SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 9 AUGUST 2022
6. REPORTS FOR NOTING BY THE COMMITTEE
5 CAPITAL PROGRAM DELIVERY STATUS – 30 JUNE 2022
Author Infrastructure Planning, Design & Delivery Manager, Craig Eldridge
Infrastructure Services Department
Index ECM/ Subject/ 2021-2022 Annual Capital Works Program
Attachments Nil.
EXECUTIVE SUMMARY
This report provides a status update for the Capital Works program as at 30 June 2022.
The year-to-date capital delivery expenditure to 30 June 2022 is $31.4m or 71% of the
Capital budget. Additionally, $22.7m has been committed to multi-year projects.
As a result of the May 2022 flood event and the February 2022 flood event, 4 major projects
along with 130 council assets have been impacted. Additionally, internal resources have
been redirected to disaster management and now recovery activities. This redirection
continued to impact both budget and schedule in the last quarter and resulted in a carry over
into 2022/2023 of approx. $14m
The reduced availability of labour, equipment and materials and a ‘hot’ construction industry
is proving challenging however works are currently being managed within overall budget
limitations where feasible.
The road reseal program budgeted at $5.3m in the 2021/2022 financial year is now
completed, reaching $5m in actual spend.
Council has forecast grant funding revenue of $19m while Council’s contribution to projects
with grant funded projects is $16.2m and $12.8m to non-grant funded capital projects.
The Design Services team are currently supporting the design of 19 projects with multiple
sub-projects with an estimated design value of $970,000 and estimated construction value
of $16m.
The design services team also support the delivery team in the construction of over $20m
worth of infrastructure and the disaster recovery effort.
The Planning Services team is currently supporting key master planning initiatives with
multiple sub-projects; estimated value $350,000 in 2022/2023 and an estimated future
project investment value of $15m.
There are currently 25 multi-year projects in various states of completion.
RECOMMENDATION
That Council note the report by the Infrastructure Planning, Design & Delivery Manager to the
Services & Organisation Committee Meeting dated 9 August 2022 providing an update on the
delivery of the 2021/2022 Capital Program as at 30 June 2022.
REPORT
This report is to inform Council of the overall status of the Capital Works Program at the end of
June 2022.
The report provides an opportunity to highlight and discuss projects within the program and
Page 55 of 71
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.