Appendix E - Construction Management Plan
PAGE 2 OF 3
ID Task Name Duration Early Start Early Finish
2024 2025
June July August September October November December January February March April May June July August September October November December January February Ma
27/05
3/06
10/06
17/06
24/06
1/07
8/07
15/07
22/07
29/07
5/08
12/08
19/08
26/08
2/09
9/09
16/09
23/09
30/09
7/10
14/10
21/10
28/10
4/11
11/11
18/11
25/11
2/12
9/12
16/12
23/12
30/12
6/01
13/01
20/01
27/01
3/02
10/02
17/02
24/02
3/03
10/03
17/03
24/03
31/03
7/04
14/04
21/04
28/04
5/05
12/05
19/05
26/05
2/06
9/06
16/06
23/06
30/06
7/07
14/07
21/07
28/07
4/08
11/08
18/08
25/08
1/09
8/09
15/09
22/09
29/09
6/10
13/10
20/10
27/10
3/11
10/11
17/11
24/11
1/12
8/12
15/12
22/12
29/12
5/01
12/01
19/01
26/01
2/02
9/02
16/02
23/02
2/03
9/0
45 CIVIL 45 days Wed 9/10/24 Thu 12/12/24 CIVIL
46 BULK EARTHWORKS 5 days Wed 9/10/24 Tue 15/10/24 BULK EARTHWORKS
47 Site Clear and Bulk Earthworks to Required RL's 5 days Wed 9/10/24 Tue 15/10/24 Site Clear and Bulk Earthworks to Required RL's
48 INGROUND CIVIL SERVICES 35 days Wed 16/10/24 Thu 5/12/24 INGROUND CIVIL SERVICES
49 Stormwater Pipe Work and Associated Inground Infrastructure 15 days Wed 16/10/24 Wed 6/11/24 Stormwater Pipe Work and Associated Inground Infrastructure
50 Sewer Reticulation 15 days Wed 23/10/24 Wed 13/11/24 Sewer Reticulation
51 Lay Underground Conduits (Electrical Services and Reticulation) 15 days Wed 23/10/24 Wed 13/11/24 Lay Underground Conduits (Electrical Services and Reticulation)
52 Install Water and Fire Services 15 days Wed 23/10/24 Wed 13/11/24 Install Water and Fire Services
53 Construct Underground Infiltration / Soakage Trenches 20 days Thu 7/11/24 Thu 5/12/24 Construct Underground Infiltration / Soakage Trenches
54 RETAINING WALLS 30 days Thu 31/10/24 Thu 12/12/24 RETAINING WALLS
55 Construct Blockwork Retaining Walls Including Footings Under 30 days Thu 31/10/24 Thu 12/12/24 Construct Blockwork Retaining Walls Including Footings Under
56 SUBSTRUCTURE 65 days Fri 6/12/24 Wed 26/03/25 SUBSTRUCTURE
57 GROUND FLOOR (RL 43290) 65 days Fri 6/12/24 Wed 26/03/25 GROUND FLOOR (RL 43290)
58 Northern Half of Building Footprint 55 days Fri 6/12/24 Tue 11/03/25 Northern Half of Building Footprint
59 Excavate and Form / Reo / Pour Footings 20 days Fri 6/12/24 Thu 16/01/25 Excavate and Form / Reo / Pour Footings
60 Construct Lift Pits (2 No.) 20 days Fri 13/12/24 Fri 24/01/25 Construct Lift Pits (2 No.)
61 Inground Services and Form / Reo / Pour Slab on Ground 15 days Fri 17/01/25 Mon 10/02/25 Inground Services and Form / Reo / Pour Slab on Ground
62 Construct Pool Shells (2 No.) and Allow to Cure 20 days Tue 11/02/25 Tue 11/03/25 Construct Pool Shells (2 No.) and Allow to Cure
63 Southern Half of Building Footprint 55 days Fri 20/12/24 Wed 26/03/25 Southern Half of Building Footprint
64 Excavate and Form / Reo / Pour Footings 20 days Fri 20/12/24 Mon 3/02/25 Excavate and Form / Reo / Pour Footings
65 Construct Lift Pits (2 No.) 20 days Fri 10/01/25 Mon 10/02/25 Construct Lift Pits (2 No.)
66 Inground Services and Form / Reo / Pour Slab on Ground 15 days Tue 4/02/25 Tue 25/02/25 Inground Services and Form / Reo / Pour Slab on Ground
67 Construct Pool Shells (2 No.) and Allow to Cure 20 days Wed 26/02/25 Wed 26/03/25 Construct Pool Shells (2 No.) and Allow to Cure
68 STRUCTURE 88 days Thu 20/03/25 Thu 31/07/25 STRUCTURE
69 FIRST FLOOR TO ROOF 88 days Thu 20/03/25 Thu 31/07/25 FIRST FLOOR TO ROOF
70 First Floor (RL 46350) 38 days Thu 20/03/25 Tue 20/05/25 First Floor (RL 46350)
71 Single Pour 38 days Thu 20/03/25 Tue 20/05/25 Single Pour
72 Erect Structural Verticals to Underside of First Floor Slab 10 days Thu 20/03/25 Wed 2/04/25 Erect Structural Verticals to Underside of First Floor Slab
73 Form / Reo / Pour Suspended Slab (First Floor) 16 days Thu 27/03/25 Tue 22/04/25 Form / Reo / Pour Suspended Slab (First Floor)
74 Initial Cure 7 days Wed 23/04/25 Tue 29/04/25 Initial Cure
75 Strip & Backprop 3 days Wed 30/04/25 Fri 2/05/25 Strip & Backprop
76 Final Cure and Remove Backprops 21 days Wed 30/04/25 Tue 20/05/25 Final Cure and Remove Backprops
77 Second Floor (RL 49410) 40 days Wed 23/04/25 Mon 23/06/25 Second Floor (RL 49410)
78 Single Pour 40 days Wed 23/04/25 Mon 23/06/25 Single Pour
79 Erect Structural Verticals to Underside of Second Floor Slab 10 days Wed 23/04/25 Thu 8/05/25 Erect Structural Verticals to Underside of Second Floor Slab
80 Form / Reo / Pour Suspended Slab (Second Floor) 16 days Thu 1/05/25 Mon 26/05/25 Form / Reo / Pour Suspended Slab (Second Floor)
81 Initial Cure 7 days Tue 27/05/25 Mon 2/06/25 Initial Cure
82 Strip & Backprop 3 days Tue 3/06/25 Thu 5/06/25 Strip & Backprop
83 Final Cure and Remove Backprops 21 days Tue 3/06/25 Mon 23/06/25 Final Cure and Remove Backprops
84 Roof Terrace RL (52470) 40 days Tue 27/05/25 Wed 23/07/25 Roof Terrace RL (52470)
85 Single Pour 40 days Tue 27/05/25 Wed 23/07/25 Single Pour
86 Erect Structural Verticals to Underside of Roof Terrace Slab 10 days Tue 27/05/25 Tue 10/06/25 Erect Structural Verticals to Underside of Roof Terrace Slab
87 Form / Reo / Pour Suspended Slab (Roof Terrace) 16 days Tue 3/06/25 Wed 25/06/25 Form / Reo / Pour Suspended Slab (Roof Terrace)
88 Initial Cure 7 days Thu 26/06/25 Wed 2/07/25 Initial Cure
89 Strip & Backprop 3 days Thu 3/07/25 Tue 8/07/25 Strip & Backprop
90 Final Cure and Remove Backprops 21 days Thu 3/07/25 Wed 23/07/25 Final Cure and Remove Backprops
91 Lift Overun Structures 25 days Thu 26/06/25 Thu 31/07/25 Lift Overun Structures
92 Construct Lift Overun Structures (4 No.) 25 days Thu 26/06/25 Thu 31/07/25 Construct Lift Overun Structures (4 No.)
Project: Sunshine Residences Task Summary Rolled Up Milestone External Tasks Inactive Milestone Duration-only Start-only External Milestone Progress
Run Date: Tue 11/06/24 Critical Task Rolled Up Task Rolled Up Progress Project Summary Inactive Summary Manual Summary Rollup Finish-only Critical Deadline
Milestone Rolled Up Critical Task Split Group By Summary Manual Task Manual Summary External Tasks Critical Split Slack
Page 2 of 3
PROPOSED DEVELOPMENT (SUNSHINE RESIDENCES), 65-67 ELANDA STREET, SUNSHINE BEACH QLD Tender Programme Rev A ~ 10.06.2024.mpp
TENDER PROGRAMME FOR BBN CONSTRUCTIONS
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (Appendix E - Construction Management Plan.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.