GENERAL COMMITTEE MEETING MINUTES 12 SEPTEMBER 2022
Plan No. Rev. Plan/Document Name Date
300.00 H Building Elevations – elevation west 01.09.2022
300.01 H Building Elevations – elevation north 01.09.2022
300.02 H Building Elevations – elevation east 01.09.2022
300.03 H Building Elevations – elevation south 01.09.2022
640.00 A Landscape details – detail driveway plan 06.05.2022
640.01 A Landscape details – driveway detail section 06.05.2022
Amended Plans
3. Prior to the issue of any further development approvals amended plans
must be submitted to Council. The plans must remove the roof top terrace.
The plans must be to the satisfaction of the Manager, Development
Assessment.
Approved Documents
4. Development must be undertaken strictly under the approved documents
listed in the following table unless otherwise amended by these conditions.
Document
Tectonic report “Geotechnical Investigation, Proposed residence 66
Seaview Terrace, Sunshine Beach”, reference 21370-001-Rev 1 dated 28
April 2022
Royal Haskoing DHV report ‘Report 66 Seaview Terrace, Sunshine Beach
Coastal Hazards Assessment, reference PA2906-RHD-ZZ-XX-RP-Z-0001
dated 3 June 2022
Built form
5. The maximum height of the development must not exceed 8 metres above
ground level in accordance with the approved plans.
6. Certification must be submitted to Council from a Licensed Surveyor which
certifies that the building does not exceed the maximum height requirement
of this Decision Notice.
7. The proposed Detached House must be located on the site, as shown on
the Site Plan, Drawing No. 100.00, Revision J. The Detached House is not
to be located closer than 10.5m to the seaward boundary, except for the
cantilevered part of the building which is not to extend closer than 7.5m to
the seaward boundary. Certification of the location of the Detached House,
including the cantilevered section from the seaward boundary, is to be
provided by a licenced surveyor before the issue of a final classification for
the Detached House by the building certifier. The certification must be
submitted to Council.
Currency Period
8. This development approval lapses if the use has not happened by 21 July
2028, unless an application to extend the currency period is approved by
Council.
Performance Bond
9. Security in the form of a cash bond or trading bank guarantee to the sum
of $20,000 must be submitted to Council, to secure performance of all
conditions of this approval, prior to the issue of a Development Permit for
Building Works. The cash bond or trading bank guarantee will be returned
on performance of the conditions of approval less any costs incurred by
Council in respect of enforcing performance of this permit. Council reserves
the right to call upon the bond or guaranteed sum to effect compliance with
conditions.
Page 10 of 21
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.