Original source · versioned page text
13. Existing DMP (2006)
1.55 Emergency response and contingency plans
A risk management matrix is shown in table 3 below.
Risk Trigger Action
Acid sulphate PH monitoring Assess area prior to dredging and exclude from
exposure and dredging if ASS soils occurs within the site.
observation Proceed in areas with adjusted dredge depth.
Excess Turbidity Cease dredging, modify dredge operations to
turbidity monitoring reduce turbidity
Excess S.S. Cease dredging, modify dredge operations to
suspended monitoring reduce S.S
solids
Fuel spill Fuel spill As per Oil Spill Contingency Response Plan.
report
Seagrass Observation by Inspect area prior to dredging and exclude from
damage Council officer dredging if seagrass occurs within site.
and Seagrass
monitoring
Rep.
1.56 Education & training
Dredge operators and relevant Council Staff are to be provided with education and
training on environmental issues of air, noise, water and waste as indicated in this
document.