Traffic Management Plan
Attached to the e-mail Operational Works Application OPW21/0212 - 31 Bottlebrush Ave, - DA Form 1 - Civil & Landscaping Plans - Construction Management Plan - Qleave - Project Management Plan - Traffic Management Plan - cover letter.
TRAFFIC GUIDANCE SCHEME/S (TGS) COVER SHEETS – 31 BOTTLEBRUSH AVE – NOOSA HEADS GENERAL INFORMATION, NOTES AND TRAFFIC MANAGEMENT CONSIDERATIONS CLIENT: COLE PROJECTS PROJECT DESCRIPTION: RESIDENTIAL CONSTRUCTION CLIENT CONTACT: CAMERON COLE WORKS LOCATION: 31 BOTTLEBRUSH AVE – NOOSA HEADS POSITION: PROJECT MANAGER NEAREST SIDE STREETS: BERRIMA ROW TRAFFIC MANAGEMENT DESIGNER: CLIENT CONTACT PHONE: 0407 593 956 ROAD CONFIGURATION: TWO WAY GUY HALLIDAY – TMD CERT. # OP-259 SITE CONTACT: STEVE COLE ORIGINAL POSTED SPEED: 50Km/H TRAFFIC MANAGEMENT & PLANNING SITE CONTACT PHONE: 0412 552 971 WORKSITE SPEED: 50KM/H DESIGN DATE: 31/05/2021 NOMINATED TRAFFIC CONTROL CO: TBA PROPOSED START DATE: TBA REVISION: ORIGINAL DOCUMENT NOMINATED TRAFFIC OFFICER: TBA DURATION OF WORKS 8 MONTHS MUTCD: PART 3 – NINTH ISSUE, 2019 N.T.O CONTACT PHONE: TBA TGS DIAGRAMS COVERED: CP-BOTT-TGS1, 1A, 2 CLAUSE 1.5 – MUTCD – RESPONSIBILITY FOR SAFETY AT WORK SITES: Organisations and individuals responsible for works in accordance with this Part of the Manual need to be aware of their responsibilities for any injury to road users or damage to property as a result of such operations. There is an equally important obligation to provide a safe workplace environment that minimises, as far as practicable, the likelihood of injury to workers by traffic within or adjacent to the work area. Principals and contractors need to be aware of the requirements of OHS legislation and implement them as they apply to this obligation. Supervisory personnel carrying out construction, maintenance or other works that require the use of a Traffic Guidance Scheme shall give attention to the following: a) Be mindful of their responsibility to provide, as far as practicable, a safe workplace for personnel and plant under their control, and safe and convenient travelling conditions for road users. b) Ensure that personnel under their control are, at all times, courteous to road users. Personnel should not allow themselves to become distracted by provocation from members of the public. c) Ensure that personnel are competent to perform the roadwork signing task (See Clause 1.4.3). d) Ensure that all personnel at a work site are aware of their responsibilities. e) Ensure that Traffic Controllers are appropriately trained and informed of their duties and that they are regularly relieved from their duty (see Clause 4.10.5). f) Be familiar with, and act, as far as is practicable, in accordance with the provisions of this Part of the Manual. SITE LOCATION OVERVIEW MAP • Setting out and recovery of devices Existing signs and traffic control devices which are inappropriate to, or conflict with, the temporary worksite situation shall be fully covered or removed. Before work commences, signs and devices at the approaches to and within the work area should be set out in accordance with the traffic guidance scheme in the following sequence: (a) Advance warning and regulatory signs (including temporary speed zone signs). (b) All intermediate advance warning and regulatory signs and devices required in advance of the taper or start of the work area. (c) All delineating devices required to form the taper including the illuminated flashing arrow sign at the end of the taper where required. (d) Delineation of the work area or side-track. (e) All other required warning and regulatory signs including termination and end of temporary speed zone signs. • Defining and protecting the work area The travelled path on the approaches and past the work area shall be delineated so as to properly define which part of the roadway is available to road users, or the path that traffic is required to follow, under all reasonably expected weather and atmospheric conditions, day or night as applicable. TGS OVERVIEW The objective of this document is to provide the client, subcontractors and Traffic Delineating devices (e.g. traffic cones, bollards, post mounted delineators) should Management personnel carrying out works at this location with a specified generally be placed 1 m clear of the travelled path where practicable. However, arrangement for the signing and delineation of construction and maintenance works traffic cones and bollards may also be used to define the edge of the travelled path which will promote the safety of both workers and the public at the work site. or to separate opposing traffic. This Traffic Guidance Scheme has been developed based on the brief of information In addition to providing adequate traffic control and guidance at a static work site provided by the client, as well as a risk assessment of the location and its observed the safety of road users will be enhanced by ensuring that the work site is and/or interpreted risks and associated hazards. The TGS diagram/s detail the traffic managed in such a way as to cause the minimum amount of inconvenience to control signs, devices and control measures to be applied at the relevant work sites traffic movement. Works in order to warn traffic and guide it through, past or around the work area. should be arranged to minimise - (i) disruption of established traffic movements and patterns; The purpose of this Traffic Guidance Scheme is to ensure the safety of all workers (ii) interference with traffic at peak movement periods; within the work site, as well as the general public. (iii) interference with public transport services; and (iv) the amount of road closed to traffic at any one time. GENERAL TRAFFIC MANAGEMENT PRINCIPLES • A TMR certified Traffic Management Implementation (TMI) Officer must implement • Risk management (or directly supervise the implementation of) the TGS. Approval for erection or Risk management entails the identification and analysis of all safety risks likely to removal of regulatory traffic control devices shall be obtained from the Department arise during works on road including the setting up, operating, changing and of Transport and Main Roads or appropriate road authorities before implementing ultimate dismantling of a Traffic Guidance Scheme, followed by the determination this Traffic Guidance Scheme. of appropriate measures to mitigate those risks. The process is appropriate at all levels of planning and operation. In each case the process should be carried out • Risk management - Risk management entails the identification and analysis of all by first identifying all the hazards likely to arise, evaluating them in terms of safety risks likely to arise during works on road including the setting up, operating, likelihood of occurrence and adverse consequences using historical data, changing and ultimate dismantling of a Traffic Guidance Scheme, followed by the experience or other means. The proposed procedural statement or Traffic determination of appropriate measures to mitigate those risks. The process is Guidance Scheme should then be checked in detail to ensure that adequate appropriate at all levels of planning and operation. In each case the process means of controlling or reducing those risks found to be significant, are in place. should be carried out by first identifying all the hazards likely to arise, evaluating them in terms of likelihood of occurrence and adverse consequences using • Traffic Controllers historical data, experience or other means. The proposed Traffic Guidance The regulation provides that the function of a traffic controller is to direct traffic in a Scheme should then be checked in detail to ensure that adequate means of way stated in the MUTCD and the TCASAP. controlling or reducing those risks found to be significant, are in place. Traffic controllers shall be relieved from their duty after not more than 2 hours for a • Positioning of devices period of rest or “other duties” of at least 15 minutes. [NOTE: “Other duties” does Signs and devices should be positioned and erected so that– not include operation of a STOP/SLOW bat to control traffic or any duties involving a) they are properly displayed and securely mounted (see Clause 3.3 - MUTCD); standing in one position or controlling traffic with a traffic control device]. b) they are within the line of sight of the intended road user; c) they cannot be obscured from view (for example, by vegetation or parked cars); Approach speeds to locations where Traffic Controllers are operating shall be d) they do not obscure other devices from the line of sight of the intended road controlled to 60 km/h or less by means of appropriate devices and advance signs user; including a temporary speed zone. e) they do not become a possible hazard to workers, pedestrians, or vehicles; f) they do not deflect traffic into an undesirable path; Traffic controllers must ensure that they have a clear escape path to a non-traffic g) they do not restrict sight distance for drivers entering from side roads or streets, (closed) section of the roadway, shoulder, footpath or median. Traffic controllers or private driveways; and must stand facing the traffic but just outside the projected travel path. A traffic h) they are not installed using supports that could be a hazard if struck by a controller must ensure that they are not partially hidden by signs and/or devices vehicle. and they do not obstruct a driver's view of such signs and/or devices. Traffic controllers shall also be provided, if necessary, to control the movement of plant and / or pedestrians through, past or within the trafficable area. 1
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Traffic Management Plan.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.
Full text of the other 7 pages
Page 2
• Signs warning of works personnel
The Workers (symbolic) sign is used to give warning of personnel engaged in • Provision for pedestrians and bicycles
works on or adjacent to the travelled path as specified in Clause 4.7.2(a). As this Where pedestrians, including school children and people with disabilities or visual
sign is used to warn of the presence of personnel, it shall only be displayed when impairment, have to move through, past or around a work site or to cross the road
they are actually working, or are visible to traffic, or both, and shall be removed or within a work site, they shall be provided with and directed to suitably constructed
covered when workers have left the work area or are no longer visible to traffic. and protected temporary footpaths and crossing points, or formal pedestrian
crossings, or refuges if warranted. Pedestrian and bicycle paths should, where
The Traffic Controller Ahead / PREPARE TO STOP sign shall be used to give practicable, be provided on the same scale and to the same width as any facilities
advance warning where traffic may be required to stop in compliance with the for pedestrian or bicycle traffic that were existing prior to the works. If this is not
directions of a Traffic Controller. The sign shall be installed 2D in advance of the practicable, such facilities shall meet the requirements of Clause 2.3.8. – MUTCD
traffic control position where D is the greater value of the range of dimension given – 2019.
in Table 4.2. This should also be the sight distance from the traffic controller to
oncoming traffic. The sign shall not be displayed when the Traffic Controller is not
actually in attendance controlling traffic.
Traffic Guidance Scheme and Traffic Management Options Analysis
Option Description Closure Type Control Features TGS Reference
Measure
Around Vehicles Detoured Full Elimination/ Full width of road closed. Detour available with minimum delay NOT
Work around existing Closure/Detour Substitution
SELECTED
Zone roadway/ Side-tracked
Past Vehicles past Part Road Isolation / Remaining lane width of 3.0m per lane can be maintained on NOT
Work delineated work zone Closure / Engineering / low speed residential roads
SELECTED
Zone Lateral Shift Administrative
Shoulder / Bus Isolation / Remaining lane width of 3.0m can be maintained SELECTED
Lane / Parking Engineering / CP-BOTT-TGS1, 1A
Lane Closure Administrative
Contra - Flow Isolation / Where a multi-lane divided road can be utilised to run NOT
Engineering / opposing lanes of traffic on one side. Remaining lane width of
SELECTED
Administrative 3.0m per lane can be maintained.
Lane / Turning Isolation / Remaining lane width of 3.0m can be maintained on low speed NOT
Lane Closure Engineering / residential roads
SELECTED
Administrative
Single Lane Isolation/ Where two – way traffic cannot be maintained as per above on SELECTED
reversible Flow Engineering/ two-way road. Remaining width of 3.0m with 0.5m edge CP-BOTT-TGS2
Administrative clearance shall be maintained to allow for single file of traffic
past work area
Temporary Isolation/ Traffic Controller/s may be required to hold traffic in one or NOT
closure / work Engineering/ both directions briefly to allow for work vehicle ingress / egress
SELECTED
vehicle access Administrative
Through Vehicles through Temporary road Isolation / Hold and Release all traffic when safe to do so. NOT
Work Work Zone closure/ Hold Engineering /
SELECTED
Zone and Release Administrative
Local Traffic Isolation / Locations where road features restrict implementation of NOT
Access Engineering / above options
SELECTED
Administrative
Warning Pre-warning signage N/A Signage MUTCD approved and custom signage as required placed as a NOT
Signage only warning to both vehicles and pedestrians
SELECTED
Pedestrian Management
Option Description TGS Reference
Around Work Zone Pedestrians diverted around work area (usually to NOT SELECTED
footpath on other side of road) utilising existing
crossing and/ or driveway
Past Work Zone Minimum 1.0m footway maintained past work area NOT SELECTED
(on the verge or on the roadway) with appropriate
delineation and protections in accordance with the
MUTCD
Through Work Zone Minimum 1.0m footway maintained through the work NOT SELECTED
zone such that pedestrians are safely managed either
under traffic control (e.g. Passage through /between
work area and parked work vehicle, or a designated,
delineated walkway through the development area
but away from specific work areas.
Note: The pedestrian footpath is on the opposite side of the footpath to the worksite and pedestrian movement will be unaffected by the works
2
Page 3
REFERENCE TABLES FOR VARIOUS PURPOSES WITH ADOPTED CRITERIA
FOR THIS WORKSITE HIGHLIGHTED IN YELLOW
Table 4.2 – Value of D TABLE 3.7 - RECOMMENDED MAX SPACING OF CONES AND BOLLARDS
Posted speed in km/h Dimension D (m) Purpose and usage Speed limit (km/h) Recommended
(prior to roadworks) maximum spacing
40 or less 5 to 10 (m)
50 10 to 15 All purposes <50 4
60 15 to 45 Closure >70 12
70, 80 60 to 80 Taper >70 9
90, 100 90 to 100
110 100 to 120 TABLE 4.1 - WORKS PROTECTION METHODS
Works Applicable Tasks MUTCD ADOPTED
Method Ref METHOD
Static All works which are Clause
Recommended taper lengths (Table 4.6) work site greater in scope and 4.2
Permanent Recommended taper lengths (m) duration than can be
posted speed Traffic Control at Lateral shift Merge taper handled by the short ADOPTED
(km/h) beginning of taper taper term, low impact
40 or less 15 5 15 provisions listed below or
50 15 15 30 mobile works
60 30 30 60 Short Isolated work on Clause
70 30 60 - 80 120 - 160 term, low pavements of up to 5 min 4.3
80 30 60 - 80 120 - 160 impact duration, traffic volumes NOT
90 30 60 - 80 120 - 160 works – permitting. Shoulder ADOPTED
open road grading and verge
100 30 60 - 80 120 - 160
areas mowing
> than 100 30 60 - 80 120 - 160
Short Work adjacent to or in a Clause
term, low traffic lane of duration 5 4.4
impact min to work 1 hour
works – depending on traffic NOT
built up volume. Median and ADOPTED
areas verge mowing, footpath
Table 4.11 - Minimum Lane Widths works
Works on Maintenance grading. Clause NOT
Posted speed limit during road works Minimum lane widths (m)
unsealed Short term partial road 4.5 ADOPTED
(km/h)
roads closures
60 or less 3.0
Mobile Line marking, pavement Clause
70 to 90 3.2
Works marker laying or removal, 4.6
Greater than 90 3.4
pavement testing where
all signs and other NOT
protective devices are ADOPTED
TABLE 4.7 - GUIDE TO THE SELECTION OF ROADWORKS SPEED LIMITS carried on vehicles
40Km/H Worker safety – Workers on foot are working within 1.2m of
traffic with no intervening physical protection
Traffic Safety – There would be structural danger to bridges at
higher speeds (1km maximum length)
60Km/H Workers Safety – Workers on foot or operating plant are within
3m of the trafficable area with no intervening
physical barrier
- A traffic controller is being used in advance of
portable or temporary traffic signals
- Dust or smoke may reduce visibility
Traffic Safety – Traffic is subjected to a reduced standard
alignment due to the works
- The pavement surface has been degraded
- A bituminous seal has just been laid
3
Page 4
EXAMPLES OF CORRECT SIGNAGE MOUNTING
FOR SIGNAGE PLACEMENT, LONG TERM
GENERALLY MEANS LONGER THAN TWO WEEKS.
LONG TERM PLACEMENT ON POSTS
• ON KERBED ROADS IN BUILT UP AREAS ADJACENT TO FOOTPATHS
OR WHERE VEHICLE PARKING MAY OCCUR, THEY SHOULD BE
ERECTED A MINIMUM OF 2.2m MIN FROM LEVEL OF KERB OR
FOOTPATH TO UNDERSIDE OF SIGN.
• SIGNS SHOULD BE PLACED SO THAT THEY ARE PROMINENTLY
DISPLAYED TO TRAFFIC AND WILL COMMAND ATTENTION.
• SIGNS SHOULD BE PLACED AT LEAST 2m CLEAR OF THE TRAVELLED
PATH WHERE PRACTICABLE.
LONG TERM PLACEMENT ON POSTS
• WHERE NEITHER PEDESTRIANS OR PARKED VEHICLES HAVE TO BE
CONSIDERED, A MOUNTING HEIGHT OF 1.5m MIN FROM LEVEL OF
SHOULDER SURFACE TO UNDERSIDE OF SIGN MAY BE MORE
APPROPRIATE, E.G MEDIANS, ISLANDS, OPEN ROAD AREAS ETC.
• SIGNS SHOULD BE PLACED SO THAT THEY ARE PROMINENTLY
DISPLAYED TO TRAFFIC AND WILL COMMAND ATTENTION.
• SIGNS SHOULD BE PLACED AT LEAST 2m CLEAR OF THE TRAVELLED
PATH WHERE PRACTICABLE.
SHORT TERM PLACEMENT OF SIGNS
• SIGNS MOUNTED ON PORTABLE SUPPORTS (LEGS) SHOULD BE A
MINIMUM HEIGHT OF 200mm FROM THE SHOULDER SURFACE TO
THE BOTTOM EDGE OF THE SIGN.
• SHORT TERM SIGNS SHOULD BE PLACED SO THAT THEY ARE
PROMINENTLY DISPLAYED TO TRAFFIC AND WILL COMMAND
ATTENTION.
• IN BUILT UP AREAS, SIGNS SHOULD BE PLACED BEHIND THE KERB
IF VISIBLE TO ONCOMING TRAFFIC. IF SIGNS HAVE TO BE PLACED
ON THE PAVEMENT, THEY SHOULD BE PLACED AS NEAR AS
PRACTICABLE TO THE KERB WITHOUT BECOMING OBSCURED OR
OBSTRUCTING MOVING TRAFFIC.
• SIGNS ARE NOT PERMITTED TO BE PLACED IN OR OBSTRUCT
BICYCLE LANES UNDER ANY CIRCUMSTANCES
• IF SIGNS ARE PLACED ADJACENT TO OR PARTLY ON A FOOTPATH,
A TRAFFIC CONE OR BOLLARD SHOULD BE PLACED AGAINST THE
SIGN TO WARN PEDESTRIANS AND CYCLISTS OF ITS PRESENCE.
• SIGNS MAY NEED TO BE WEIGHTED DOWN WITH SAND BAGS IN
WINDY CONDITIONS OR OVERNIGHT TO ENSURE STABILITY.
Note: In all cases,
1. Traffic Management signage may only be placed in position by a person who holds a Traffic Management
Implementation (TMI) qualification.
2. Implementation of signs should be done in accordance with a Traffic Guidance Scheme designed by a Traffic
Management Design qualified person.
3. Any changes to a Traffic Guidance Scheme may only be authorised by a Traffic Management Design qualified
person.
4
Page 5
GENERAL TRAFFIC GUIDANCE SCHEME NOTES
1. Traffic Guidance Schemes attached herewith have been drawn based on the principles of the current issue of the MUTCD Pt. 3 "Works on Roads” (November 2019).
2. All signage to be placed, based on an onsite risk assessment in accordance with clause 2.2.3 of the MUTCD Part 3, at the time of installation.
3. The Principal Contractor (PC) / PCBU is responsible for ensuring all works are conducted in accordance with relevant legislation.
4. A site pre-start should be undertaken prior to starting to ensure consultation with all workers understand the work activities and details of the TGS.
5. Signs and devices shall be set out and placed by a Traffic Management Implementation (TMI) qualified person.
6. Setting out of signs and devices should be done in the following sequence and removed in reverse order (Clause 2.5.3):
a) Advanced warning and regulatory signs (including temporary speed zone signs)
b) All intermediate advance warning and regulatory signs and devices required in advance of the taper or start of work area.
c) All delineating devices required to form taper including the illuminated flashing arrow sign at the end of the taper where required.
d) Delineation of the work area or side-track.
e) All other required warning and regulatory signs including termination and end of temporary speed zone signs.
7. It is the responsibility of the Principal Contractor (PC) / PCBU, to ensure, all signage is checked regularly, once installed. (Appendix A-A2)
8. Due consideration is to be to be given to all road users at all times, including but not limited to motorists, cyclists and pedestrians.
9. Signs that are inappropriate to, or conflict with, the worksite situation shall be covered or removed. This might include conflicting speed signs during working hours,
or “Workman” symbolic and/or Traffic Controller Ahead signs when workers are not present, or Traffic Controllers are not operating.
10. Signage and devices to not be placed as to obstruct vehicles or pedestrians (usually 1m from any running lane), but clause 4.13.4 of the MUTCD should be observed
in all situations.
11. Changes to the signage arrangements, as documented here, are to be recorded as per the requirements of the MUTCD Pt. 3 Clause 2.6.2
12. Placement of signage will need to consider any existing signage and other obstacles such as buildings, street furniture and vegetation at the location.
13. Signage / device placement must be assessed on site and adjusted within tolerances allowed if necessary. (Clause 4.1.6).
14. Where no distance for sign placement are given, a literal interpretation is required, based on an onsite risk assessment.
15. Diagrams drawn are not to scale and locations shown are indicative only.
13. Short term signage (usually up to 2 weeks) may be mounted at a minimum of 200mm above road / kerb surface level.
Long term signage should be mounted on fixed supports (posts). On kerbed roads in built-up areas where signs are mounted on posts adjacent to a footpath, or
where vehicle parking may occur, they should be erected a minimum of 2.2 m above the level of the kerb or footpath to the underside of the sign, to reduce
interference from parked vehicles. Where neither pedestrians nor parked vehicles have to be considered, for example, on a traffic island or median, a mounting
height of 1.5 m may be more appropriate. (See clause 2.5.2 of MUTCD).
14. Minimum lane widths in accordance with table 4.11 and edge clearances will be maintained at all times.
15. Cone or bollard spacing should be done in accordance with table 3.7 of the MUTCD.
16. Where signage cannot be placed on the left side of the road as indicated in the diagrams, it may be placed on the right-hand side (or median).
17. Plant, vehicles and materials are not to be stored in positions where they may create a hazard, obscure signage or block the line of sight for approaching drivers /
cyclists.
18. Any changes to the TGS (Outside the scope of TMI Table 1.4.31 Supplement MUTCD Part 3) shall be reported to a TMD officer for approval prior to changes being made.
19. Clearances for excavation works adjacent to running lane to be delineated in accordance with table E1 in the MUTCD Part 3.
20. All incidents/ accidents within the site area to be dealt with in accordance with the site safety plan.
Notes below on Traffic Controllers apply when Traffic Controllers have been contracted:
21. Traffic Controllers must conduct their operational procedures in accordance with the TCASAP.
22. Traffic Controllers must be clothed in accordance with the DTMR – Queensland Traffic Controller Clothing Standard.
23. Traffic Controllers shall be relieved from their duty after not more than 2 hours for a period of rest or other duties of at least 15 minutes (TCASAP).
24. Traffic Controllers should always have an escape route to a safe location established prior to starting work.
25. Traffic controllers should follow the guidelines for daily routines (Appendices A2 & A3 of MUTCD Part 3).
Traffic Management & Planning Disclaimer
The following Traffic Guidance Schemes have been prepared in accordance with information supplied by the client and/or onsite visits. Technical due
diligence has been applied in the production of these documents based on that information supplied. The “Traffic Management Design professional /
consultant”, and Traffic Management & Planning is not responsible for any omissions or errors in the base information supplied by the client.
While all care has been taken in the preparation of these documents, traffic and site conditions at the time of the works may vary from those established
in the development of the Traffic Guidance Schemes. The “client” is responsible for undertaking an evaluation of the site and traffic conditions against
the application constraints outlined within the Traffic Guidance Schemes as appropriate. Where conditions vary from those documented, additional
input from a Traffic Management Design professional should be sought.
5
Page 6
www.invarion.com
COLE PROJECTS RESIDENTIAL DEVELOPMENT 31 BOTTLEBRUSH AVE NOOSA HEADS
N SHOULDER CLOSURE & GENERAL WORKS SIGNAGE
TGS #:CPBOTTTGS1
FOR POSTED SPEED OF 50Km/H D = 10 15m
FOR USE DURING
WORKING HOURS
FUTURE TRAFFIC
BE
CONTROLLER SIGN
RR
MATERIALS DELIVERY AREA
IM
A
RO
W
NEIGHBOR
DRIVEWAY
FOOTPATH FOOTPATH NEIGHBOR
CLOSED CLOSED DRIVEWAY
DO NOT OVERTAKE
REDUCE SPEED
DRIVE SAFELY
AHEAD
WORK
ROAD
PREPARE
WORK
STOP
ROAD
END
TO
30m 15m 15m
BOTTLEBRUSH AVE
15m 15m
30m
PREPARE
DO NOT OVERTAKE
WORK
DRIVE SAFELY
ROAD
STOP
END
TO
REDUCE SPEED
AHEAD
WORK
ROAD
FUTURE TRAFFIC
CONTROLLER SIGN
LEGEND TGS SPECIFIC NOTES
1). THIS ARRANGEMENT IS DEVELOPED IN ACCORDANCE WITH CLAUSE 4.2 (STATIC WORK SITES) OF THE MUTCD 2019
= WORK AREA 2). SIGNS THAT ARE INAPPROPRIATE TO, OR CONFLICT WITH, THE WORKSITE SITUATION SHALL BE COVERED OR REMOVED. (REF. CLAUSE 2.4.4 MUTCD 2019)
= BOLLARDS OR 700mm CONES 3). ON KERBED ROADS IN BUILT UP AREAS, SIGNS MOUNTED ON POSTS SHOULD BE ERECTED A MINIMUM OF 2.2m ABOVE KERB OR FOOTPATH TO THE BOTTOM IF THE SIGN. (REF. CLAUSE 2.5.2 – MUTCD – 2019).
4). ALL SIGNS TO BE MOUNTED IN PROMINENT POSITIONS WITH CLEAR LINE OF SIGHT TO ONCOMING TRAFFIC. (REF. CLAUSE 2.5.2 MUTCD 2019).
= SIGN PLACEMENT POSITION 5). WORK VEHICLES AND TRUCKS ARE NOT PERMITTED TO STOP AND/OR REVERSE ON PUBLIC ROADS WITHOUT TRAFFIC CONTROL. A SPOTTER SHOULD BE USED TO ASSIST WORK VEHICLES TO ENTER THE
= EXISTING FOOTPATH DELINEATED SHOULDER AREA.
6). WORKMAN (SYMBOLIC) SIGNS TO BE COVERED WHEN WORKERS HAVE LEFT THE AREA OR ARE NO LONGER VISIBLE TO TRAFFIC.(REF. CLAUSE 3.4.4 MUTCD).
= TEMP. HAZARD MARKER 7). THE TRUCKS SIGNS SHOULD ONLY BE DISPLAYED WHEN THE NEED EXISTS AND SHOULD BE COVERED WHEN TRUCK ACTIVITY HAS CEASED. (REF. CLAUSE 3.16.2 MUTCD).
8). 3m MIN LANE WIDTH REQUIRED FOR ALL OPEN TRAFFIC LANES AT ALL TIMES. (REF. CLAUSE 4.13.3 MUTCD 2019).
= SIGN COVER 9). FOR ADDITIONAL NOTES RELATING TO THIS TGS PLEASE REFER TO THE GENERAL TRAFFIC GUIDANCE SCHEME NOTES SUPPLIED WITH THE ORGINAL TGS DIAGRAMS FOR THIS JOB.
REV DATE DESCRIPTION CLIENT: COLE PROJECTS IMPLEMENTATION DATE: TBA DIAGRAM PREPARED BY:
GUY HALLIDAY
00 31/05/21 PRODUCED FOR CONSTRUCTION LOCATION: 31 BOTTLEBRUSH AVE NOOSA HOURS OF OPERATION: 06301800
REVISIONS
Dept. Transport & Main Roads
Traffic Management Design
01 PLAN NUMBER: CPBOTTTGS1 TRAFFIC MANAGEMENT: REGULATORY Certification # 259
02 SCALE / PRINT SIZE: NOT TO SCALE PRINT TO A3 CONTROL METHOD: SHOULDER CLOSURE
03 SITE CONTACT: STEVEN COLE 0412 552 971 TERM OF WORKS: LONG
04 TRAFFIC CONTROL Co. TBA ORIGINAL POSTED SPEED: 50 Km/h MINIMUM LANE WIDTH: 3.0m
PROJECT CAMERON COLE 0407 593 956 NTO CONTACT: TBA WORKSITE SPEED LIMIT: 50 Km/h VALUE OF D: TABLE 4.2 (MUTCD)
MANAGER DURATION OF WORKS: 8 MONTHS ROAD TYPE: TWO WAY TAPER LENGTH: TABLE 4.6 (MUTCD)
Page 7
www.invarion.com
COLE PROJECTS RESIDENTIAL DEVELOPMENT 31 BOTTLEBRUSH AVE NOOSA HEADS
N SHOULDER CLOSURE & GENERAL WORKS SIGNAGE
TGS #:CPBOTTTGS1A
FOR POSTED SPEED OF 50Km/H D = 10 15m
FOR USE AFTER
WORKING HOURS
FUTURE TRAFFIC
BE
CONTROLLER SIGN
RR
MATERIALS DELIVERY AREA
IM
A
RO
W
NEIGHBOR
DRIVEWAY
FOOTPATH FOOTPATH NEIGHBOR
CLOSED CLOSED DRIVEWAY
DO NOT OVERTAKE
REDUCE SPEED
DRIVE SAFELY
AHEAD
WORK
ROAD
PREPARE
WORK
STOP
ROAD
END
TO
30m 15m 15m
BOTTLEBRUSH AVE
15m 15m
30m
PREPARE
DO NOT OVERTAKE
WORK
DRIVE SAFELY
ROAD
STOP
END
TO
REDUCE SPEED
AHEAD
WORK
ROAD
FUTURE TRAFFIC
CONTROLLER SIGN
LEGEND TGS SPECIFIC NOTES
1). THIS ARRANGEMENT IS DEVELOPED IN ACCORDANCE WITH CLAUSE 4.2 (STATIC WORK SITES) OF THE MUTCD 2019
= WORK AREA 2). SIGNS THAT ARE INAPPROPRIATE TO, OR CONFLICT WITH, THE WORKSITE SITUATION SHALL BE COVERED OR REMOVED. (REF. CLAUSE 2.4.4 MUTCD 2019)
= BOLLARDS OR 700mm CONES 3). ON KERBED ROADS IN BUILT UP AREAS, SIGNS MOUNTED ON POSTS SHOULD BE ERECTED A MINIMUM OF 2.2m ABOVE KERB OR FOOTPATH TO THE BOTTOM IF THE SIGN. (REF. CLAUSE 2.5.2 – MUTCD – 2019).
4). ALL SIGNS TO BE MOUNTED IN PROMINENT POSITIONS WITH CLEAR LINE OF SIGHT TO ONCOMING TRAFFIC. (REF. CLAUSE 2.5.2 MUTCD 2019).
= SIGN PLACEMENT POSITION 5). WORK VEHICLES AND TRUCKS ARE NOT PERMITTED TO STOP AND/OR REVERSE ON PUBLIC ROADS WITHOUT TRAFFIC CONTROL. A SPOTTER SHOULD BE USED TO ASSIST WORK VEHICLES TO ENTER THE
= EXISTING FOOTPATH DELINEATED SHOULDER AREA.
6). WORKMAN (SYMBOLIC) SIGNS TO BE COVERED WHEN WORKERS HAVE LEFT THE AREA OR ARE NO LONGER VISIBLE TO TRAFFIC.(REF. CLAUSE 3.4.4 MUTCD).
= TEMP. HAZARD MARKER 7). THE TRUCKS SIGNS SHOULD ONLY BE DISPLAYED WHEN THE NEED EXISTS AND SHOULD BE COVERED WHEN TRUCK ACTIVITY HAS CEASED. (REF. CLAUSE 3.16.2 MUTCD).
8). 3m MIN LANE WIDTH REQUIRED FOR ALL OPEN TRAFFIC LANES AT ALL TIMES. (REF. CLAUSE 4.13.3 MUTCD 2019).
= SIGN COVER 9). FOR ADDITIONAL NOTES RELATING TO THIS TGS PLEASE REFER TO THE GENERAL TRAFFIC GUIDANCE SCHEME NOTES SUPPLIED WITH THE ORGINAL TGS DIAGRAMS FOR THIS JOB.
REV DATE DESCRIPTION CLIENT: COLE PROJECTS IMPLEMENTATION DATE: TBA DIAGRAM PREPARED BY:
GUY HALLIDAY
00 31/05/21 PRODUCED FOR CONSTRUCTION LOCATION: 31 BOTTLEBRUSH AVE NOOSA HOURS OF OPERATION: OUTSIDE WORKING HOURS
REVISIONS
Dept. Transport & Main Roads
Traffic Management Design
01 PLAN NUMBER: CPBOTTTGS1A TRAFFIC MANAGEMENT: REGULATORY Certification # 259
02 SCALE / PRINT SIZE: NOT TO SCALE PRINT TO A3 CONTROL METHOD: SHOULDER CLOSURE
03 SITE CONTACT: STEVEN COLE 0412 552 971 TERM OF WORKS: LONG
04 TRAFFIC CONTROL Co. TBA ORIGINAL POSTED SPEED: 50 Km/h MINIMUM LANE WIDTH: 3.0m
PROJECT CAMERON COLE 0407 593 956 NTO CONTACT: TBA WORKSITE SPEED LIMIT: 50 Km/h VALUE OF D: TABLE 4.2 (MUTCD)
MANAGER DURATION OF WORKS: 8 MONTHS ROAD TYPE: TWO WAY RESIDENTIAL TAPER LENGTH: TABLE 4.6 (MUTCD)
Page 8
www.invarion.com
COLE PROJECTS RESIDENTIAL DEVELOPMENT 31 BOTTLEBRUSH AVE NOOSA HEADS
N LANE CLOSURE WITH SHUTTLE FLOW
TGS #:CPBOTTTGS2
FOR POSTED SPEED OF 50Km/H D = 10 15m
FOR USE DURING
WORKING HOURS
BE
RR
3m MINIMUM ROAD WIDTH
IM
A
RO
W
NEIGHBOR
DRIVEWAY
FOOTPATH FOOTPATH NEIGHBOR
CLOSED CLOSED
15m DRIVEWAY
DO NOT OVERTAKE
REDUCE SPEED
DRIVE SAFELY
AHEAD
WORK
ROAD
PREPARE
WORK
STOP
ROAD
END
TO
TC
30m 15m
BOTTLEBRUSH AVE TC
15m
15m
15m 30m
PREPARE
DO NOT OVERTAKE
THESE CAR PARKS MAY
WORK
DRIVE SAFELY
ROAD
STOP
END
TO
NEED TO BE APPROPRIATED
REDUCE SPEED
AHEAD
WORK
ROAD
LEGEND TGS SPECIFIC NOTES
1). THIS ARRANGEMENT IS DEVELOPED IN ACCORDANCE WITH CLAUSE 4.2 (STATIC WORK SITES) OF THE MUTCD 2019
= WORK AREA 2). SIGNS THAT ARE INAPPROPRIATE TO, OR CONFLICT WITH, THE WORKSITE SITUATION SHALL BE COVERED OR REMOVED. (REF. CLAUSE 2.4.4 MUTCD 2019)
= BOLLARDS OR 700mm CONES 3). ON KERBED ROADS IN BUILT UP AREAS, SIGNS MOUNTED ON POSTS SHOULD BE ERECTED A MINIMUM OF 2.2m ABOVE KERB OR FOOTPATH TO THE BOTTOM IF THE SIGN. (REF. CLAUSE 2.5.2 – MUTCD – 2019).
4). ALL SIGNS TO BE MOUNTED IN PROMINENT POSITIONS WITH CLEAR LINE OF SIGHT TO ONCOMING TRAFFIC. (REF. CLAUSE 2.5.2 MUTCD 2019).
= SIGN PLACEMENT POSITION 5). WORK VEHICLES AND TRUCKS ARE NOT PERMITTED TO STOP AND/OR REVERSE ON PUBLIC ROADS WITHOUT TRAFFIC CONTROL. A SPOTTER SHOULD BE USED TO ASSIST WORK VEHICLES TO ENTER THE
= EXISTING FOOTPATH DELINEATED SHOULDER AREA.
6). WORKMAN (SYMBOLIC) SIGNS TO BE COVERED WHEN WORKERS HAVE LEFT THE AREA OR ARE NO LONGER VISIBLE TO TRAFFIC.(REF. CLAUSE 3.4.4 MUTCD).
= TEMP. HAZARD MARKER 7). THE TRUCKS SIGNS SHOULD ONLY BE DISPLAYED WHEN THE NEED EXISTS AND SHOULD BE COVERED WHEN TRUCK ACTIVITY HAS CEASED. (REF. CLAUSE 3.16.2 MUTCD).
8). 3m MIN LANE WIDTH REQUIRED FOR ALL OPEN TRAFFIC LANES AT ALL TIMES. (REF. CLAUSE 4.13.3 MUTCD 2019).
= SIGN COVER 9). FOR ADDITIONAL NOTES RELATING TO THIS TGS PLEASE REFER TO THE GENERAL TRAFFIC GUIDANCE SCHEME NOTES SUPPLIED WITH THE ORGINAL TGS DIAGRAMS FOR THIS JOB.
REV DATE DESCRIPTION CLIENT: COLE PROJECTS IMPLEMENTATION DATE: TBA DIAGRAM PREPARED BY:
GUY HALLIDAY
00 31/05/21 PRODUCED FOR CONSTRUCTION LOCATION: 31 BOTTLEBRUSH AVE NOOSA HOURS OF OPERATION: 06301800
REVISIONS
Dept. Transport & Main Roads
Traffic Management Design
01 PLAN NUMBER: CPBOTTTGS2 TRAFFIC MANAGEMENT: REGULATORY Certification # 259
02 SCALE / PRINT SIZE: NOT TO SCALE PRINT TO A3 CONTROL METHOD: LANE CLOSURE
03 SITE CONTACT: STEVEN COLE 0412 552 971 TERM OF WORKS: SHORT
04 TRAFFIC CONTROL Co. TBA ORIGINAL POSTED SPEED: 50 Km/h MINIMUM LANE WIDTH: 3.0m
PROJECT CAMERON COLE 0407 593 956 NTO CONTACT: TBA WORKSITE SPEED LIMIT: 50 Km/h VALUE OF D: TABLE 4.2 (MUTCD)
MANAGER DURATION OF WORKS: 8 MONTHS ROAD TYPE: TWO WAY TAPER LENGTH: TABLE 4.6 (MUTCD)