                      B.      The Subsequent payment of headworks shall include interest charged at the rate set
                              by the Queensland Treasury Corporation for Local Government borrowings as they
                              apply to Noosa Shire and current at the time the trading bank guarantee is submitted.
                      C.      Should the contributions not be paid at the due time, Council shall call upon the sum
                              secured by the trading bank guarantee.
                      D.      The trading bank guarantee will be returned on payment of the required contributions
                              plus interest or on expiry of the relevant Building Approval, whichever is sooner.
               8.     The footpath across the frontage of the site is to be upgraded by the provision of a 1.2 metres
                      wide concrete footpath and the forming, grassing and topsoiling of the remaining area to the
                      standards and requirements of the Shire Engineer. The applicant is to contact Council’s
                      Engineering Department to determine the footpath alignment prior to the commencement of
                      any works. A straight footpath is general undesirable.
               9.     The developer shall bear the cost of alteration of any public utility or other facilities
                      necessitated by the development of the land or associated construction works external to the
                      site.
               10.    Connection to Council’s existing water supply and sewerage reticulation systems at the
                      developer’s expense to the standards and requirements of the Shire Engineer.
               11.    The Developer shall provide metered water connections from the water supply system to the
                      proposed development, in accordance with Council’s standards and to the satisfaction of the
                      Shire Engineer.
               12.    Roof and surface water is to be collected on site and is to be discharged through a single
                      underground line into existing drainage into Sunseeker Close to the satisfaction of the Shire
                      Engineer. A Building Approval shall not be granted until the Shire Engineer has approved the
                      drainage scheme.
               13.    Provisions of approval refuse containers in accordance with the requirements of the Refuse
                      Management Regulations of 1983 for the storage and collection of refuse to the satisfaction
                      of Council’s Environmental Health Officer.
               14.    Provision of an imperviously paved area upon which to stand all refuse containers together
                      with a suitable enclosure, if required, to enclose the refuse container area to the satisfaction
                      of the Environmental Health Officer.
               15.    Any flat or unit intended to be let out for fee or reward is to be licensed annually with Council’s
                      Health Department in accordance with the provisions of Chapter 43 of Council’s By-Laws
                      prior to such letting.
               16.    Submission of a cash bond or trading bank guarantee to the sum of %3000 to secure
                      performance of conditions, prior to the issue of Building Approval. The cash bond or trading
                      bank guarantee will be returned upon performance of the conditions of approval.
               17.    The provisions of this approval are to be effected, prior to the commencement of the
                      approved use. Council reserves the right to call upon the bond or guaranteed sum referred
                      to in the approval for the purposes of litigation should the use not be conducted in accordance
                      with this approval.
               18.    The Town Planning Consent Permit may be revoked pursuant to Section 4.14 of the Local
                      Government (Planning and Environment) Act if the commencement of erection or works have
                      not been made in accordance with that Permit or the rights conferred by that Permit are not
                      exercised within two (2) years of the date of issue of the Permit.
               19.    The Town Planning Consent Permit lapses where:-
                      a.      The use or erection of a building or other structure associated with the use, has not
                              been commenced within four (4) years of the date of issue of the Town Planning
                              Consent Permit, unless application is made and approved by Council for an extension;
                              or



                                                                                                           Page 3 of 6
Document Set ID: 22475691
Version: 4, Version Date: 29/06/2023

Used in these records

About this file

File size
155 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - Minor Change - 51994 1165 01 [As Published].pdf · 155 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.