Earthworks and Retaining Walls
44. All fill and associated batters must be undertaken in accordance with an Operational Works
approval, be generally in accordance with RECOR’s Bulk Earthworks Layout Plan (C020,
Rev. D) dated 18 September 2026 and contained entirely within the subject site unless
written permission from the respective landowner(s) is provided to Council.
45. All retaining walls must be designed and constructed in accordance with the planning scheme
and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that
are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade
safety fence.
Damage to Services and Assets
46. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
Roofwater Harvesting
47. Operating roofwater harvesting and detention tanks must be provided for the development.
The tanks must be provided in accordance with an approval for Building Works and must
include in particular:
a. the details identified in section 3.0 and 4.2.1.1 of RECOR’s Stormwater Management
Plan (P0478-26-001, Rev. 1) dated 24 June 2026;
b. a total tank capacity of 50 kilolitres for reuse and 50 kilolitres for detention;
c. a catchment of 100% of the building roof area;
d. re-use of harvested stormwater for internal non-potable uses and outdoor uses; and
e. The roofwater drainage system flowing to the tanks is to be designed to cater for the
1%AEP event including a 20% increase in rainfall intensity due to climate change.
Document Set ID: 25264554
Version: 1, Version Date: 22/10/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Council Report - 45 Maple Street, Cooroy (MCU23 0007 AND RAL23 0001) (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 17.0 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.