Fauna Management Plan
3-7 Serenity Close, Noosa Heads
Most of the construction activities that can impact fauna are similar to the clearing
activities mentioned in Section 4.2.1. Table 6 summarises the activities and management
responses which need to be carried out during the construction phase of the
development.
TABLE 6: CONSTRUCTION ACTIVITIES.
Action Task Responsibility Timing
Restrict vehicle 1) No vehicle access to areas of vegetation yet Site Manager During
access to be cleared. construction
2) Access is prohibited to vehicles outside of activities
construction machinery.
3) Set lower vehicle speeds around the site so
that motorists have a longer response time
to avoid collision with potentially disoriented
fauna.
4) Install signage depicting native wildlife in
areas of vehicular traffic on site.
Limit dust 1) Vehicles to drive slowly to keep dust clouds Site Manager During
generation from forming. vegetation
2) Thoroughly clean machinery after use. clearing
3) Use barriers to control dust.
Minimise 1) Trenches, pits and sediment ponds must be Fauna Spotter, During
damage covered when not in use. Site Manager construction
caused by 2) Unclimbable fences should be installed activities
construction around any pits to prevent fauna from falling.
material 3) Barbed wire, nets and other material that
could entrap fauna should not be left
unattended when not in use.
4) Electricity poles, towers and cranes must be
wrapped to prevent fauna from climbing.
5) Suggested risk mitigation measures can be
found in the Koala-Sensitive Design Guideline
2022 (Department of Environment and
Science 2022).
Restrict access 1) Any domestic pets brought onto site during Site Manager During
to site by construction are to be prevented from construction
domestic pets entering actual construction areas to avoid activities
injury and/or predation of wildlife.
2) Guard dogs must be kept on a leash and
under supervision at all times.
All machinery 1) Visually check all the machinery for the Wildlife During
is to be presence of wildlife before the start of Spotter/Catcher, construction
checked for construction. Site Manager activities
wildlife before
29 | 35
Document Set ID: 23516334
Version: 1, Version Date: 30/01/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Approved Document Fauna Management Plan Rev 1 0 OPW25-0012.pdfRelated documentApplication case desk ↗
About this file
- File size
- 18.4 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.