or refuges if warranted. Pedestrian and bicycle paths should, where
   The Traffic Controller Ahead / PREPARE TO STOP sign shall be used to give                        practicable, be provided on the same scale and to the same width as any facilities
   advance warning where traffic may be required to stop in compliance with the                     for pedestrian or bicycle traffic that were existing prior to the works. If this is not
   directions of a Traffic Controller. The sign shall be installed 2D in advance of the             practicable, such facilities shall meet the requirements of Clause 2.3.8. – MUTCD
   traffic control position where D is the greater value of the range of dimension given             – 2019.
   in Table 4.2. This should also be the sight distance from the traffic controller to
   oncoming traffic. The sign shall not be displayed when the Traffic Controller is not
   actually in attendance controlling traffic.



 Traffic Guidance Scheme and Traffic Management Options Analysis
 Option        Description                  Closure Type         Control              Features                                                                TGS Reference
                                                                 Measure
 Around        Vehicles Detoured            Full                 Elimination/         Full width of road closed. Detour available with minimum delay          NOT
 Work          around existing              Closure/Detour       Substitution
                                                                                                                                                              SELECTED
 Zone          roadway/ Side-tracked
 Past          Vehicles past                Part Road            Isolation /          Remaining lane width of 3.0m per lane can be maintained on              NOT
 Work          delineated work zone         Closure /            Engineering /        low speed residential roads
                                                                                                                                                              SELECTED
 Zone                                       Lateral Shift        Administrative

                                            Shoulder / Bus       Isolation /          Remaining lane width of 3.0m can be maintained                          SELECTED
                                            Lane / Parking       Engineering /                                                                                CP-BOTT-TGS1, 1A
                                            Lane Closure         Administrative
                                            Contra - Flow        Isolation /          Where a multi-lane divided road can be utilised to run                  NOT
                                                                 Engineering /        opposing lanes of traffic on one side. Remaining lane width of
                                                                                                                                                              SELECTED
                                                                 Administrative       3.0m per lane can be maintained.
                                            Lane / Turning       Isolation /          Remaining lane width of 3.0m can be maintained on low speed             NOT
                                            Lane Closure         Engineering /        residential roads
                                                                                                                                                              SELECTED
                                                                 Administrative
                                            Single Lane          Isolation/           Where two – way traffic cannot be maintained as per above on            SELECTED
                                            reversible Flow      Engineering/         two-way road. Remaining width of 3.0m with 0.5m edge                    CP-BOTT-TGS2
                                                                 Administrative       clearance shall be maintained to allow for single file of traffic
                                                                                      past work area
                                            Temporary            Isolation/           Traffic Controller/s may be required to hold traffic in one or          NOT
                                            closure / work       Engineering/         both directions briefly to allow for work vehicle ingress / egress
                                                                                                                                                              SELECTED
                                            vehicle access       Administrative
 Through       Vehicles through             Temporary road       Isolation /          Hold and Release all traffic when safe to do so.                        NOT
 Work          Work Zone                    closure/ Hold        Engineering /
                                                                                                                                                              SELECTED
 Zone                                       and Release          Administrative

                                            Local Traffic        Isolation /          Locations where road features restrict implementation of                NOT
                                            Access               Engineering /        above options
                                                                                                                                                              SELECTED
                                                                 Administrative
 Warning       Pre-warning signage          N/A                  Signage              MUTCD approved and custom signage as required placed as a               NOT
 Signage       only                                                                   warning to both vehicles and pedestrians
                                                                                                                                                              SELECTED



 Pedestrian Management
 Option                                                            Description                                                   TGS Reference
 Around Work Zone                                                  Pedestrians diverted around work area (usually to             NOT SELECTED
                                                                   footpath on other side of road) utilising existing
                                                                   crossing and/ or driveway
 Past Work Zone                                                    Minimum 1.0m footway maintained past work area                NOT SELECTED
                                                                   (on the verge or on the roadway) with appropriate
                                                                   delineation and protections in accordance with the
                                                                   MUTCD
 Through Work Zone                                            Minimum 1.0m footway maintained through the work NOT SELECTED
                                                              zone such that pedestrians are safely managed either
                                                              under traffic control (e.g. Passage through /between
                                                              work area and parked work vehicle, or a designated,
                                                              delineated walkway through the development area
                                                              but away from specific work areas.
Note: The pedestrian footpath is on the opposite side of the footpath to the worksite and pedestrian movement will be unaffected by the works




                                                                                                                                                                                          2

Page 3

                    REFERENCE TABLES FOR VARIOUS PURPOSES WITH ADOPTED CRITERIA
                              FOR THIS WORKSITE HIGHLIGHTED IN YELLOW

                           Table 4.2 – Value of D                                  TABLE 3.7 - RECOMMENDED MAX SPACING OF CONES AND BOLLARDS
        Posted speed in km/h                      Dimension D (m)                  Purpose and usage        Speed limit (km/h)        Recommended
         (prior to roadworks)                                                                                                         maximum spacing
               40 or less                              5 to 10                                                                        (m)
                   50                                 10 to 15                     All purposes             <50                       4
                   60                                 15 to 45                     Closure                  >70                       12
                 70, 80                               60 to 80                     Taper                    >70                       9
                90, 100                              90 to 100
                  110                               100 to 120                    TABLE 4.1 - WORKS PROTECTION METHODS
                                                                                  Works         Applicable Tasks             MUTCD         ADOPTED
                                                                                  Method                                     Ref           METHOD
                                                                                  Static        All works which are          Clause
                 Recommended taper lengths (Table 4.6)                            work site     greater in scope and         4.2
Permanent                     Recommended taper lengths (m)                                     duration than can be
posted speed     Traffic Control at Lateral shift    Merge taper                                handled by the short                       ADOPTED
(km/h)           beginning of taper taper                                                       term, low impact
  40 or less              15               5                 15                                 provisions listed below or
       50                 15              15                 30                                 mobile works
       60                 30              30                 60                   Short         Isolated work on             Clause
       70                 30           60 - 80            120 - 160               term, low     pavements of up to 5 min     4.3
       80                 30           60 - 80            120 - 160               impact        duration, traffic volumes                    NOT
       90                 30           60 - 80            120 - 160               works –       permitting. Shoulder                       ADOPTED
                                                                                  open road     grading and verge
      100                 30           60 - 80            120 - 160
                                                                                  areas         mowing
  > than 100              30           60 - 80            120 - 160
                                                                                  Short         Work adjacent to or in a     Clause
                                                                                  term, low     traffic lane of duration 5   4.4
                                                                                  impact        min to work 1 hour
                                                                                  works –       depending on traffic                         NOT
                                                                                  built up      volume. Median and                         ADOPTED
                                                                                  areas         verge mowing, footpath
                     Table 4.11 - Minimum Lane Widths                                           works
                                                                                  Works on      Maintenance grading.         Clause          NOT
Posted speed limit during road works     Minimum lane widths (m)
                                                                                  unsealed      Short term partial road      4.5           ADOPTED
(km/h)
                                                                                  roads         closures
               60 or less                             3.0
                                                                                  Mobile        Line marking, pavement       Clause
                70 to 90                              3.2
                                                                                  Works         marker laying or removal,    4.6
           Greater than 90                            3.4
                                                                                                pavement testing where
                                                                                                all signs and other                          NOT
                                                                                                protective devices are                     ADOPTED
TABLE 4.7 - GUIDE TO THE SELECTION OF ROADWORKS SPEED LIMITS                                    carried on vehicles
40Km/H       Worker safety – Workers on foot are working within 1.2m of
                                traffic with no intervening physical protection
             Traffic Safety – There would be structural danger to bridges at
                              higher speeds (1km maximum length)
60Km/H       Workers Safety – Workers on foot or operating plant are within
                                 3m of the trafficable area with no intervening
                                 physical barrier
                   -     A traffic controller is being used in advance of
                         portable or temporary traffic signals
                   -     Dust or smoke may reduce visibility
             Traffic Safety – Traffic is subjected to a reduced standard
                              alignment due to the works
                   -     The pavement surface has been degraded
                   -     A bituminous seal has just been laid




                                                                                                                                                        3

Page 4

                                   EXAMPLES OF CORRECT SIGNAGE MOUNTING

                                          FOR SIGNAGE PLACEMENT, LONG TERM
                                       GENERALLY MEANS LONGER THAN TWO WEEKS.




                                         LONG TERM PLACEMENT ON POSTS

                                             •    ON KERBED ROADS IN BUILT UP AREAS ADJACENT TO FOOTPATHS
                                                  OR WHERE VEHICLE PARKING MAY OCCUR, THEY SHOULD BE
                                                  ERECTED A MINIMUM OF 2.2m MIN FROM LEVEL OF KERB OR
                                                  FOOTPATH TO UNDERSIDE OF SIGN.
                                             •    SIGNS SHOULD BE PLACED SO THAT THEY ARE PROMINENTLY
                                                  DISPLAYED TO TRAFFIC AND WILL COMMAND ATTENTION.
                                             •    SIGNS SHOULD BE PLACED AT LEAST 2m CLEAR OF THE TRAVELLED
                                                  PATH WHERE PRACTICABLE.




                                         LONG TERM PLACEMENT ON POSTS

                                             •    WHERE NEITHER PEDESTRIANS OR PARKED VEHICLES HAVE TO BE
                                                  CONSIDERED, A MOUNTING HEIGHT OF 1.5m MIN FROM LEVEL OF
                                                  SHOULDER SURFACE TO UNDERSIDE OF SIGN MAY BE MORE
                                                  APPROPRIATE, E.G MEDIANS, ISLANDS, OPEN ROAD AREAS ETC.
                                             •    SIGNS SHOULD BE PLACED SO THAT THEY ARE PROMINENTLY
                                                  DISPLAYED TO TRAFFIC AND WILL COMMAND ATTENTION.
                                             •    SIGNS SHOULD BE PLACED AT LEAST 2m CLEAR OF THE TRAVELLED
                                                  PATH WHERE PRACTICABLE.




                                          SHORT TERM PLACEMENT OF SIGNS

                                              •   SIGNS MOUNTED ON PORTABLE SUPPORTS (LEGS) SHOULD BE A
                                                  MINIMUM HEIGHT OF 200mm FROM THE SHOULDER SURFACE TO
                                                  THE BOTTOM EDGE OF THE SIGN.
                                              •   SHORT TERM SIGNS SHOULD BE PLACED SO THAT THEY ARE
                                                  PROMINENTLY DISPLAYED TO TRAFFIC AND WILL COMMAND
                                                  ATTENTION.
                                              •   IN BUILT UP AREAS, SIGNS SHOULD BE PLACED BEHIND THE KERB
                                                  IF VISIBLE TO ONCOMING TRAFFIC. IF SIGNS HAVE TO BE PLACED
                                                  ON THE PAVEMENT, THEY SHOULD BE PLACED AS NEAR AS
                                                  PRACTICABLE TO THE KERB WITHOUT BECOMING OBSCURED OR
                                                  OBSTRUCTING MOVING TRAFFIC.
                                              •   SIGNS ARE NOT PERMITTED TO BE PLACED IN OR OBSTRUCT
                                                  BICYCLE LANES UNDER ANY CIRCUMSTANCES
                                              •   IF SIGNS ARE PLACED ADJACENT TO OR PARTLY ON A FOOTPATH,
                                                  A TRAFFIC CONE OR BOLLARD SHOULD BE PLACED AGAINST THE
                                                  SIGN TO WARN PEDESTRIANS AND CYCLISTS OF ITS PRESENCE.
                                              •   SIGNS MAY NEED TO BE WEIGHTED DOWN WITH SAND BAGS IN
                                                  WINDY CONDITIONS OR OVERNIGHT TO ENSURE STABILITY.




Note: In all cases,

    1. Traffic Management signage may only be placed in position by a person who holds a Traffic Management
       Implementation (TMI) qualification.
    2. Implementation of signs should be done in accordance with a Traffic Guidance Scheme designed by a Traffic
       Management Design qualified person.
    3. Any changes to a Traffic Guidance Scheme may only be authorised by a Traffic Management Design qualified
       person.

                                                                                                                   4

Page 5

                                                     GENERAL TRAFFIC GUIDANCE SCHEME NOTES
1. Traffic Guidance Schemes attached herewith have been drawn based on the principles of the current issue of the MUTCD Pt. 3 "Works on Roads” (November 2019).
2. All signage to be placed, based on an onsite risk assessment in accordance with clause 2.2.3 of the MUTCD Part 3, at the time of installation.
3. The Principal Contractor (PC) / PCBU is responsible for ensuring all works are conducted in accordance with relevant legislation.
4. A site pre-start should be undertaken prior to starting to ensure consultation with all workers understand the work activities and details of the TGS.
5. Signs and devices shall be set out and placed by a Traffic Management Implementation (TMI) qualified person.
6. Setting out of signs and devices should be done in the following sequence and removed in reverse order (Clause 2.5.3):
    a) Advanced warning and regulatory signs (including temporary speed zone signs)
    b) All intermediate advance warning and regulatory signs and devices required in advance of the taper or start of work area.
    c) All delineating devices required to form taper including the illuminated flashing arrow sign at the end of the taper where required.
    d) Delineation of the work area or side-track.
    e) All other required warning and regulatory signs including termination and end of temporary speed zone signs.
7. It is the responsibility of the Principal Contractor (PC) / PCBU, to ensure, all signage is checked regularly, once installed. (Appendix A-A2)
8. Due consideration is to be to be given to all road users at all times, including but not limited to motorists, cyclists and pedestrians.
9. Signs that are inappropriate to, or conflict with, the worksite situation shall be covered or removed. This might include conflicting speed signs during working hours,
   or “Workman” symbolic and/or Traffic Controller Ahead signs when workers are not present, or Traffic Controllers are not operating.
10. Signage and devices to not be placed as to obstruct vehicles or pedestrians (usually 1m from any running lane), but clause 4.13.4 of the MUTCD should be observed
    in all situations.
11. Changes to the signage arrangements, as documented here, are to be recorded as per the requirements of the MUTCD Pt. 3 Clause 2.6.2
12. Placement of signage will need to consider any existing signage and other obstacles such as buildings, street furniture and vegetation at the location.
13. Signage / device placement must be assessed on site and adjusted within tolerances allowed if necessary. (Clause 4.1.6).
14. Where no distance for sign placement are given, a literal interpretation is required, based on an onsite risk assessment.
15. Diagrams drawn are not to scale and locations shown are indicative only.
13. Short term signage (usually up to 2 weeks) may be mounted at a minimum of 200mm above road / kerb surface level.
     Long term signage should be mounted on fixed supports (posts). On kerbed roads in built-up areas where signs are mounted on posts adjacent to a footpath, or
     where vehicle parking may occur, they should be erected a minimum of 2.2 m above the level of the kerb or footpath to the underside of the sign, to reduce
     interference from parked vehicles. Where neither pedestrians nor parked vehicles have to be considered, for example, on a traffic island or median, a mounting
     height of 1.5 m may be more appropriate. (See clause 2.5.2 of MUTCD).
14. Minimum lane widths in accordance with table 4.11 and edge clearances will be maintained at all times.
15. Cone or bollard spacing should be done in accordance with table 3.7 of the MUTCD.
16. Where signage cannot be placed on the left side of the road as indicated in the diagrams, it may be placed on the right-hand side (or median).
17. Plant, vehicles and materials are not to be stored in positions where they may create a hazard, obscure signage or block the line of sight for approaching drivers /
     cyclists.
18. Any changes to the TGS (Outside the scope of TMI Table 1.4.31 Supplement MUTCD Part 3) shall be reported to a TMD officer for approval prior to changes being made.
19. Clearances for excavation works adjacent to running lane to be delineated in accordance with table E1 in the MUTCD Part 3.
20. All incidents/ accidents within the site area to be dealt with in accordance with the site safety plan.

Notes below on Traffic Controllers apply when Traffic Controllers have been contracted:
21. Traffic Controllers must conduct their operational procedures in accordance with the TCASAP.
22. Traffic Controllers must be clothed in accordance with the DTMR – Queensland Traffic Controller Clothing Standard.
23. Traffic Controllers shall be relieved from their duty after not more than 2 hours for a period of rest or other duties of at least 15 minutes (TCASAP).
24. Traffic Controllers should always have an escape route to a safe location established prior to starting work.
25. Traffic controllers should follow the guidelines for daily routines (Appendices A2 & A3 of MUTCD Part 3).




Traffic Management & Planning Disclaimer

The following Traffic Guidance Schemes have been prepared in accordance with information supplied by the client and/or onsite visits. Technical due
diligence has been applied in the production of these documents based on that information supplied. The “Traffic Management Design professional /
consultant”, and Traffic Management & Planning is not responsible for any omissions or errors in the base information supplied by the client.

While all care has been taken in the preparation of these documents, traffic and site conditions at the time of the works may vary from those established
in the development of the Traffic Guidance Schemes. The “client” is responsible for undertaking an evaluation of the site and traffic conditions against
the application constraints outlined within the Traffic Guidance Schemes as appropriate. Where conditions vary from those documented, additional
input from a Traffic Management Design professional should be sought.




                                                                                                                                                                        5

Page 6

                                                                                                                                                                                                                                                                                           www.invarion.com

                                                                               COLE PROJECTS ­ RESIDENTIAL DEVELOPMENT ­ 31 BOTTLEBRUSH AVE ­ NOOSA HEADS
                    N                                                                          SHOULDER CLOSURE & GENERAL WORKS SIGNAGE
            TGS #:CP­BOTT­TGS1
                                                                                                                                      FOR POSTED SPEED OF 50Km/H ­ D = 10 ­ 15m
  FOR USE DURING
  WORKING HOURS


                                                                                                              FUTURE TRAFFIC




                                                                                                                                                                                                                                              BE
                                                                                                             CONTROLLER SIGN




                                                                                                                                                                                                                                                      RR
                                                                                                                                                                            MATERIALS DELIVERY AREA




                                                                                                                                                                                                                                                             IM
                                                                                                                                                                                                                                                              A
                                                                                                                                                                                                                                                               RO
                                                                                                                                                                                                                                                                 W
                                                                                                                                          NEIGHBOR
                                                                                                                                          DRIVEWAY



                                                                                                                                                 FOOTPATH                   FOOTPATH        NEIGHBOR
                                                                                                                                                  CLOSED                     CLOSED         DRIVEWAY
                                                                                     DO NOT OVERTAKE
                     REDUCE SPEED




                                                                                                                                                                                                                                              DRIVE SAFELY
                                    AHEAD
                                    WORK
                                    ROAD




                                                                                                       PREPARE




                                                                                                                                                                                                                                                             WORK
                                                                                                        STOP




                                                                                                                                                                                                                                                             ROAD
                                                                                                                                                                                                                                                             END
                                                                                                         TO




                                                                  30m                                                15m                 15m
                                                             BOTTLEBRUSH AVE


                                                                                                                                                                                15m                     15m
                                                                                                                                                                                                                                                   30m




                                                                                                                                                                                                                  PREPARE



                                                                                                                                                                                                                            DO NOT OVERTAKE
                          WORK

                                       DRIVE SAFELY
                          ROAD




                                                                                                                                                                                                                   STOP
                           END




                                                                                                                                                                                                                    TO




                                                                                                                                                                                                                                                                                                           REDUCE SPEED
                                                                                                                                                                                                                                                                                                   AHEAD
                                                                                                                                                                                                                                                                                                   WORK
                                                                                                                                                                                                                                                                                                   ROAD
                                                                                                                                                                                                               FUTURE TRAFFIC
                                                                                                                                                                                                              CONTROLLER SIGN




                                    LEGEND                               TGS SPECIFIC NOTES
                                                                         1). THIS ARRANGEMENT IS DEVELOPED IN ACCORDANCE WITH CLAUSE 4.2 (STATIC WORK SITES) OF THE MUTCD ­ 2019
                   = WORK AREA                                           2). SIGNS THAT ARE INAPPROPRIATE TO, OR CONFLICT WITH, THE WORKSITE SITUATION SHALL BE COVERED OR REMOVED. (REF. CLAUSE 2.4.4 ­ MUTCD ­ 2019)
                   = BOLLARDS OR 700mm CONES                             3). ON KERBED ROADS IN BUILT UP AREAS, SIGNS MOUNTED ON POSTS SHOULD BE ERECTED A MINIMUM OF 2.2m ABOVE KERB OR FOOTPATH TO THE BOTTOM IF THE SIGN. (REF. CLAUSE 2.5.2 – MUTCD – 2019).
                                                                         4). ALL SIGNS TO BE MOUNTED IN PROMINENT POSITIONS WITH CLEAR LINE OF SIGHT TO ONCOMING TRAFFIC. (REF. CLAUSE 2.5.2 ­ MUTCD ­ 2019).
                   = SIGN PLACEMENT POSITION                             5). WORK VEHICLES AND TRUCKS ARE NOT PERMITTED TO STOP AND/OR REVERSE ON PUBLIC ROADS WITHOUT TRAFFIC CONTROL. A SPOTTER SHOULD BE USED TO ASSIST WORK VEHICLES TO ENTER THE
                   = EXISTING FOOTPATH                                       DELINEATED SHOULDER AREA.
                                                                         6). WORKMAN (SYMBOLIC) SIGNS TO BE COVERED WHEN WORKERS HAVE LEFT THE AREA OR ARE NO LONGER VISIBLE TO TRAFFIC.(REF. CLAUSE 3.4.4 ­ MUTCD).
                   = TEMP. HAZARD MARKER                                 7). THE TRUCKS SIGNS SHOULD ONLY BE DISPLAYED WHEN THE NEED EXISTS AND SHOULD BE COVERED WHEN TRUCK ACTIVITY HAS CEASED. (REF. CLAUSE 3.16.2 ­ MUTCD).
                                                                         8). 3m MIN LANE WIDTH REQUIRED FOR ALL OPEN TRAFFIC LANES AT ALL TIMES. (REF. CLAUSE 4.13.3 ­ MUTCD ­ 2019).
                   = SIGN COVER                                          9). FOR ADDITIONAL NOTES RELATING TO THIS TGS PLEASE REFER TO THE GENERAL TRAFFIC GUIDANCE SCHEME NOTES SUPPLIED WITH THE ORGINAL TGS DIAGRAMS FOR THIS JOB.


             REV    DATE                                         DESCRIPTION    CLIENT:                                        COLE PROJECTS                   IMPLEMENTATION DATE:         TBA                                                                                  DIAGRAM PREPARED BY:
                                                                                                                                                                                                                                                                                     GUY HALLIDAY
              00   31/05/21                           PRODUCED FOR CONSTRUCTION LOCATION:                                      31 BOTTLEBRUSH AVE ­ NOOSA      HOURS OF OPERATION:          0630­1800
REVISIONS




                                                                                                                                                                                                                                                                    Dept. Transport & Main Roads
                                                                                                                                                                                                                                                                     Traffic Management Design
              01                                                                   PLAN NUMBER:                                CP­BOTT­TGS1                    TRAFFIC MANAGEMENT:          REGULATORY                                                                    Certification # 259

              02                                                                   SCALE / PRINT SIZE:                         NOT TO SCALE      PRINT TO A3   CONTROL METHOD:              SHOULDER CLOSURE
              03                                                                    SITE CONTACT:                              STEVEN COLE ­ 0412 552 971      TERM OF WORKS:               LONG
              04                                                                    TRAFFIC CONTROL Co. TBA                                                    ORIGINAL POSTED SPEED:       50 Km/h                         MINIMUM LANE WIDTH:                      3.0m
PROJECT CAMERON COLE ­ 0407 593 956                                                 NTO CONTACT:       TBA                                                     WORKSITE SPEED LIMIT:        50 Km/h                         VALUE OF D:                              TABLE 4.2 (MUTCD)
MANAGER                                                                             DURATION OF WORKS: 8 MONTHS                                                ROAD TYPE:                   TWO WAY                         TAPER LENGTH:                            TABLE 4.6 (MUTCD)

Page 7

                                                                                                                                                                                                                                                                                           www.invarion.com

                                                                              COLE PROJECTS ­ RESIDENTIAL DEVELOPMENT ­ 31 BOTTLEBRUSH AVE ­ NOOSA HEADS
                   N                                                                          SHOULDER CLOSURE & GENERAL WORKS SIGNAGE
     TGS #:CP­BOTT­TGS1A
                                                                                                                                      FOR POSTED SPEED OF 50Km/H ­ D = 10 ­ 15m
  FOR USE AFTER
  WORKING HOURS


                                                                                                             FUTURE TRAFFIC




                                                                                                                                                                                                                                              BE
                                                                                                            CONTROLLER SIGN




                                                                                                                                                                                                                                                      RR
                                                                                                                                                                             MATERIALS DELIVERY AREA




                                                                                                                                                                                                                                                             IM
                                                                                                                                                                                                                                                              A
                                                                                                                                                                                                                                                               RO
                                                                                                                                                                                                                                                                 W
                                                                                                                                          NEIGHBOR
                                                                                                                                          DRIVEWAY



                                                                                                                                                 FOOTPATH                   FOOTPATH         NEIGHBOR
                                                                                                                                                  CLOSED                     CLOSED          DRIVEWAY
                                                                                    DO NOT OVERTAKE
                    REDUCE SPEED




                                                                                                                                                                                                                                              DRIVE SAFELY
                                   AHEAD
                                   WORK
                                   ROAD




                                                                                                      PREPARE




                                                                                                                                                                                                                                                             WORK
                                                                                                       STOP




                                                                                                                                                                                                                                                             ROAD
                                                                                                                                                                                                                                                             END
                                                                                                        TO




                                                                 30m                                                15m                  15m
                                                            BOTTLEBRUSH AVE


                                                                                                                                                                                15m                     15m
                                                                                                                                                                                                                                               30m




                                                                                                                                                                                                                  PREPARE



                                                                                                                                                                                                                            DO NOT OVERTAKE
                         WORK

                                      DRIVE SAFELY
                         ROAD




                                                                                                                                                                                                                   STOP
                          END




                                                                                                                                                                                                                    TO




                                                                                                                                                                                                                                                                                                           REDUCE SPEED
                                                                                                                                                                                                                                                                                                   AHEAD
                                                                                                                                                                                                                                                                                                   WORK
                                                                                                                                                                                                                                                                                                   ROAD
                                                                                                                                                                                                               FUTURE TRAFFIC
                                                                                                                                                                                                              CONTROLLER SIGN




                                   LEGEND                               TGS SPECIFIC NOTES
                                                                        1). THIS ARRANGEMENT IS DEVELOPED IN ACCORDANCE WITH CLAUSE 4.2 (STATIC WORK SITES) OF THE MUTCD ­ 2019
                  = WORK AREA                                           2). SIGNS THAT ARE INAPPROPRIATE TO, OR CONFLICT WITH, THE WORKSITE SITUATION SHALL BE COVERED OR REMOVED. (REF. CLAUSE 2.4.4 ­ MUTCD ­ 2019)
                  = BOLLARDS OR 700mm CONES                             3). ON KERBED ROADS IN BUILT UP AREAS, SIGNS MOUNTED ON POSTS SHOULD BE ERECTED A MINIMUM OF 2.2m ABOVE KERB OR FOOTPATH TO THE BOTTOM IF THE SIGN. (REF. CLAUSE 2.5.2 – MUTCD – 2019).
                                                                        4). ALL SIGNS TO BE MOUNTED IN PROMINENT POSITIONS WITH CLEAR LINE OF SIGHT TO ONCOMING TRAFFIC. (REF. CLAUSE 2.5.2 ­ MUTCD ­ 2019).
                  = SIGN PLACEMENT POSITION                             5). WORK VEHICLES AND TRUCKS ARE NOT PERMITTED TO STOP AND/OR REVERSE ON PUBLIC ROADS WITHOUT TRAFFIC CONTROL. A SPOTTER SHOULD BE USED TO ASSIST WORK VEHICLES TO ENTER THE
                  = EXISTING FOOTPATH                                       DELINEATED SHOULDER AREA.
                                                                        6). WORKMAN (SYMBOLIC) SIGNS TO BE COVERED WHEN WORKERS HAVE LEFT THE AREA OR ARE NO LONGER VISIBLE TO TRAFFIC.(REF. CLAUSE 3.4.4 ­ MUTCD).
                  = TEMP. HAZARD MARKER                                 7). THE TRUCKS SIGNS SHOULD ONLY BE DISPLAYED WHEN THE NEED EXISTS AND SHOULD BE COVERED WHEN TRUCK ACTIVITY HAS CEASED. (REF. CLAUSE 3.16.2 ­ MUTCD).
                                                                        8). 3m MIN LANE WIDTH REQUIRED FOR ALL OPEN TRAFFIC LANES AT ALL TIMES. (REF. CLAUSE 4.13.3 ­ MUTCD ­ 2019).
                  = SIGN COVER                                          9). FOR ADDITIONAL NOTES RELATING TO THIS TGS PLEASE REFER TO THE GENERAL TRAFFIC GUIDANCE SCHEME NOTES SUPPLIED WITH THE ORGINAL TGS DIAGRAMS FOR THIS JOB.


            REV    DATE                                         DESCRIPTION       CLIENT:                                     COLE PROJECTS                 IMPLEMENTATION DATE:       TBA                                                                                       DIAGRAM PREPARED BY:
                                                                                                                                                                                                                                                                                     GUY HALLIDAY
             00   31/05/21                           PRODUCED FOR CONSTRUCTION LOCATION:                                      31 BOTTLEBRUSH AVE ­ NOOSA    HOURS OF OPERATION:        OUTSIDE WORKING HOURS
REVISIONS




                                                                                                                                                                                                                                                                    Dept. Transport & Main Roads
                                                                                                                                                                                                                                                                     Traffic Management Design
             01                                                                   PLAN NUMBER:                                CP­BOTT­TGS1A                 TRAFFIC MANAGEMENT:        REGULATORY                                                                         Certification # 259

            02                                                                    SCALE / PRINT SIZE:                         NOT TO SCALE     PRINT TO A3 CONTROL METHOD:             SHOULDER CLOSURE
            03                                                                    SITE CONTACT:                               STEVEN COLE ­ 0412 552 971    TERM OF WORKS:         LONG
            04                                                                    TRAFFIC CONTROL Co. TBA                                                   ORIGINAL POSTED SPEED: 50 Km/h                                  MINIMUM LANE WIDTH:                      3.0m
PROJECT CAMERON COLE ­ 0407 593 956                                               NTO CONTACT:       TBA                                                    WORKSITE SPEED LIMIT:      50 Km/h                              VALUE OF D:                              TABLE 4.2 (MUTCD)
MANAGER                                                                           DURATION OF WORKS: 8 MONTHS                                               ROAD TYPE:                 TWO WAY ­ RESIDENTIAL                TAPER LENGTH:                            TABLE 4.6 (MUTCD)

Page 8

                                                                                                                                                                                                                                                                                              www.invarion.com

                                                                               COLE PROJECTS ­ RESIDENTIAL DEVELOPMENT ­ 31 BOTTLEBRUSH AVE ­ NOOSA HEADS
                    N                                                                                LANE CLOSURE WITH SHUTTLE FLOW
            TGS #:CP­BOTT­TGS2
                                                                                                                              FOR POSTED SPEED OF 50Km/H ­ D = 10 ­ 15m
  FOR USE DURING
  WORKING HOURS




                                                                                                                                                                                                                                                 BE
                                                                                                                                                                                                                                                         RR
                                                                                                                                                                                       3m MINIMUM ROAD WIDTH




                                                                                                                                                                                                                                                                IM
                                                                                                                                                                                                                                                                 A
                                                                                                                                                                                                                                                                  RO
                                                                                                                                                                                                                                                                    W
                                                                                                                                  NEIGHBOR
                                                                                                                                  DRIVEWAY



                                                                                                                                           FOOTPATH                              FOOTPATH        NEIGHBOR
                                                                                                                                            CLOSED                                CLOSED
                                                                                                                                15m                                                              DRIVEWAY
                                                                                     DO NOT OVERTAKE
                     REDUCE SPEED




                                                                                                                                                                                                                                                 DRIVE SAFELY
                                    AHEAD
                                    WORK
                                    ROAD




                                                                                                       PREPARE




                                                                                                                                                                                                                                                                WORK
                                                                                                        STOP




                                                                                                                                                                                                                                                                ROAD
                                                                                                                                                                                                                                                                END
                                                                                                         TO




                                                                                                                                      TC


                                                                  30m                                            15m
                                                             BOTTLEBRUSH AVE                                                                                                TC
                                                                                                                                             15m

                                                                                                                                                                                                               15m
                                                                                                                                                                                     15m                                                              30m




                                                                                                                                                                                                                     PREPARE



                                                                                                                                                                                                                               DO NOT OVERTAKE
                                                                                                                                                    THESE CAR PARKS MAY
                          WORK

                                       DRIVE SAFELY
                          ROAD




                                                                                                                                                                                                                      STOP
                           END




                                                                                                                                                                                                                       TO
                                                                                                                                                  NEED TO BE APPROPRIATED




                                                                                                                                                                                                                                                                                                              REDUCE SPEED
                                                                                                                                                                                                                                                                                                      AHEAD
                                                                                                                                                                                                                                                                                                      WORK
                                                                                                                                                                                                                                                                                                      ROAD
                                    LEGEND                               TGS SPECIFIC NOTES
                                                                         1). THIS ARRANGEMENT IS DEVELOPED IN ACCORDANCE WITH CLAUSE 4.2 (STATIC WORK SITES) OF THE MUTCD ­ 2019
                   = WORK AREA                                           2). SIGNS THAT ARE INAPPROPRIATE TO, OR CONFLICT WITH, THE WORKSITE SITUATION SHALL BE COVERED OR REMOVED. (REF. CLAUSE 2.4.4 ­ MUTCD ­ 2019)
                   = BOLLARDS OR 700mm CONES                             3). ON KERBED ROADS IN BUILT UP AREAS, SIGNS MOUNTED ON POSTS SHOULD BE ERECTED A MINIMUM OF 2.2m ABOVE KERB OR FOOTPATH TO THE BOTTOM IF THE SIGN. (REF. CLAUSE 2.5.2 – MUTCD – 2019).
                                                                         4). ALL SIGNS TO BE MOUNTED IN PROMINENT POSITIONS WITH CLEAR LINE OF SIGHT TO ONCOMING TRAFFIC. (REF. CLAUSE 2.5.2 ­ MUTCD ­ 2019).
                   = SIGN PLACEMENT POSITION                             5). WORK VEHICLES AND TRUCKS ARE NOT PERMITTED TO STOP AND/OR REVERSE ON PUBLIC ROADS WITHOUT TRAFFIC CONTROL. A SPOTTER SHOULD BE USED TO ASSIST WORK VEHICLES TO ENTER THE
                   = EXISTING FOOTPATH                                       DELINEATED SHOULDER AREA.
                                                                         6). WORKMAN (SYMBOLIC) SIGNS TO BE COVERED WHEN WORKERS HAVE LEFT THE AREA OR ARE NO LONGER VISIBLE TO TRAFFIC.(REF. CLAUSE 3.4.4 ­ MUTCD).
                   = TEMP. HAZARD MARKER                                 7). THE TRUCKS SIGNS SHOULD ONLY BE DISPLAYED WHEN THE NEED EXISTS AND SHOULD BE COVERED WHEN TRUCK ACTIVITY HAS CEASED. (REF. CLAUSE 3.16.2 ­ MUTCD).
                                                                         8). 3m MIN LANE WIDTH REQUIRED FOR ALL OPEN TRAFFIC LANES AT ALL TIMES. (REF. CLAUSE 4.13.3 ­ MUTCD ­ 2019).
                   = SIGN COVER                                          9). FOR ADDITIONAL NOTES RELATING TO THIS TGS PLEASE REFER TO THE GENERAL TRAFFIC GUIDANCE SCHEME NOTES SUPPLIED WITH THE ORGINAL TGS DIAGRAMS FOR THIS JOB.


             REV    DATE                                         DESCRIPTION    CLIENT:                                COLE PROJECTS                         IMPLEMENTATION DATE:                TBA                                                                                DIAGRAM PREPARED BY:
                                                                                                                                                                                                                                                                                        GUY HALLIDAY
              00   31/05/21                           PRODUCED FOR CONSTRUCTION LOCATION:                              31 BOTTLEBRUSH AVE ­ NOOSA            HOURS OF OPERATION:                 0630­1800
REVISIONS




                                                                                                                                                                                                                                                                       Dept. Transport & Main Roads
                                                                                                                                                                                                                                                                        Traffic Management Design
              01                                                                   PLAN NUMBER:                        CP­BOTT­TGS2                          TRAFFIC MANAGEMENT:                 REGULATORY                                                                  Certification # 259

              02                                                                   SCALE / PRINT SIZE:                 NOT TO SCALE        PRINT TO A3       CONTROL METHOD:                     LANE CLOSURE
              03                                                                    SITE CONTACT:                      STEVEN COLE ­ 0412 552 971            TERM OF WORKS:                      SHORT
              04                                                                    TRAFFIC CONTROL Co. TBA                                                  ORIGINAL POSTED SPEED:              50 Km/h                       MINIMUM LANE WIDTH:                      3.0m
PROJECT CAMERON COLE ­ 0407 593 956                                                 NTO CONTACT:       TBA                                                   WORKSITE SPEED LIMIT:               50 Km/h                       VALUE OF D:                              TABLE 4.2 (MUTCD)
MANAGER                                                                             DURATION OF WORKS: 8 MONTHS                                              ROAD TYPE:                          TWO WAY                       TAPER LENGTH:                            TABLE 4.6 (MUTCD)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.