Appendix E - Construction Management Plan.pdf
Environmental Management Plan
MANAGEMENT SYSTEMS
Eff. Date:
Rev.: E Pg. 10 of 20
15/07/2020
Category/Activity Aspect Potential Impact/Risks Risk Rating Target Actions and Controls Residual
Risk
C P Initial
Risk
• Potential dust emission 1 C L • Minimal impact on air • Install control measures (i.e. water spraying*, L
Haulage which degrade air quality or surrounding area rumble grids, road sweepers) which limit the
quality. ambience. opportunity for dust, noise or spillage to occur.
• Exhaust emissions • Compliance with EPA • Limit site speed to 20 klm/h and ensure that
which exceed accepted requirements. transported loads are covered.
standards.
• Modify construction activities or utilise alternative
• Noise generation. machinery to control emissions.
• Fuel/oil spills which • Daily review and inspections of control measures.
impact on environment
quality.
• Contamination of 2 C M • No incidents. • Install bunding/silt fencing around stockpiles to L
Stockpile watercourses.
• No infringement notices.
prevent against water runoff.
management • Potential dust emission • Dampen* stockpiles by means of water sprays to
which degrade air management dust emissions.
quality.
• Where practicable, vegetate stockpiles to improve
soil stability.
• Limit the height and volume of stockpiles so that
control measures can be implemented.
• Daily inspections of stockpiles and erosion control
measures.
• Contamination of 3 C H • No major incidents. • Where practicable and applicable, install residue L
Trade waste ground soil, sewerage
• No infringement notices.
waste bins to accommodate such substances (i.e.
systems and storm concrete, paint, plaster).
water systems.
• Ensure that subcontractors include environmental
• Health hazards to site management in their WMS.
personnel and other
non-construction • Include residue management requirements in
personnel. Subcontract Agreements, trade requirements and
during trade tendering.
• Increased
housekeeping and • Daily inspections of work activities and installed
control devices.
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (Appendix E - Construction Management Plan.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.