Attachment A Orginal approval and master plans

of 20

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
NOOSA COUNCIL IDAS Development Application Decision Notice


13. This Development Permit for a material change of use of premises lapses if:-
          13.1. the use or erection of a building or other structure associated with the use, has not happened by
                 19 May 2009, unless application is made and approved by Council for an extension; or

          13.2. the use of any premises pursuant to the Development permit ceases.

Land Development
Carparking Off Street
14. Carparking shall be provided within the site as shown on Dhamma Rasmi - Master plan prepared by Bal
          Salrai LFRAIA Architect, except as modified herein.

15. A minimum of 25 uncovered carpark spaces shall be provided on site, including 1 clearly defined disabled
          carpark space.

16. The carparking area shall be designed to comply with the provisions of AS 28g0.1-2004 for user class               1
          with allowance for vehicles to enter and leave the site in a forward gear,

17. All carparking shall be kept, maintained and line-marked in a condition fit for use,
18. The carparking area shall be drained and the pavement constructed to access road standards. plans and
          specifications for these works shall be submitted in conjunction with an application for a Development
          Permit for Operational Works.
Pathways
'1   9.   A contribution toward pathways external to the site within the Pomona pathway catchment shall be paid
          prior to the commencement of the use, in accordance with Council's policy for contributions for pathways.
          The amount of the contribution shall be calculated at the rate current at the date of payment. An estimite
          only of the contribution rate at June 2004 was 9780 for the development.
Vegetation Protection
20.       Pavements within the drip zone of any of the existing trees on site to be retained shall be designed as a
          pervious pavement (such as grass paving cells or similar), as this will allow water that falls on thls surface
          to penetrate to the trees root system. The pavement shall be constructed so as not to damage the tree or
          their root system and in this regard temporary fencing shall be provided around the lrees during
          construction to help protect them.

          Plans shall be submitted to the Council for approval that clearly show the type and extent of the pervious
          pavement and the temporary fencing prior to obtaining a Development Permit for Operational Works.

Stormwater Drainage
21   .    All stormwater drainage shall be collected on site and discharged so there is no net increase in
          stormwater runoff from the site.

22.       All site stormwater drainage shall be by means of a gravity system.

23.       Roof runoff shall be directed to a rainwater storage system or tank (minimum storage 1000 litres) that is
          plumbed to service the toilets and bathroom of each new cabin. The design of the ralnwater storage
          system shall be to the satisfaction of the Manager Plumbing Services.

24. To ensure that polluted run-off does not enter the tributary of Cooroora Creek, stormwater run-off from the
          carparking areas and the driveways shall have the first flush (the first 12 mm of rainfall or hose-down)
          treated via a grassed swale or similar treatment system using Water Sensitive Urban Design principles.
Effluent Disposal
25. The design and construction of any on-site effluent disposal system and disposal area (land application
          area) shall be in accordance with Council's Planning Scheme Policy PSP2g On-Slfe Domestic
          Wastewater Systems.

          Specifically, the land application area shall be positioned to achieve the greatest possible setback to the
          dam and to any permanent or intermittent watercourse.




SEP p:\civica\documents\dd\01   0\from5000\01 0-2004-00005633-001\0006decnotice.doc
Log in to download the original file

Attachment A Orginal approval and master plans.pdf · 4.4 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.