2022-02-14 General Committee Meeting Minutes
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
GENERAL COMMITTEE MEETING MINUTES 14 FEBRUARY 2022
the first rain event forecast following initial tree clearing or removal of soil stabilising
material for each stage. At the hold point inspection, all required sediment basins,
drains and bunds to divert waters away from disturbed soil or soils about to become
exposed through cut to fill activities must be installed. All areas that will not require
earthworks in the imminent cut to fill operation must be stabilised to prevent
entrainment of sediments into receiving waters.
96. Cut to fill earthworks must not commence until after the Supervising CPESC has
certified that all installed erosion and sediment controls required by this approval are
sized in accordance with conditions of the approval and the written acceptance of the
certification is provided to the supervising RPEQ by Council officers.
97. Prescribed Water Contaminants (as defined in Schedule 10 of Environmental
Protection Regulation 2019) must not be released from the site or to waters within the
site, or be likely to be released should rainfall occur, unless all reasonable and
practicable measures are taken to prevent or minimise the release and concentration
of contamination.
98. Sediment and erosion control measures must be in place prior to works commencing.
If such measures are not in place or are not satisfactory, “on the spot” fines may be
issued. Such fines can be issued if sediments from the site are found to enter or have
the potential to enter Council’s stormwater system, natural waterways, any
downstream stormwater filtration system or adversely impacting on other properties.
The sediment and erosion control design and measures have NOT been approved, it
is the site's Supervising Engineer who is responsible for ensuring that the sediment
and erosion control measures have:
a. Been duly designed by an RPEQ or CPESC and constructed in accordance with
"best practise" methods;
b. Been revised by an RPEQ or CPESC to address the issues raised by changes
in the projected construction schedule and/or methods;
c. Been revised to address predicted rainfall events, and
d. Achieve the desired environmental outcomes.
99. Council may request further controls to be installed should the implemented measures
be found inefficient.
100. The erosion and sediment control measures must be designed, installed and
maintained in accordance with the supervising engineer instructions and the current
best practice standards * (Refer to Advisory Note).
101. The developer must ensure non-essential exposure of soil is prevented by restricting
the extent of disturbance and minimising the duration of soil exposure to adverse
weather conditions and effectively turf, cover or stabilise any disturbed area without
delay and prior to rainfall occurring.
102. The developer in conjunction with the engaged CPESC must ensure measures
installed to divert the upstream water are designed and certified by the supervising
RPEQ and installed prior to commencement of bulk earthworks.
103. The developer must ensure sediment does not leave the site or enter onto adjoining
properties or Council’s drainage system due to surface runoff or on tyres of vehicles
and/or machinery. It is essential to implement appropriate approved erosion and
sediment control measures throughout the site during all phases of construction
including vehicle shakedown pad/grid (or similar) at the access to the construction site.
Where sediments or other contaminants are deposited on a road, they must be
removed so as not to enter Council’s drainage system or waterways.
Page 23 of 26
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.