Negotiated Approved Plans - MCU26/0040, OPW26/0066 & RAL26/0013 (As Published)
Original PDF page 7, section 1. The text section number identifies this passage in the reader.
NOTE:-
END OF TRIP FACILITIES TO BE PROVIDED IN EACH TENANCY
BUILDING D
BUILDING B BUILDING C
TRIMDEK ROOF SHEETING
TRIMDEK ROOF SHEETING
BUILDING A
PART 01 PART 02
@ MIN 2o PITCH
@ MIN 2o PITCH
FALL
FALL
03 KEY PLAN
- LEVEL 1 Scale @ A3 1:2500
STAGE LEGEND
STAGE 1 BOUNDARY
STAGE 2 BOUNDARY
01 FLOOR PLAN - BUILDING A STAGE 3 BOUNDARY NORTH
- LEVEL 2 - PART 01 Scale @ A3 1:200 STAGE 4 BOUNDARY
STAGE 5 BOUNDARY
A
20
TRIMDEK ROOF SHEETING
@ MIN 2o PITCH
J1 26.09.28 Elevations on sheet 25 amended ST DJ
FALL
J 26.08.31 DA Revision ST DJ
i 26.05.29 DA Revised civil Issue C inserted ST DJ
H 26.05.26 Revised civil Issue C inserted ST DJ
G 18.05.26 Revised Area schedule ST DJ
F 14.05.26 Concrete panel to caretakers ST DJ
E 14.05.26 Preliminary WD Buildings A & B for coordination ST DJ
D 14.05.26 RFI response with Civil Rev B added ST DJ
C 01.05.26 Revised stages & bin locations ST DJ
B 30.04.26 550mm setback to Bldg D Tenancies 37 - 47 ST DJ
A 27.02.26 Preliminary DA Issue ST DJ
REMI RAFTER
LOT 18 TAYLOR COURT
COOROY
NOOSA COUNCIL
APPROVED PLAN
A
MCU26/0040, OPW26/0066 & RAL26/0013 ROOF PLAN - BUIDING A _ LEVEL 3
20 1 OCTOBER 2026 ST DJ
02 FLOOR PLAN - BUILDING A As Indicated 03.12.25
- LEVEL 2 - PART 02 Scale @ A3 1:200
MATERIAL CHANGE OF USE FOR LOW IMPACT INDUSTRY AND 2025-68 07
ANCILLARY TRANSPORT DEPOT (CONTRACTORS DEPOT) DA DRAWINGS J1
GSPublisherVersion 676.0.97.0
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.