                 Fauna Management Plan
                 3-7 Serenity Close, Noosa Heads




                  Action               Task                                                   Responsibility   Timing
                  the beginning        2) Visually check all the routes for the presence
                  of operations           of wildlife before allowing construction to
                                          start.
                  Salvage injured      1)   If injured wildlife is detected during such       Fauna Spotter,   During
                  wildlife                  activities, the Fauna Spotter must take           Site Manager     construction
                                            immediate action to notify the machinery                           activities
                                            operator to cease work, either verbally using
                                            two-way radio or by visual commands, until
                                            such time as the injured wildlife is captured
                                            or otherwise removed from danger.
                                       2) All animals removed from the site must be
                                          captured, restrained and held in a manner
                                          that is unlikely to result in further injury,
                                          unacceptable distress or suffering. Animal
                                          welfare is the primary priority and
                                          responsibility of the Fauna Spotter.
                                       3) All fauna injuries or deaths will be reported
                                          to the Fauna Spotter and/or Project / Site
                                          Manager.
                                       4) Contact applicable agency / group listed in
                                          Table 3.
                  Monitor              1)   Artificial lighting on the subject site must be   Fauna Spotter,   During
                  artificial                operated to ensure it is directed away from       Site Manager     construction
                  lighting                  the adjacent conservation areas and other                          activities
                                            fauna corridors to minimise impacts to
                                            koalas and other wildlife inhabiting or
                                            moving through the site.
                  Adaptive             1)   Project manager to conduct regular                Site Manager     During
                  management,               inspections to ensure compliance with                              construction
                  monitoring and            procedures outlined in this plan.                                  activities
                  compliance           2) Project manager to issue notice of
                                          compliance to contractor for non-
                                          conforming works and any remedial works
                                          to ensure compliance.


                 4.4 POST-CONSTRUCTION MANAGEMENT MEASURES


                 After construction activities, there are several procedures and actions that must be
                 followed to ensure the site presents no risk to fauna. Procedures and actions include
                 removing all construction material that could potentially be harmful to koalas and
                 monitoring the site for the presence of koalas at the end of construction activities. Table 7
                 summarises the activities and management responses that need to be carried out during
                 the post-construction phase of the development.




                                                                                                                   30 | 35

Document Set ID: 23516334
Version: 1, Version Date: 30/01/2025

Used in these records

About this file

File size
18.4 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Approved Document Fauna Management Plan Rev 1 0 OPW25-0012.pdf · 18.4 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.