2022-08-18 Ordinary Meeting Minutes

of 55

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (10.0 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

ORDINARY MEETING MINUTES   18 AUGUST 2022




                            Page 41 of 55

ORDINARY MEETING MINUTES                                                                      18 AUGUST 2022

     Corporate Plan Key   Operational Initiatives       Outcomes                  Responsible     Update                                         Status Q3     er.)
     Focus Areas                                                                  Areas/Officers
     2.2 Adopt and        Implement priority activities | Delivery of better social Community     21/22 Cultural Action Plan —Key priority activities |On track | Ontrack
     implement the        from the Cultural Plan,       outcomes including a      Development/ | underway including: ITQ for Stage 2 Gallery Pre-
     following plans that | Community Health and        cohesive resilient        Community       Feasibility study; Shirewide Liveability Survey;
     form part of our     Wellbeing Plan and the Sport | community, an active and | Development   ae & Local     ee Program; and
     Noosa Social         and Active Recreation Plan    healthy community, an     Manager         vena       tame      Se       ial
     Strategy - Cultural                                accessible diverse and                      aiibatleay: Gus.
     Plan, Community                                    affordable community
     Health and                                                                                   Sport and Active Recreation Plan - Key
     Wellbeing Plan and                                                                           recommendations currently being implemented
     the Sport and                                                                                including Feasibility for non-powered water sports
     Active Recreation                                                                            — tender closed and consultant appointed; Noosa
    Plan                                                                                          Cycling and Walking strategy and implementation
                                                                                                  plan completed and endorsed; Noosa Trails
                                                                                                  network master plan implementation underway;
                                                                                                  and Sport infrastructure improvements including
                                                                                                  LED lighting for sports fields.
                          Deliver Floating Land 2021    Increased access to and   Galleries/      Floating Land: at the edge of ideas delivered 9" | Completed) Completed
                          event                         participation in arts and Gallery         to 24th October. In excess of 30 installations and
                                                        culture                   Director        performances delivered across Boreen Point and
                                                                                                  Park Road Boardwalk.
                          Annual Christmas convoy       Increased community       Community       Completed 6t — 9th December 2021.              Completed| Completed
                                                        connectedness             Development/
                                                                                  Community
                                                                                  Development
                                                                                  Manager
     2.3 Implement the    New Mobile Library and        Accessible and            Libraries/      Vehicle tender awarded in July 2021 — supplier Behind     Behind
     Libraries Strategic  Community Outreach Service | contemporary outreach      Libraries &     delay with vehicle arriving in Australia — new Schedule | Schedule
     Plan                 is planned and implemented | library services           Galleries       project schedule provided with ETA on delivery
                                                                                  Manager         for October — tentative date of launch Dec/Jan;
                                                                                                  Kiosk installed at Peregian Community House
                                                                                                  and will be operational by end of July. Kiosk for
                                                                                                  Pomona Community House ordered and due
                                                                                                  July/August; New suite of library outreach
                                                                                                  programs developed and being delivered. Three
                                                                                                  initial focus locations — Pomona, Peregian and
                                                                                                  Kin Kin.
     2.4 Continue to      Continue the construction of | Completion of site       Director        Construction of new Peregian Beach Community | Behind     On track
     support our          Stage 3 of the Rufous Street | construction andthe new | Community      House is now complete with soft opening        Schedule
     community to utilise | project incl. the construction | neighbourhood centre Services        undertaken. Concept design for refit of old
     Council controlled   of the new Peregian Beach     which will strengthen                     community house drafted. Tender process
     land and buildings   Community House.              community connection                      underway for refit of old community house.

                                                                                                 Page 41 of 55
Log in to download the original file

2022-08-18 Ordinary Meeting Minutes(PDF, 10MB).pdf · 10.0 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.