MCU16/0012 Attach B Engineering report & SMP
Original PDF page 15, section 1. The text section number identifies this passage in the reader.
ENG
Engineering Report & Stormwater Management Plan
Date: 24/06/2016 Document No.: 15087-ENG-01.Docx
By: MRS Revision No.: C
Figure 7.2 shows a sewer main behind the site, running from north to south with an existing
property connection in Wimmer’s Lane.
SITE
Figure 7.2: Existing sewer Infrastructure (DBYD)
A new 150dia sewer connection will be provided from the main in Wimmer’s Lane to the
proposed development to Unitywater standards.
For more details of the sewer reticulation refer to the engineering plans in Appendix B.
Internal house drainage design for this proposed development will be by others.
8. Water Reticulation
Figure 6.3 shows the existing water reticulation infrastructure for the proposed site. A hydrant
is situated adjacent to the site in Garnet Street.
A PO Box 26, Carina Q 4152 14 | P a g e
E [email protected]
W www.vtce.com.au
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.