230518 Hofmann CMP
Exclusion zone fencing may be installed by the Main Contractor as required to minimize damage to
natural nature and fauna areas not designated as construction areas.
4.1 Traffic Management
The Main Contractor will be required to prepare a detailed Traffic Management Plan prior to the
issue of a Construction Certificate. Traffic will generally be managed in the following way:
Designated transport routes will be communicated to all personal, and enforced by Site
Management Team
Designated peak hour and non-peak hour delivery vehicle waiting areas will be assigned.
Strict scheduling of vehicle movement will occur to minimize off site waiting times.
On-site parking will not be provided, and site workers will utilize car sharing wherever
possible. Further investigations will be undertaken to bolster site parking strategy.
Vehicle movements will be compliant with Conditions of Consent and broader road-use
regulations, particularly with regard to hours of work, materials loading and unloading, and over
size deliveries and installation.
A suitable vehicle hold/staging point will not be necessary outside the site area to facilitate the
coordination as deliveries arrive and are unloaded as there are suitable areas within the site for this to
occur.
4.1.1 Street Closures
For works to be completed safely, some temporary street closures may be required. These closures will
be well planned in advance, with approvals sought from relevant authorities. Activities that may require a
street closure include tower crane erection and dismantling, and installation of major plant and
structures. Wherever possible these closures will be scheduled for non-peak times.
4.2 Pedestrian Management
The site is bound by a reasonable thorough fare connecting to Rene Street. There are no existing pedestrian
paths, these will be installed as part of the development.
4.3 Site Accommodation Compound & Shedding
The site accommodation compound and shedding will be positioned is yet to be determined, however it is
likely to be located at the front of the site or potentially on the adjacent site if permission is received.
4.4 Site Security
The Main Contractor will ensure the site is locked and secured when there is not a presence on the site. Licensed
security firms may be engaged as required to provide further security coverage. Typically, this would be over
holiday periods or closer to completion of the project.
4.5 Construction Zones and Material Handling
4.5.1 Construction Zones
All construction traffic will enter and exit via the shared access driveway from Hoffman Drive with
appropriate traffic management and signage to the external of the site.
During the road widening on Hoffman Drive, to provide the slip lane, the Main Contractor and
Civil Contractor will be responsible for all barriers and signage during this phase of the works
10