Original source · versioned page text
Appendix E - Construction Management Plan.pdf
Environmental Management Plan
MANAGEMENT SYSTEMS
Eff. Date:
Rev.: E Pg. 11 of 20
15/07/2020
Category/Activity Aspect Potential Impact/Risks Risk Rating Target Actions and Controls Residual
Risk
C P Initial
Risk
waste removal
requirements and costs,
• Noise pollution. 2 B H • Maintain a reasonable • Plant, equipment and machinery to be fitted with M
Noise and • Discomfort to site
acoustic environment for noise reducing attachments (i.e. mufflers).
living and use of properties
vibration personnel and adjoining impacted by constructions • Plant, equipment and machinery to be maintained in
neighbors and activities. accordance with manufacturers specifications.
properties.
• Establish consultation • Works (so far as is practicable) to be completed
and/or communication during approved work hours (i.e. per DA, Council or
policies to advise property EPA conditions).
occupiers of the potential • As applicable, install noise and vibration monitors to
impact of construction measure and record discomfort levels.
activities.
• Completion of applicable plant or equipment
• No complaints requiring Checklists at arrival of plant on site and before
corrective action. commencement of works.
• Implement work and • Daily inspections of Plant and works activities.
construction practices
which seek to minimise the • Investigate noise complaints or causes of excessive
impact of noise and noise and implement control measures as required
vibration of personnel and to manage noise emissions.
properties.
• Degradation of surfaces 1 C L • No traffic or other • Protect footpaths, kerbs and roads from damage L
Use of and kerbs due to infringement notices. through (e.g.) use of metal plates, restriction of
excessive force or heavy vehicles, prohibition for storing equipment or
roads and weight of heavy • No damage to roads, material on roads and footpaths etc.
footpaths, gutters,
footpaths vehicles and plant.
culverts, etc. • Ensure that hoardings, fencing etc is positioned and
• Impact on the safety of secured to prevent damage, hazardous or incidents.
pedestrians and other
road users from • Provide information to subcontract personnel in
obstructions and order to coordinate delivery mechanisms.
degradation of surfaces. • Conduct daily inspections of activities against the
• Impact on safe conditions noted in regulatory permits.
access/egress.
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (Appendix E - Construction Management Plan.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.