43. Digital detail drawings and calculations shall be submitted with any application for a
Development Permit for Operational Works in respect of roadworks and stormwater drainage
works. The design shall be in accordance with Co0uncil’s Planning Scheme Policy 5 –
Engineering Design Standards – Roads, Draining and Earthworks. To avoid conflict with
underground pipes or services, all existing and proposed services required by the
development shall be shown on the plans.
44. Any damage caused to any public utility during the course of construction shall be repaired
to Council’s standards and at no cost to Council.
45. Any alteration of any public utility or other facilities necessitated by the development of the
land or associated construction works external to the site shall be at no cost to Council.
46. The transportation of all materials to and from the site shall be undertaken I a manner such
that no particle matter escapes onto a public road. All vehicles carrying materials either to
or from the site shall be covered to prevent materials including dust being windblown from
the vehicle.
Environmental Health
47. A Waste Management Plan (Demolition/Construction) in accordance with the Planning
Scheme Policy “Waste Management Multi Dwellings and Commercial and Industrial
Premises”, shall be submitted for the demolition and construction phases of the development
and approved by Council’s Environmental Health Section prior to the issue of the
development permit of Operational Works. The Plan shall contain the following information:
MATERIALS ON-SITE DESTINATION
Re-use and Recycling Disposal
Expected Waste Estimated On-site Off-site *specify *specify
Material Volume *specify contractor and contractor
(m3) proposed re- recycling outlet and landfill
use or on-site site
recycling
methods
Excavation material
Green Waste
Bricks
Concrete
Timber-please specify
Plasterboard
Metals-please specify
Asbestos
Other-please specify
Note: Details of site area to be used for onsite separation, treatment and storage (including
weather protection) shall be provided on the plan drawings accompanying your application.
48. Noise emission from swimming pool and spa equipment (including heating equipment) shall
comply with the following requirements:
a. The equipment shall be installed and located in a manner that prevents excessive noise
accordance with Council’s Local Law No. 12 – Control of Nuisances. Infringement
Notices (on-the-spot fines) may apply for offences.
b. A person must not use equipment on any day if it makes or causes noise to be made
–
i. From 10pm to 1am: which is audible outside the most exposed part of an
affected building.
ii. From 7am to 7pm: More than the lower of either –
• 50 dB(A)
Page 7 of 11
Document Set ID: 23339788
Version: 3, Version Date: 08/11/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Minor Change Existing Approval 132006 272 01 (3).pdfRelated documentApplication case desk ↗
About this file
- File size
- 198 KB (small file)
- File type
No other editions are linked here.