NOOSA COUNCIL IDAS Development Application Decision Notice




                                                 Noosa Gouncil Gonditions
                                                  INTEGRATED PLANN/NG ACT 1 997, IDAS DEVELOPMENT APPLICATION


Land Use
1.      Development undertaken in accordance with this approval must generally comply with the approved plans
        of development. The approved plans are numbered Dhamma Rasmi - Master Plan prepared by Bal Salrai
        LFRAIA Architect as included with the application; Reception/ Administration Office Drawing prepared by
        Bal Salrai Architect and dated 10 September 2004; VSQ-002C1 to VSQ-002C3; VSQ-002B1 to VSQ-
        00282; VSQ-002A1 to VSQ-002A3 prepared by Bal SalraiArchitect and dated 16 November 2004 and as
        may be amended by these conditions.

2,       The development must be undertaken and operated in a manner that causes no detrimental effect upon
         the amenity of the neighbourhood by reason of the creation of excessive noise, lighting nuisance or other
         emissions.

3.       The disturbed areas in the vicinity of the new building extension and the new 5 bay car park adjoining the
         reception office are to be landscaped in accordance with Council's Policy on Landscaping Guidelines and
         a properly prepared landscape plan prepared by a suitably qualified Landscape Architect or
         Horticulturalist. Such landscaping is to be completed prior to the new building extension being occupied
         and maintained at all times thereafter.

4.       Existing trees on the site and within road reserves are to be retained, except where required to be
         removed due to building operations or the conduct of the approved use. These landscape plans required
         to be submitted are to denote areas of existing vegetation or any existing trees proposed or required to be
         retained.

5.       No part of the building extension shall exceed a height of 9m to the peak or ridge of any pitched roof, and
         8m elsewhere above the natural ground level and the finished ground level.

6.       Any advertising sign or device is to comply with Council's policies on advertising.

7.       Security in the form of a cash bond or trading bank guarantee to the sum of $5000 must be submitted, to
         secure performance of all conditions of this approval, prior to the issue of a Development Permit for
         operational works. The cash bond or trading bank guarantee will be returned on performance of the
         conditions of approval less any costs incurred by Council in respect of enforcing performance of this
         Dermit.

8.       The requirements of this development approval are to be effected, prior to the use of the premises.
         Council reseryes the right to call upon the bond or guaranteed sum referred to in this approval to effect
         compliance with conditions.

 9.      The developer must obtain all of the other Development Permits referred to in the Decision Notice, prior to
         obtaining a Development Permit for Building Works.

 10. The maximum number of people to be accommodated on site is 52, which includes all teaching,
          caretaking and other staff.

 11. The proposed development shall have all bathroom fittings comply with the AAA Water Conservation
          Rating System as defined by the AS/NZS 6400 (Water Efficient Products - Rating and Labelling 2003) and
          AS/NZS 3500 (National Plumbing and Drainage Standard Part1.2), with toilets to comply with the AAAA
          Water Conservation Rating System, All tap ware and shower roses shall not exceed a maximum flow of 9
          litres per min.

 12. All additional hot water systems shall be either solar systems; electric heat pump systems; or gas systems
          (LPG or natural).

 13. This Development Permit for a material change of use of premises lapses if:-




 S E P c :\d atawrk s\te m p\1 2 223 33\5 633n d n. do c
Log in to download the original file

Attachment A Orginal approval and master plans.pdf · 4.4 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.