Appendix E - Construction Management Plan

of 127

Page text read automatically using OCR, there may be inaccuracies

Traffic Management Plan - MPH09-BBN-ELAN-TMP-01
Unit Construction – 65-67 ELANDA St, Sunshine Beach, QLD. 4567
______________________________________________________________________________________
6.3 MONITORING AND MANAGEMENT FOLLOWING IMPLEMENTATION
The AGTTM Part 6 regarding Inspections and Maintenance states:
    a) Section 7.8 – Monitor and Measure
        At attended worksites the TMI should carry out the checklists listed in Table 7.1 below.




         Image courtesy AGTTM Part 6 Section 7

         The first inspection must take place as soon as the equipment has been installed.
         Monitoring the effectiveness of the TTM signs and devices and the operation of the TTM system should be continuous.
         Back-up TTM equipment must be available, to minimise the potential for disruption of worksite operations.

         Furthermore, All inspections shall be undertaken using a dash mounted camera and performed in accordance with TMR
         Technical Note 109 Video Record Keeping of Traffic Management at Roadworks (July 2014) and MUTCD Part 3
         Appendix A.

    b) 2.6.3 Maintenance of devices
       Ineffective signs and devices shall be replaced by similar items in good condition, if they cannot be made effective by
       cleaning or repairing.

         Signs and devices which are damaged or otherwise no longer in good condition should be either refurbished to new
         condition or replaced.

         Non-repairable signs should be destroyed so that they are not inadvertently reused.

         Water in water-filled safety barrier elements shall be maintained at the required level.

The Traffic Management for Construction or Maintenance work Code of Practice 2008 (section 7) states, the following:
    a) 7.4 Before work starts
         The following routine should be undertaken before work starts each day:
         •    inspect all traffic signs and devices and make a note of signs out of place or damaged during the night, for
              subsequent rectification
         •    inspect all water-ballasted safety barrier or containment fence modules and make a note of any out of position
              modules, low water levels and damaged modules, for subsequent rectification
         •    check for safety and effectiveness by an inspection drive through job after adjustments have been made to the
              traffic management provisions for the day, and make a record of the signs erected and their locations.

    b) 7.5 During work hours
       The following routine should be followed while work is in progress:
       •    periodically drive through the worksite to check that all signs, markings and delineation devices, as seen by other
            road users, are satisfactory and in their correct position
       •    attend to any minor problems, as they occur
       •    move personnel clear of the work area during work breaks (e.g. tea breaks); park plant clear of traffic lanes, and
            remove from view or cover inappropriate signs such as Traffic Controller Ahead/PREPARE TO STOP or Workers
            (symbolic), if workers leave the site or cannot be seen


MPH09-BBN-ELAN-TMP-01                            Document uncontrolled when printed or saved                       Page 20 of 61

Log in to download the original (Appendix E - Construction Management Plan.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.