                                                  Engineering Report & Stormwater Management Plan
                                          Date:          24/06/2016     Document No.:        15087-ENG-01.Docx

                                           By:              MRS          Revision No.:              C


          SPP2016 PART E: INTERIM DEVELOPMENT ASSESSMENT
                                                                                         YES / NO
           REQUIREMENTS. STATE INTEREST – WATER QUALITY
     Material change of use for urban purposes that involves a land area
     greater than 2500m2 that:
        will result in an impervious area greater than 25% of the net
        developable area                                                                   YES
          Will result in 6 or more dwellings                                               NO
     Reconfiguring a lot for urban purposes that involves a land area
     greater than 2500m2 and will result in six or more lots:                              NO
     Operational works for urban purposes that involve disturbing more
     than 2500m2 of land
                                                                                           YES
      Table 5.1:      Water Quality Objectives

As the proposed development triggers one or more applicable items in the above Table 5.1,
the State Planning Policy April 2016 is applicable and compliance will be expected by the local
government authority.

To achieve the above State Planning Policy outcomes the development is to:
     avoid or minimise development impacts arising from altered stormwater quality and
        flow by providing for development and construction activities in accordance with
        acceptable design objectives
     avoid or minimise development impacts of waste water (other than contaminated
        stormwater) on water quality objectives
     avoid or minimise development impacts arising from the creation or expansion of
        non-tidal artificial waterways such as urban lakes

The proposed development will comply with the State Planning Policy April 2016 – Water
Quality policies.

A copy of the completed State Planning Policy April 2016 —Water Quality development
assessment code is attached in Appendix E.


                     b. Water Quality Objectives
Water quality parameters and the proposed limits applicable to this site have been selected in
accordance with SPP2016 Appendix 3, Table B and MUSIC Modelling Guidelines for South East
Queensland Version (2010).

It is proposed that best practice stormwater treatment be used and therefore it is required to
demonstrate the achievement of the following load reduction targets:




A PO Box 26, Carina Q 4152                                                                       8|P a g e
E [email protected]
W www.vtce.com.au
Log in to download the original file

MCU16_0012 Attach B Engineering report & SMP.pdf · 8.6 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.