5865_R02_V06_Final_FEMP.docx
FIGURE A-6 SITE EVACUATION ROUTE (WATERTECH 2018)
The evacuation route from the site via Lake Weyba Drive to Eenie Creek Road overpass generally has a
minimum elevation of approximately 1.5m AHD based on the 2016 LIDAR data.
The evacuation route is impacted by floodwaters originating from the Noosa River catchment in events greater
than the 2% AEP flood event.