Appendix E - Construction Management Plan
PAGE 1 OF 3
ID Task Name Duration Early Start Early Finish
2024 2025
June July August September October November December January February March April May June July August September October November December January February Ma
27/05
3/06
10/06
17/06
24/06
1/07
8/07
15/07
22/07
29/07
5/08
12/08
19/08
26/08
2/09
9/09
16/09
23/09
30/09
7/10
14/10
21/10
28/10
4/11
11/11
18/11
25/11
2/12
9/12
16/12
23/12
30/12
6/01
13/01
20/01
27/01
3/02
10/02
17/02
24/02
3/03
10/03
17/03
24/03
31/03
7/04
14/04
21/04
28/04
5/05
12/05
19/05
26/05
2/06
9/06
16/06
23/06
30/06
7/07
14/07
21/07
28/07
4/08
11/08
18/08
25/08
1/09
8/09
15/09
22/09
29/09
6/10
13/10
20/10
27/10
3/11
10/11
17/11
24/11
1/12
8/12
15/12
22/12
29/12
5/01
12/01
19/01
26/01
2/02
9/02
16/02
23/02
2/03
9/0
1 370 days Mon 10/06/24 Fri 7/11/25 PROPOSED DEVELOPMENT, 65-67 ELANDA ST, S
PROPOSED DEVELOPMENT, 65-67 ELANDA ST, SUNSHINE BEACH QLD
2 PROJECT MILESTONES 370 days Mon 10/06/24 Fri 7/11/25 PROJECT MILESTONES
3 TENDER MILESTONES 65 days Mon 10/06/24 Fri 6/09/24 TENDER MILESTONES
4 Tender Close 0 days Mon 10/06/24 Mon 10/06/24 Mon 10/06/24
5 Tender Negotiations, Award and Contract Execution - Subject to Finance (Client / Builder) 10 days Mon 10/06/24 Fri 21/06/24 Tender Negotiations, Award and Contract Execution - Subject to Finance (Client / Builder)
6 Finanace Approval 20 days Mon 24/06/24 Fri 19/07/24 Finanace Approval
7 Traffic Management Consultant - By Builder 5 days Mon 24/06/24 Fri 28/06/24 Traffic Management Consultant - By Builder
8 Operational Works, Building Approval Documents / Detailing, Plumbing & Drainage Approval, Partial Road Closure Permit and Building 40 days Mon 1/07/24 Fri 23/08/24 Operational Works, Building Approval Documents / Detailing, Plumbing & Drainage Approval, Partial Road Closure Permit and Building Approval - By Principal
Approval - By Principal
9 Lead-in Period Prior to Site Establishment and Commencement Onsite 10 days Mon 26/08/24 Fri 6/09/24 Lead-in Period Prior to Site Establishment and Commencement Onsite
10 CONSTRUCTION MILESTONES 304 days Mon 9/09/24 Fri 7/11/25 CONSTRUCTION MILESTONES
11 Site Possession 0 days Mon 9/09/24 Mon 9/09/24 Mon 9/09/24
12 PROJECT COMPLETION 0 days Fri 7/11/25 Fri 7/11/25 Fri 7/11/25
13 PROJECT COMPLETION (61 CALENDAR WEEKS CONSTRUCTION TIMEFRAME FROM SITE POSSESSION / START ONSITE) 0 days Fri 7/11/25 Fri 7/11/25 Fri 7/11/25
14 EARLY WORKS TRADE LETTING 30 days Mon 24/06/24 Fri 2/08/24 EARLY WORKS TRADE LETTING
15 CIVIL TRADES 10 days Mon 24/06/24 Fri 5/07/24 CIVIL TRADES
16 Negotiate and Award Civil Packages Including Inground Trunk Services 10 days Mon 24/06/24 Fri 5/07/24 Negotiate and Award Civil Packages Including Inground Trunk Services
17 STRUCTURAL TRADES 10 days Mon 8/07/24 Fri 19/07/24 STRUCTURAL TRADES
18 Negotiate and Award Formwork Concrete Reinforcing Packages 10 days Mon 8/07/24 Fri 19/07/24 Negotiate and Award Formwork Concrete Reinforcing Packages
19 SERVICES TRADES 10 days Mon 22/07/24 Fri 2/08/24 SERVICES TRADES
20 Negotiate and Award Services Packages 10 days Mon 22/07/24 Fri 2/08/24 Negotiate and Award Services Packages
21 REMAINING TRADE PACKAGE DOCUMENTATION 40 days Mon 5/08/24 Tue 1/10/24 REMAINING TRADE PACKAGE DOCUMENTATION
22 Remaining Trade Package Documentation 40 days Mon 5/08/24 Tue 1/10/24 Remaining Trade Package Documentation
23 LONG LEADTIME ITEMS 105 days Mon 12/08/24 Tue 28/01/25 LONG LEADTIME ITEMS
24 MAJOR PLANT AND EQUIPMENT (MECHANICAL AND ELECTRICAL) 60 days Mon 12/08/24 Thu 7/11/24 MAJOR PLANT AND EQUIPMENT (MECHANICAL AND ELECTRICAL)
25 Procure Mechanical and Electrical Services Plant and Equipment 60 days Mon 12/08/24 Thu 7/11/24 Procure Mechanical and Electrical Services Plant and Equipment
26 VERTICAL TRANSPORTATION (LIFTS) 100 days Mon 19/08/24 Tue 28/01/25 VERTICAL TRANSPORTATION (LIFTS)
27 Procure Lifts ~ 4 No. (20 Calendar Weeks ~ TBC) 100 days Mon 19/08/24 Tue 28/01/25 Procure Lifts ~ 4 No. (20 Calendar Weeks ~ TBC)
28 PLANT AND EQUIPMENT 221 days Fri 6/12/24 Fri 10/10/25 PLANT AND EQUIPMENT
29 CRANAGE 179 days Fri 6/12/24 Wed 13/08/25 CRANAGE
30 OVERALL DURATION ~ CRANE TYPE TO BE CONFIRMED (35.8 CALENDAR WEEKS APPROX.) 179 days Fri 6/12/24 Wed 13/08/25 OVERALL DURATION ~ CRANE TYPE TO BE CONFIRMED (35.8 CALENDAR WEEKS
31 Establish Crane 0 days Fri 6/12/24 Fri 6/12/24 Fri 6/12/24
32 Crane No Longer Required 0 days Wed 13/08/25 Wed 13/08/25 Wed 13/08/25
33 SCAFFOLD 147 days Thu 20/03/25 Fri 10/10/25 SCAFFOLD
34 OVERALL DURATION (29.4 CALENDAR WEEKS APPROX.) 147 days Thu 20/03/25 Fri 10/10/25 OVERALL DURATION (29.4 CALENDAR WEEKS APPROX.)
35 Erect Scaffold (With First Suspended Slab Cycle) 0 days Thu 20/03/25 Thu 20/03/25 Thu 20/03/25
36 Scaffold Drop Complete (All Elevations) 0 days Fri 10/10/25 Fri 10/10/25 Fri 10/10/25
37 CONSTRUCTION 274 days Mon 9/09/24 Fri 7/11/25 CONSTRUCTION
38 MOBILISATION AND SITE ESTABLISHMENT 5 days Mon 9/09/24 Fri 13/09/24 MOBILISATION AND SITE ESTABLISHMENT
39 Mobilisation and Site Establishment (Following Site Possession) 5 days Mon 9/09/24 Fri 13/09/24 Mobilisation and Site Establishment (Following Site Possession)
40 Implement Additional Silt Management Programme Including Hoardings 5 days Mon 9/09/24 Fri 13/09/24 Implement Additional Silt Management Programme Including Hoardings
41 Initial Survey and Setout 5 days Mon 9/09/24 Fri 13/09/24 Initial Survey and Setout
42 Setout of Services 5 days Mon 9/09/24 Fri 13/09/24 Setout of Services
43 DEMOLITION 15 days Mon 16/09/24 Tue 8/10/24 DEMOLITION
44 Demolition of Existing Vegetation, Site Services and Structures (As Required) 15 days Mon 16/09/24 Tue 8/10/24 Demolition of Existing Vegetation, Site Services and Structures (As Required)
Project: Sunshine Residences Task Summary Rolled Up Milestone External Tasks Inactive Milestone Duration-only Start-only External Milestone Progress
Run Date: Tue 11/06/24 Critical Task Rolled Up Task Rolled Up Progress Project Summary Inactive Summary Manual Summary Rollup Finish-only Critical Deadline
Milestone Rolled Up Critical Task Split Group By Summary Manual Task Manual Summary External Tasks Critical Split Slack
Page 1 of 3
PROPOSED DEVELOPMENT (SUNSHINE RESIDENCES), 65-67 ELANDA STREET, SUNSHINE BEACH QLD Tender Programme Rev A ~ 10.06.2024.mpp
TENDER PROGRAMME FOR BBN CONSTRUCTIONS
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (Appendix E - Construction Management Plan.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.