Response to Information Request - April 2019 Final

Attached to the e-mail Response to Information Request - RAL18/0023.

of 14

Page text shows just the words. Original shows the document exactly as it was published.

           o   the management works being the responsibility of the owner of Lot 12.

   •   it is recommended that proposed Lots 12-15 are each provided with a fire hydrant with a hose
       and reel along the outer boundary of each lot adjoining the parkland to the south; and

   •   the proposed extension of the previously approved development will materially improve the
       bushfire safety for the entire precinct. The SPP Hazard Mapping confirms the need for a set of
       mitigating actions to ensure the safety of people and property. The details in section four of this
       Bushfire Management Plan confirm the capacity to comply with the current Noosa Plan Natural
       Hazards Overlay Code.

13. Provide a concept management plan for the open space areas which addresses the
    management of these lands, including bushfire, tree/limb drop, weed control and other
    matters as deemed relevant.

Response

   As above Gondwana Ecology Group have prepared a Flora Survey Report which also
   responds to Item 13 of the Information Request.

In summary, Gondwana Ecology Group advise:

   •   areas proposed as covenants to the east of Lots 2 and 7 to 11 (i.e. west of Walter Hay
       Drive) and south of Lots 23 to 25 (i.e. north of Walter Hay Drive) are for screening and
       buffering purposes, forming part of OS3 and primarily for the preservation of visual
       amenity;

   •   the area to the south of Lot 12 (Covenant L), which is an environmental buffer area for
       the setback to Eenie Creek and also for the management of bushfire to some extent
       (referred to below);

   •   the area to the west (Covenant K) required primarily for stormwater drainage purposes
       (OS5);

   •   areas in the west (Covenant J) which is to be retained for stormwater drainage purposes
       (OS7 – Environmental Drainage). No activities are necessary within these areas prior to
       vegetation clearing the subject land. Activities immediately prior to vegetation clearing
       would require the installation of temporary protective fencing. It is intended that
       protective fencing be provided around large trees (i.e. trees on boundary to be retained
       within the covenant area). Both tree protection measures and the associated setbacks
       are to be incorporated into the management of these areas;

   •   it is also proposed that rehabilitation will occur along the open space boundary
       immediately adjacent to the development area (i.e. following all construction works) to
       reinstate any disturbance due to fencing and edge effects;

   •   with respect to Covenant L (proposed Lot 12), this is to be also managed as a bushfire
Log in to download the original file

Response to Information Request - April 2019 Final.pdf · 1.0 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.