5 WATER QUALITY ANALYSIS
Stormwater quality modelling is based on split surface areas and their associated export pollutant
load. As per Table 1, above, the roof area increases by approximately 1,200 m2, while the road
area decreases by approximately 1,200m2. In accordance with MUSIC Modelling Guidelines, roof
pollutant export values are significantly less than road pollutant export parameters (see Table 3). As
such, it could be expected that stormwater pollutant loads would decrease with the proposed
developed. Therefore, no additional stormwater quality improvement devices are required.
Table 3. Pollutant Export Parameters.
Pollutant Export Parameters for Split Catchment Land-use (Log10 values)
Land Split Flow Type TSS TP TN
Use Mean Std. Dev Mean Std. Dev Mean Std. Dev
Roof Baseflow N/A N/A N/A N/A N/A N/A
Stormflow 1.3 0.38 -0.89 0.34 0.37 0.34
Commercial
Roads Baseflow 0.78 0.39 -0.6 0.5 0.32 0.3
Stormflow 2.43 0.38 -0.3 0.34 0.37 0.34
Ground Baseflow 0.78 0.39 -0.6 0.5 0.32 0.3
Stormflow 2.16 0.38 -0.39 0.34 0.37 0.34
Source: Table 3.9 (MUSIC Modelling Guidelines).
6 CONCLUSION
As there have been no significant changes to the overall impervious area associated with the
proposed Arts Centre, it has been determined that no additional detention or stormwater quality
improvement devices are required. This advice is based on the current Masterplan layout (Burling
Brown’s drawing: GSL05-SK-02, Dated 24/2/23) and aligns with QUDM (2017) and MUSIC Modelling
Guidelines (2018) requirements, and Noosa Shire Council requirements.
If Council require further explanation of the above or additional information, please contact the
undersigned at [email protected] DISCLAIMER
This report is prepared by Colliers for exclusive use by its client only. No responsibility is accepted for
the use of or reliance upon this report in whole or in part by any third party.
The sole purpose of this report and the associated services performed by Colliers is to display
information in accordance with the scope of services set out in the contract/quotation between
Colliers and its client. The scope of works and services were defined by the requests of the client,
by the time and budgetary constraints imposed by the client, and by the availability of access to
site/s and information.
This report is prepared with information supplied by the client and possibly others which is presumed
to be accurate and complete. No responsibility is accepted for information that is withheld,
incorrect or that is inaccurate, nor for changes to the conditions over the passage of time or from
latent circumstance or conditions. No warranty or guarantee is made in relation to the data,
findings and conclusions expressed in this report.
Technical Memo | 21-0211TM-SW01-v3 |Good Shepherd Page 4
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Stormwater Technical Memo.pdfRelated documentApplication case desk ↗
About this file
- File size
- 517 KB (small file)
- File type
No other editions are linked here.