13. All future dwellings on the approved Lot 7 must be sited within the building envelopes shown
on the Approved Plans.
14. All future dwellings on the approved Lot 7 must be sited and/or constructed in accordance
with section 6 of the Bushfire Hazard Assessment and Management Plan listed within this
Decision Notice.
ENGINEERING
Property Access and Driveways
15. A residential driveway must be constructed off the existing access handle to service
proposed Lot 7.
16. Vehicle access to Lot 7 & 8 is limited to the constructed driveway only. A clause must be
included in the contract of sale for Lots 7 & 8 which requires vehicle access to be from the
constructed driveway only, and which prohibits the driveway from being relocated without
Council agreement.
Stormwater Drainage
17. Stormwater runoff from the development must be disposed of on-site without causing scour
or damage to the subject site or any adjoining property.
Services
18. Reticulated electricity and telecommunication services must be provided to each lot in
accordance with the standards and requirements of the relevant service provider.
19. Unless otherwise stipulated by telecommunications legislation at the time of construction, the
development must be provided with all necessary conduits, pits and pipes to accommodate
the future connection of optic fibre technology telecommunications.
20. Certification must be submitted to Council from all relevant service providers (Energex and
NBN) which certifies that the development has met the requirements of this Decision Notice
and all applicable legislation at the time of construction.
Easements
21. An easement for the purpose of access and services must be registered against the titles of
the properties in favour of proposed Lot 7. The easement must be sized to provide Lot 7 with
vehicle access and include areas required for vehicle manoeuvring.
22. Unless otherwise agreed in writing by the relevant service provider, any public or third party
infrastructure located on the subject site must be placed within an easement registered
against the title of the property.
23. All easements must be designed in accordance with the planning scheme and granted at no
cost to the Grantee. Where the Grantee is Council or a service authority, the easement
documentation must be in accordance with the Grantee’s standard easement terms. Draft
easement documentation must be submitted to Council for endorsement.
24. All works must be kept clear of any existing or proposed easements on the subject land,
unless agreed otherwise in writing by the Grantee.
Earthworks and Retaining Walls
25. All earthworks and associated batters/retaining structures, both above and below ground
level, both temporary and permanent, must be undertaken in accordance with an Operational
Works approval, and contained entirely within the subject site unless written permission from
the respective landowner(s) is provided to Council.
Page 13 of 15
Document Set ID: 24837619
Version: 14, Version Date: 07/09/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Report - Code - Planning RAL26 0015 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.1 MB (small file)
- File type
No other editions are linked here.