Engineering Report & Stormwater Management Plan
Date: 24/06/2016 Document No.: 15087-ENG-01.Docx
By: MRS Revision No.: C
Site
Figure 5.1: Lake Macdonald Water Supply Catchment Adjacent to Site
The site currently hosts a stormwater easement for a 525 diameter pipe which traverses from
Garnet Street to Wimmer’s Lane at the rear. It is proposed to upgrade this pipe to 750
diameter and reroute it around the proposed building, to the vicinity of the existing sewer line
through the property and back to the existing manhole in Wimmer’s Lane. It is anticipated
that this will require 2 sag gullies in Garnet Street to accommodate the capture of surface
stormwater flow from a Q100 event. Calculations are shown in Appendix G.
a. Stormwater Quality Management
State Planning Policy
The State Planning Policy April 2016 applies for stormwater quality management and
management of new or expanded non-tidal artificial waterways applies to development that is
outlined below in Table 5.1.
A PO Box 26, Carina Q 4152 7|P a g e
E [email protected]
W www.vtce.com.au
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.