TOWN PLANNING CONSENT PERMIT - TPC 2500 Pages
8. Construction work and other associated activities are permitted only during the hours
of 7.00 a.m. to 6.00 p.m. Monday to Saturday. No work is permitted on public
holidays, except where extended hours are approved by the Building Surveyor.
9. All separate, adjoining lots that form part of this application are to be amalgamated
into one undivided lot in accordance with Section 5.11 of the Local Government
(Planning and Environment) Act, prior to the issue of a Building Approval.
10. Payment of contributions in accordance with Council's Policy on Water Supply and
Sewerage Headworks, current at the time of Building Approval. An estimate only
of the charges as at April, 1993under the current policy is as follows:-
Water Supply- $3043
Sewerage - $2226
TOTAL: $5269
Please note that the headworks charges will alter in accordance with Price Index
variations or if any amendment is made to Council's policy.
If payment is not proposed to be made prior to the issue of Building Approval, a cash
bond or trading bank guarantee for the required amount is to be lodged, prior to the
release of that Approval. The contribution is then required to be made within
fourteen (14) days of the issue of Building Approval.
11. The footpath across both frontages of the site are to be upgraded by the provision of
a 1.2 metres wide concrete footpath and the forming, grassing and topsoiling of the
remaining area to the satisfaction of the Shire Engineer. The footpath is to be
generally located 0.9 metres from the property alignment and is to be integrated with
any existing slopes and vegetation within the road reserve.
12. The developer shall bear the cost of alteration of any public utility or other facilities
necessitated by the development of the land or associated construction works
external to the site.
13. Connection to Council's existing water supply and sewerage reticulation systems at
the developer's expense to the standards and requirements of the Shire Engineer.
Document Set ID: 21970015
Version: 1, Version Date: 20/06/2022
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
002 ECM_21970015_v1_TPC 2500 - Approval.pdfRelated documentApplication case desk ↗
About this file
- File size
- 2.3 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.