2004/4386
The detailed deigns shall then be submitted to ENERGEX for approval and a copy of their
approval submitted to Council in conjunction with a “Certificate of Electricity Supply for
Proposed Subdivisions” (prepared by an approved ENERGEX Electrical Design Consultant)
prior to Council endorsing the Plan of Survey.
Any agreement with ENERGEX or an approved ENERGEX Electrical Design Consultant shall
be wholly at the applicant’s expense and shall not entail a financial encumbrance on future
purchasers of the proposed lots.
24. The requirements for TELECOMMUNICATION services shall be satisfied in relation to the
provision of new telephone services to the proposed lots. In this regard written confirmation
from an approved telecommunication agency shall be submitted to the Council prior to Council
endorsing the Plan of Survey.
25. Any person acting on this permit shall prevent erosion and sediment export from leaving the
site. Site control measures such as silt fencing, controlled gravel access to the site and
controlled disposal of waste, will be necessary.
In this regard plans detailing the methods of controlling erosion and sediment are required to
be submitted to the Council for approval prior to obtaining a Development Permit for
Operational Works.
26. Any damage caused to any public utility during the course of construction shall be repaired to
Council’s standards and at no cost to Council.
27. Any alteration of any public utility or other facilities necessitated by the development of the
land or associated construction works external to the site shall be at no cost to Council.
28. The transportation of all materials to and from the site shall be undertaken in a manner such
that no particle matter escapes onto a public road. All vehicles carrying materials either to or
from the site shall be covered to prevent materials including dust being windblown from the
vehicle.
29. A Registered Professional Engineer of Queensland shall certify engineering drawings and
specifications for all engineering works, which shall be submitted in conjunction with an
application for a Development Permit for Operational Works.
30. For the following classes of work associated with development, a Development Permit for
Operational Works must be obtained prior to commencement of works relating to that class of
work. The application may combine any or all of these classes of work:-
Access and Carparking.
Stormwater Drainage.
Frontage Works.
Landscaping.
5 REFERRAL AGENCY CONDITIONS
The referral agencies applicable to this application are:
Referral Trigger Referral Status Referral Agency Referral Address
Contaminated Land Unit
Environmental Protection
Contaminated land Concurrence PO Box 155
Agency
Brisbane Qld 4002
A copy of any referral agency conditions is attached.
Page 4 of 9
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Letter - Change to an Existing Approval - 010.2004.00004386.002 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 65 KB (small file)
- File type
No other editions are linked here.