ORDINARY MEETING AGENDA 25 SEPTEMBER 2014
Damage to Services and Assets
20. Any damage caused to existing services and assets as a result of the
development works must be repaired at no cost to the asset owner at the
following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety,
immediately; or
b. where otherwise, upon completion of the works associated with the
development.
Any repair work which proposes to alter the alignment or level of existing
services and assets must first be referred to the relevant service authority for
approval.
UNITYWATER
Important Advisory Note - The following Unitywater conditions are applied in accordance
with the Chapter 4c, part 7 and sections 135 and 140(c) South East Queensland (Distribution
and Retail) Restructuring Act 2009 and Unitywater’s Interim Connections Policy. The
conditions below form part of a water connection aspect which are taken to be a water
approval for a staged connection. You are entitled to appeal against the water connection
aspects of this application in accordance with section 99BRAY and Chapter 4c, part 4,
Divisions 1 and 2 of the South East Queensland (Distribution and Retail) Restructuring Act
2009. Unitywater can be contacted as follows:
Phone: 1300 0 Unity (1300 086 489)
Email: [email protected]
Web: www.unitywater.com.
Water Connections
21. Reticulated water must be provided to each lot in the development. This must
include:
a. Ensuring that existing internal water pipes are wholly contained within the
lot they will serve;
b. An approved water meter for each lot in accordance with Unitywater and
SEQ Standard Drawings;
c. Provision of a water service from the existing 150 mm diameter water
main that runs across the lot to service all proposed and future lots in
accordance with Unitywater and SEQ Standard Drawings.
22. Tree plantings must maintain a minimum horizontal clearance of 1.0 metre from
Unitywater water mains. Landscaping plants within these clearances must be
low growing when mature and suitable Unitywater approved varieties.
23. Written approval to enter and construct must be obtained from the owners of
properties through which external water mains will traverse. This must include
approval for a 3 meter wide easement over the mains, and be submitted with
lodgement of the associated development application for Operational Works.
24. Construction works undertaken in the vicinity of Unitywater water supply or
sewerage infrastructure must not adversely affect the integrity of the
infrastructure. All costs associated with repair, replacement or alteration of
infrastructure must be met by the applicant.
Page 27 of 29
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.