14. The person acting on this permit shall ensure that its consultants and contractors take all reasonable care
during the construction of the engineering works to ensure that Council property, road pavements or
facilities (such as underground drainage, water supply, sewerage, footpaths, kerbing, landscaping, street
furniture etc.) are protected against any damage or interference whatsoever.
If any Council property or facilities should be damaged by the Applicant or any of its Consultants or
Contractors through any cause whatsoever in the course of, directly or indirectly, carrying out the
engineering works, the Applicant and/or its Contractors shall forthwith notify the Manager Land
Development and shall forthwith rectify the damage to that property or facility at its cost and to the
satisfaction of the Manager Land Development.
All rectification works are to be completed prior to the sealing of the survey plan or, alternatively, the
Applicant may request the Council to carry out the rectification work at the Applicant’s cost, such cost
being paid by the Applicant to the Council prior to the sealing of the survey plan.
In the case of any emergency the Council shall be entitled to rectify such damage at the cost of the
Applicant, such cost being paid prior to the sealing of the survey plan.
15. The development of the site shall be carried out in such a manner as to prevent dust and/or sand
nuisance to residents and/or tenants in the vicinity of the development.
16. Construction work and other associated activities are permitted only during the hours of 7.00 am and 6.00
pm Monday to Saturday. No work is permitted on Sundays or public holidays, except where extended
hours are approved by the Manager-Land Development or his nominee.
17. All signage, including that for safety during construction shall be in accordance with the Manual of Uniform
Traffic Control Devices and Traffic Infrastructure (Roads) Act.
18. Sediment and erosion control measures must be in place prior to works commencing. If such measures
are not in place or are not satisfactory, “on the spot “fines may be issued. Such fines can be issued if
sediments from the site are found to enter or have the potential to enter Council’s stormwater system or
natural waterways. Council’s Manager – Land Development may request further controls to be installed
should approved measures be inefficient.
19. A 5% cost of works to become Council assets or $1,500 bond (whichever is the greater) will be imposed
on construction works during the maintenance period, which is a minimum period of 12 months duration.
Such bond must be lodged by, and shall only be accepted from the Developer for the works.
20. The works to become Council assets will not be accepted "On Maintenance" until the landscaping is
completed.
21. These works are also to be in compliance with the relevant conditions of Development Permit No.
2006/1354.
22. Pursuant to Section 3.5.21(5) of the Integrated Planning Act 1997, the Relevant Period is two (2) years
from the day this permit takes effect (7 November 2009) during which time all conditions must have been
complied with and the Plan of Survey lodged with the Council for endorsement.
23. Notwithstanding that Council has checked the plans with due care, where it is found during construction
that variations from Council's standards exist, then Council standards shall apply.
NSC c:\docume~1\rhr\locals~1\temp\bcl technologies\easypdf 5\@bcl@a4017bc0\@[email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - 010.2007.00001849.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 30 KB (small file)
- File type
No other editions are linked here.