NOOSA COUNCIL IDAS Development Application Decision Notice                                                           5


20.       The disable space shall be designed so that pedestrian access to and from the space is not via the
          driveway, as this is considered an unacceptable pedestrian access arrangement for a disabled person.
          To this end, a pedestrian path shall be provided to link this space with the entry to the building. The path
          shall also be designed to meet the appropriate disabled access requirements.

21.       All carparking areas shall be drained and the sealed pavement constructed to an Access Road standard
          in accordance with Council’s Engineering Design Standards. Plans and specifications for these works
          shall be submitted in conjunction with an application for a Development Permit for Operational Works.

22.       All carparking shall be kept maintained and line-marked in a condition fit for use to the reasonable
          satisfaction of the Manager - Land Development.

23.       A contribution in accordance with Planning Scheme Policy PSP 13 Contributions in Lieu of the Provision
          of Off Street Parking for 8 spaces shall be paid to Council prior to the issue of a Development Permit for
          Operational Works and the amount of the contribution shall be calculated at the rate current at the date of
          payment. An estimate only of the contribution rate as at March 2001 is $10,690 per car space short.

          Frontage Works

24.       At the completion of the Heron Street / David Low Way roundabout, the existing opening in the median
          within David Low Way, which currently provides access to the site, shall be closed off at no cost to
          Council. Details of this work shall be prepared by a suitably qualified Registered Professional Engineer
          and submitted to the Council prior to obtaining a Development Permit for Operational Works.

25.       A monetary contribution of $13,890 shall be paid to the Council prior to the issue of Development Permit
          for Operational Works towards the cost of frontage works / roadworks undertaken by Council, external to
          the development site (within the David Low Way). This amount will be subject to variations in the Price
          Index, All Groups Brisbane from June 2002 until the date of payment.

          Stormwater Drainage

26.       Roofwater and surface water from northern car park area is to be collected on site and discharged
          through a single underground drain line into existing drainage in the David Low Way to the reasonable
          satisfaction of the Manager - Land Development. In this regard, plans shall be prepared by a Registered
          Professional Civil Engineer and submitted to Council prior to obtaining a Development Permit for
          Operational Works.

27.       Surface water from the southern car park area is to be collected on site and discharged through a single
          underground drain line into an approved drainage system in the southwest corner of the property to the
          reasonable satisfaction of the Manager - Land Development. In this regard, plans shall be prepared by a
          Registered Professional Civil Engineer and submitted to Council prior to obtaining a Development Permit
          for Operational Works.

28.       To ensure that polluted run-off does not enter Council’s stormwater drainage system, stormwater run-off
          from the carparking areas and the driveways shall have the first flush (the first 12 mm of rainfall or hose-
          down) collected and treated in a grease/oil arrestor provided on site prior to being discharged off-site.

          All other clean stormwater, such as roof water, can be collected on site and discharged through a single
          underground drain line directly into the existing drainage system, bypassing the grease/oil arrestor.

29.       The developer shall negotiate with the downstream property owners for an easement to be created over
          any stormwater discharge from any part of this site onto neighbouring properties. This easement will cover
          the area necessary for Q100 flows and the underground pipe system to a lawful point of discharge.
          Council shall sight the easement documents prior to issuing a Development Permit for Operational Works.

          As an alternative to the easement option, the developer may install an infiltration or combined
          detention/infiltration system under the car park to dispose of all flows up to a Q100 event. A Registered
          Professional Engineer of Queensland will certify this design and its construction.

30.       All site stormwater drainage shall be by means of a gravity system.




H o:\database\onestop\decision.doc

Used in these records

About this file

File size
66 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

0015A7FC.001.pdf · 66 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.