13. Existing DMP (2006)
1.57 Environmental management reports
Notification to EPA will be provided 40 days prior to dredge works. The notification
will include:
Location and quantities
Timetable of works
Depth of water and bottom topography
Current velocities, tidal movements and dispersal of sediments
Sampling program
Acid sulphate investigations
Particle type & size
Contingency plans
Contact details
Potential impacts
Information permits and conditions from other authorities
Management techniques to environmental harm
Weekly reports on the dredge operations will be kept by Council Works Department
at Pelican Street, Tewantin and be made available to EPA if required. The reports will
be kept for five years and annual summaries provided to EPA. The report will address
sand dredging volumes, results of water, noise, air and waste monitoring. A sample
weekly report form is shown attached.
2.0 Activity specific information
2.1 Description of processes
2.11 Plant and machinery
The dredge operator will be contracted as per Local Government procurement
guidelines. Broadwater Dredging have expressed an interest in the dredging works
and attached are details of the plant and machinery specifications.
11