Landscaping
10. A minimum of 20% of the site must be retained as soft landscaping.
11. To screen the development, screening vegetation must be planted for the
full length of the north and south boundaries, with the exception of the
bin/gas/bike store area, in accordance with Council’s Planning Scheme
Policy PSP2 - Landscaping. The planted vegetation must have a minimum
pot size of 200mm and consist of native, endemic species with a mature
height of not less than 8 metres and a maximum spacing of 2 metre centres.
12. A mix of native landscaping, such as ground covers, shrubs and trees, is
provided for a width of 5 metres from the seaward or rear boundary of the
site. The planted vegetation must have a minimum pot size of 200mm and
consist of native, endemic species as per Table 3.1 & 3.2 of PSP2
Landscaping for suitable coastal species. The planted vegetation must be
planted at the following density:
a. trees must have a maximum spacing of 6m;
b. shrubs must have a maximum spacing of 1.5m; and
c. ground covers planted between the trees and shrub must achieve a
dense coverage.
13. The development is to provide adequate landscape buffering to protect the
character of the beachfront, to the reasonable satisfaction of the Manager
Development Assessment.
14. Two 100 litre street trees must be provided within the frontage. The trees
must be a coastal species in accordance with PSP2 – Landscaping.
Coastal Protection
15. External colours and finishes of the building must comprise of
muted/environmental tones that blend with the natural environment.
Pedestrian Access
16. A pedestrian access gate must not be installed along the seaward property
boundary with direct access by residents to the beachfront area not being
permitted.
Geotechnical Stability
17. A footing system and erosion protection system must be designed for the
proposed development to withstand the short-term erosion associated with
a 500-year average recurrence interval storm event combined with
shoreline recession due to sea-level rise for 2100 climate change. The
short-term erosion associated with a 500-year average recurrence interval
storm event combined with shoreline recession due to sea-level rise for
2100 climate change to be considered for the design as per the
recommendations of the Royal Haskoing DHV report ‘Report 66 Seaview
Terrace, Sunshine Beach Coastal Hazards Assessment, reference
PA2906-RHD-ZZ-XX-RP-Z-0001 dated 3 June 2022.
18. The footing system and erosion protection system must in accordance with
the works detailed in the Tectonic report “Geotechnical Investigation,
Proposed residence 66 Seaview Terrace, Sunshine Beach”, (Reference
21370-001-Rev 1 dated 28 April 2022) and other supporting documents
referenced in the Tectonic report.
19. The design must include the protection of the northern and southern
boundaries of the site to prevent erosion on neighbouring properties
Page 11 of 21
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.