                      d.      trees must Meet AS2303 - Tree stock for landscape use and be located in accordance
                              with engineering requirements for safe vehicle and pedestrian sight lines.

                      Fauna Management
               14.    Prior to felling or pruning, all trees are to be checked for wildlife (i.e. koalas, possums, birds
                      etc.) If wildlife is present, the tree vegetation must not be felled or pruned until the wildlife
                      has left vegetation or has been relocated by a qualified fauna spotter catcher.
                      (*) Refer to Advisory Note
                      Removal of Existing Trees and Vegetation
               15.    Removal of existing trees and vegetation must be undertaken by a qualified person* and
                      must include:
                      a.      Legal disposal of all removed vegetation and debris.
                      (*) Refer to Advisory Note
                      Engineering
               16.    The developer must meet any costs to repair damage to any Council asset during
                      construction, where damage is a result of the development works. Damage to assets must
                      be repaired immediately where it creates a hazard to the community. In circumstances where
                      the damage does not create a hazard to the community, it must be repaired immediately on
                      completion of the works associated with the development.
               17.    All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
                      who is independent of the Developer and Principal Contractor, and they must certify that all
                      works conform to the Operational Works permit. Where municipal works are involved, such
                      confirmation must be submitted for the respective hold points prior to any site inspection by
                      Council Officers.
               18.    All works must be constructed and work procedure undertaken in accordance with:
                      a.      The approved plans/documents and conditions detailed in this Decision Notice;
                      b.      The relevant conditions of the higher order Material Change of Use approval
                              MCU23/0070 to which this approval relates;
                      c.      All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
                              specifications and guidelines; and
                      d.      The latest version of the Healthy Waterways document “Water Sensitive Urban Design
                              Technical Design Guidelines for South East Queensland” for all water quality devices
                              to be constructed on site.
                      Pavement Design and Construction
               19.    Pavement design for privately owned works must be undertaken in accordance with the
                      relevant standards. Structural integrity of the driveway and car park areas will remain the
                      responsibility of the property owner/developer and must be certified by an RPEQ.
                      Works within Road Reserve/Reinstatement
               20.    Safe vehicle and pedestrian access on all streets in the vicinity of the development must be
                      maintained at all times. Should footpath/road closures be necessary to carry out construction
                      works, Council’s Engineering Officer must be notified prior to the proposed closure and all
                      requirements complied with.
               21.    All frontage works must match neatly with existing road and verge/footpath features.
                      Additional works beyond the frontage may be required to provide an acceptable transition to
                      existing road and verge/footpath profiles.




                                                                                                         Page 5 of 11
Document Set ID: 23291220
Version: 3, Version Date: 09/10/2024

Used in these records

About this file

File size
175 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - Approved by Delegation of Authority OPW24 0103 (As Published).pdf · 175 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.