Decision Notice - 010.2008.00000831.001 [As Published] · 142008.831

of 11

Text shows just the words. Original shows the document exactly as it was published.

                                               Officer:          Tracy Jones
                                               Direct Telephone: (07) 5449 5228
                                               Response Address: PO Box 141, Tewantin QLD 4565
                                               Email:            [email protected]
                                               Our Reference:    2008/831
                                               Your Reference:
25 August 2008

Building Surveying Professionals Qld Pty Ltd
PO Box 1632
BUDERIM QLD 4556




Dear Sir

                                      Decision Notice
                                   Integrated Planning Act 1997

I refer to your application and advise that on 25 August 2008 Council decided to approve the
application in full subject to conditions.
Details of the decision are as follows:

1     APPLICATION DETAILS

 Application No:                     2008/831
 Street address:                     247, 249 & 253 David Low Way, Peregian Beach
 Real property description:          Lots 1 & 2 RP 903222 & Lot 26 P 9315
 Planning Scheme:                    The Noosa Plan
2     DECISION DETAILS

The following type of approval has been issued:
    Development Permit for Operational Works - Landscaping, Frontage Works, Roadworks,
      Stormwater, Drainage, Water Supply and Sewerage, Sediment and Erosion Controls and
      Earthworks

3     RELEVANT PERIOD OF APPROVAL
The relevant period for this Development Approval is identified in the Assessment Manager
conditions.

4     ASSESSMENT MANAGER CONDITIONS

Landscaping
1.    The site is to be landscaped in accordance with Council’s Landscaping Code and Planning
      Scheme Policy PSP3 on Landscaping Plants and Guidelines and approved plans as listed
      below: -
       Plan         /      Rev.    Plan / Document Name                           Date
       Document No.



                                                                                          Page 1 of 11
Full text of the other 10 pages

Page 2

                                                                                         2008/831



      LA 01 - 01 of 04    C       Operational Works Hardscape Plan –          17-06-08
                                  Landgraphics
      LA 02 - 02 of 04    C       Operational Works Landscape Plan –          17-06-08
                                  Landgraphics
      LA 03 - 03 of 04    C       Operational Works Landscape Details –       17-06-08
                                  Landgraphics
      LA 04 - 04 of 04    C       Operational Works Landscape Details –       17-06-08
                                  Landgraphics

      and may be amended by these conditions.
2.    The landscape construction is to be implemented in accordance with the amended landscape
      plan, planting schedule and horticultural industry best practices.
3.    All trees must be located a minimum of 1 metre from all services to prevent root/service
      conflict and to provide future ease of maintenance requirements
4.    All native plant species located in-group plantings shall not be subjected to any hedging
      maintenance regimes.
5.    All street trees and internal trees 45 litre and greater must be securely staked and tied to
      assist their growth during the establishment period.
6.    The density of planting must achieve the set out requirements as detailed on the approved
      landscape plan.
7.    All landscaping treatment shall not unduly restrict or prevent access to service meters within
      the site.
8.    All manholes, inspection pits and grates are to be raised to finish surface level and kept free of
      cover and be visible at all times to ensure prompt access in case of emergency.
9.    The Body Corporate of this development is responsible for the ongoing maintenance of any
      landscaping within the road reserve.
10.   This Development Permit lapses if the development has not happened by 25 August 2010,
      unless application to extend the currency is approved by Council.
Land Development
11.   The development shall be carried out in accordance with the approved plans listed below or as
      modified herein
      Plan         /      Rev.    Plan / Document Name                        Date
      Document No.
      070172 H – 03       B       Hydraulic Services – Plumbing Design        11.06.08
      TD                          & Drafting
      M3087/C01           A       Cover Sheet – Barlow Gregg
      M3087 – C02         B       Sediment & Erosion Control Plan –           27/5/08
                                  Barlow Gregg
      M3087 – C03         F       Carpark Layout Plan – Barlow Gregg          19/8/08
      M3087 – C04         C       Standard Details – General – Barlow         27/5/08
                                  Gregg
      M3087 – C05         F       Stormwater Layout Plan                      19/8/08



                                                                                      Page 2 of 11

Page 3

                                                                                       2008/831



      M3087 – C06         D      Stormwater Longitudinal Sections &         19/8/08
                                 Details – Barlow Gregg
      BM003087 – 00       F      Basement Slab Relief Drainage System       19/8/08
      – 03                       Layout – Barlow Gregg
      BM003087 – B        C      Basement Footing Details Sheet 2       –   15/7/08
      – 04                       Barlow Gregg
      W-02-02             O      Ground     Floor     Plan    –    CORE     28.07.07
                                 Architecture
      W-01-01             H      Site Plan – CORE Architecture              28.07.07

12.   A Traffic Management Plan (TMP) for the development addressing all construction phases
      shall be prepared by suitably qualified persons and submitted to Council for approval prior to
      the pre start meeting. The TMP shall address, but not be limited to, all items listed below:
            12.1      A single nominated access location to and from the site.
            12.2      The plan should detail the routing of trucks to and from the site.
            12.3      Provision of onsite parking for personnel working on this development, as
                      there is limited parking available in adjacent streets.
            12.4      Provision of safe cycle and pedestrian movements in the vicinity of the
                      development along David Low Way.
            12.5      No queuing of trucks is permitted on residential streets, especially prior to
                      7.00am. Further parked trucks must have engines turned off.
            12.6       Provision of signage and traffic controllers in accordance with Manual of
                       Uniform Traffic Control Devices and the Transport Infrastructure (Roads) Act.
            12.7       Provide an indication where the surplus spoil is to be transported to.
13.   The finished level of all mulch in garden beds and landscaped medians is to be a minimum of
      50mm below the level of the adjacent top of kerb. All landscaping is to be constructed in
      accordance with Council’s Planning Scheme Policy PSP03 Landscaping Plants and
      Guidelines.
14.   Suitable root barriers shall be installed where proposed trees are adjacent to paths, pavement,
      etc, in accordance with Council’s Planning Scheme Policy PSP03 Landscaping Plants and
      Guidelines.
15.   The pipe class for stormwater drainage line 3/2 to EX/2 shall be “Class 2”. (Drawing M3087-
      C05-F refers).
16.   Council’s Construction Technical Officer (phone 0410 512 505) shall be given seven (7) days’
      notice of intention to commence works to arrange a “pre start” meeting prior to the
      commencement of those works.
17.   The principal contractor must have all the appropriate insurance and public liability
      documentation to carry out the works. The principal contractor is also responsible to ensure
      that any sub contractors also have the appropriate insurance and public liability
      documentation.
18.   Prior to the “pre start” meeting, the principal contractor must be provided with a copy
      of Council’s signed approved drawings and conditions by the applicant.




                                                                                   Page 3 of 11

Page 4

                                                                                       2008/831



19.   The Consulting Engineers for the project shall be currently Registered Professional Engineers
      of Queensland (RPEQ).          The consulting engineers are responsible for arranging all
      inspections with Council’s Construction Technical Officer or nominated staff. Council’s
      Construction Technical Officer shall provide an inspection form for signing off by the Engineer
      at appropriate stages of construction, during on-site meetings. Council’s Construction
      Technical Officer will also sign the form at each stage when requested conditions have been
      satisfied. The works will be accepted “On maintenance” after this form has been signed by
      Council’s Construction Technical Officer, together with a letter from the Engineer requesting
      that the works go “On maintenance”.
20.   Prior to works commencing, Council is to be advised of the Engineer (RPEQ) supervising the
      project. (This person will be the contact for the project).
21.   Council standards shall apply to these works unless otherwise modified herein.
22.   The person acting on this permit shall ensure that its consultants and contractors take all
      reasonable care during the construction of the engineering works to ensure that Council
      property, road pavements or facilities (such as underground drainage, water supply,
      sewerage, footpaths, kerbing, landscaping, street furniture, etc.) are protected against any
      damage or interference whatsoever.
      If any Council property or facilities should be damaged by the Applicant or any of its
      Consultants or Contractors through any cause whatsoever in the course of, directly or
      indirectly, carrying out the engineering works, the Applicant and/or its Contractors shall
      forthwith notify the Manager Land Development and shall forthwith rectify the damage to that
      property or facility at its cost and to the satisfaction of the Manager Land Development.
      All rectification works are to be completed prior to the commencement of the use or,
      alternatively, the Applicant may request Council to carry out the rectification work at the
      Applicant’s cost, such cost being paid by the Applicant to Council prior to the commencement
      of the use.
      In the case of any emergency, Council shall be entitled to rectify such damage at the cost of
      the Applicant, such cost being paid prior to the commencement of the use.
23.   The development of the site shall be carried out in such a manner as to prevent dust and/or
      sand nuisance to residents and/or tenants in the vicinity of the development.
24.   Construction work and other associated activities are permitted only during the hours
      of 7.00 am and 6.00 pm Monday to Saturday. No work is permitted on Sundays or public
      holidays, except where extended hours are approved by the Manager, Land Development, or
      his nominee.
25.   Safe pedestrian access along David Low Way in the vicinity of the development shall be
      maintained at all times. If footpath / road closures are necessary to carry out construction
      works, Council’s Construction Technical Officer (phone 0410 512 505) must be notified prior to
      the proposed closure.
26.   Sediment and erosion control measures must be in place prior to works commencing. If such
      measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such
      fines can be issued if sediments from the site are found to enter or have the potential to enter
      Council’s stormwater system or natural waterways. Although the sediment and erosion control
      measures have been approved on Barlow Gregg’s drawing M3087 – C02 B, Council’s
      Manager, Land Development, may request further controls to be installed should approved
      measures be inefficient.
27.   The owner of the subject property shall inspect the gross pollutant traps on a weekly basis,
      after each storm event and in accordance with the manufacturer’s specifications. The owner
      shall also enter into an ongoing maintenance contract with a Registered Contractor to clean
      and maintain the gross pollutant traps at regular three monthly intervals and on an “On Call”
      basis in the case of an emergency.
                                                                                    Page 4 of 11

Page 5

                                                                                        2008/831



      The management and maintenance of the gross pollutant traps shall be included in the
      Community Management Scheme for the completed development.
28.   All stormwater drainage lines, including private drainage lines or as otherwise approved by
      Council’s Manager of Land Development shall be inspected by closed circuit television
      (CCTV) at the completion of all works and immediately prior to acceptance of ‘On
      Maintenance’. Council’s Construction Technical Officer shall be advised of the timing of this
      inspection.
      A report of the CCTV inspection, including photographic records (which includes photos &
      video recordings burnt onto a CD) of the inspection shall be submitted to the Council for
      approval. Any defects or substandard works shall be recorded and accurately illustrated on
      the drainage plan showing the location of the defect(s).

      Substandard work will not be accepted ‘On Maintenance’ and must be rectified at the
      applicants expense with a further CCTV inspection arranged once the rectification works have
      been completed.
      To this extent all CCTV inspections, including any additional inspections necessary following
      defect identification and rectification, shall be entirely at the applicant’s expense. Any costs
      incurred by Council in reviewing the CCTV inspection results shall also be borne by the
      applicant.
29.   Prior to acceptance of civil works to become Council assets "On Maintenance", the lodgement
      of satisfactory “As Constructed” records shall be submitted to Council.
      As Constructed drawings and data shall be certified by a qualified experienced Civil Engineer
      (RPEQ) for design intent, and a Licensed Surveyor shall certify the cadastre and the location,
      level and type of all services and structures. All of which shall be submitted to Council for
      checking and for Council’s records.
      The data must fully detail levels for all engineering works including but not limited to drainage
      structures, finished ground levels and pavement surface levels. The data shall be submitted in
      the Asset Design and As Constructed (ADAC) digital format. Guidelines on the use of ADAC
      are available at www.adac.com.au and Council’s “Noosa Planning Scheme Policy 5 –
      Engineering Design Standards – Roads, Drainage and Earthworks”.
      Approval of works shall not be granted until all As Constructed information has been supplied
      and accepted by Council.
30.   A 5% cost of works to become Council assets or $1,500 bond (whichever is the greater) will
      be imposed on construction works during the maintenance period, which is a minimum period
      of 12 months duration. Such bond must be lodged by, and shall only be accepted from the
      Developer for the works.
31.   The works to become Council assets will not be accepted "On Maintenance" until the
      landscaping is completed.
32.   Notwithstanding that Council has checked the plans with due care, where it is found during
      construction that variations from Council's standards exist, then Council standards shall apply.
Water and Sewer
33.   The names of any proposed contractors for works are to be submitted in writing, together with
      copies of current Public Liability and Workers Compensation Insurances together with
      certificates of currency for those policies, for consideration by the Assessment Manager seven
      (7)     days     prior   to     pre-start    meetings     and     commencement      of    works.
      A separate letter will then be issued approving the contractor (or otherwise) for the works. No
      other contractor or subcontractor shall be engaged to carry out the works or any part of the
      works without the written approval of the Assessment Manager.


                                                                                     Page 5 of 11

Page 6

                                                                                        2008/831



34.   Council’s Water & Sewerage Inspector shall be given (7) days notice of intention to commence
      works. A pre-start meeting shall be arranged prior to commencement of works by contacting
      Council’s Water & Sewerage Inspector, Mr Trevor Mourilyan, Ph. 0417 780 830. Inspector is
      only available for pre-start meetings, inspections and testing etc. between the hours of 6:30am
      to 4:00pm, Monday to Friday. Inspector will not be available outside these hours unless prior
      approval is obtained from the Water & Sewerage Capital Works Manager with any costs
      incurred by Council outside the hours nominated above, met by the Contractor/Developer.
      These costs will be in addition to normal inspection fees.
35.   All works to raise the existing sewer manhole lid (MP20/03/07) is to be carried out by a
      Contractor that has written approval by Council.
36.   Notwithstanding that Council has checked the plans with due care, where it is found during
      construction that variations exist with Council's standards, Council standards shall apply.
37.   It is the responsibility of the applicant to ensure that its consultants and contractors take all
      reasonable care during the construction of the engineering works to ensure that Council
      property or facilities (such as underground drainage, water supply and sewerage) are
      protected against any damage or interference whatsoever. If any Council property or facilities
      should be damaged by the applicant or any of its consultants or contractors through any cause
      whatsoever in the course of, directly or indirectly, carrying out the engineering works, the
      applicant and/or its contractors shall forthwith notify the Assessment Manager and shall
      forthwith rectify the damage to that property or facility at its cost to the satisfaction of the
      Assessment Manager prior to the sealing of the survey plan and/or acceptance of the works
      on-maintenance. Alternatively, the applicant may request the Council to carry out the
      rectification work at the applicant's cost, such cost being paid by the applicant to the Council
      prior to the sealing of the survey plan and/or acceptance of the works 'on maintenance'
      provided that in the case of emergency, the Council shall be entitled to rectify such damage at
      the cost of the applicant such cost being paid prior to the sealing of the survey plan and/or
      acceptance of the work 'on maintenance'.
38.   The Contractor shall make all necessary arrangements for supply of water required for
      construction works. The use of hydrant standpipes on Council mains will NOT be permitted.
      Contractors should contact Council’s Water Section on phone 5449 5254 to obtain an
      application form for issue of a key to access Council’s water tanker filling stations. Conditions
      of access and location of filling stations are detailed on the application form.
39.   As Constructed drawings in both hardcopy and digital format (ADAC) produced in GDA94
      Zone 56 coordinate value to the standards and requirements of the Assessment Manager are
      required for Council records. Such 'as constructed' drawings will be required prior to works
      being accepted "on maintenance", where applicable. Requirements for "as constructed"
      information are detailed in the current version of Council's Engineering Design Standards
      (Water & Sewerage) Manual.
      Release of plans of survey and/or acceptance of the works on-maintenance will not be
      considered until lodgement of satisfactory 'as constructed' records.

      Please note that bonding of outstanding works will not be considered by Council.
40.   Construction work and other associated activities are permitted only during the hours of
      7:00am and 6:00pm Monday to Saturday. No work is permitted on Sundays or public
      holidays, except where extended hours are approved by the Assessment Manager or his
      nominee.
41.   Cut-ins to existing live sewer are to be performed by Approved Contractor. Noosa Council Works
      Inspector shall be present during any work on live sewer undertaken by contractor. <An
      additional fee of $160.00 (included below) is required to cover costs associated with these live
      sewer works.


                                                                                     Page 6 of 11

Page 7

                                                                                          2008/831



42.    Fees applicable to the above project are listed below and are to be paid within fourteen (14) days
       of the date of this Decision Notice.
       Plan Examination                   $ 930 – Paid

43.    Builder to liaise with Council in respect to costs and programming of work to be carried out by
       Council. Contact Councils Sewerage Administration on 5449 5254, to arrange a quote for works.

5      REFERRAL AGENCY CONDITIONS
The referral agencies applicable to this application are:

 Referral Trigger              Referral Status   Referral Agency         Referral Address

 Nil

6      APPROVED PLANS/DOCUMENTS

The approved plans and / or documents for this development approval are listed in the following
table:
 Plan / Document No.       Rev.     Plan / Document Name                       Date
 LA 01 - 01 of 04          C        Operational Works Hardscape Plan –         17-06-08
                                    Landgraphics
 LA 02 - 02 of 04          C        Operational Works Landscape Plan –         17-06-08
                                    Landgraphics
 LA 03 - 03 of 04          C        Operational Works Landscape Details –      17-06-08
                                    Landgraphics
 LA 04 - 04 of 04          C        Operational Works Landscape Details –      17-06-08
                                    Landgraphics
 070172 H – 03 TD          B        Hydraulic Services – Plumbing Design       11.06.08
                                    & Drafting
 M3087/C01                 A        Cover Sheet – Barlow Gregg
 M3087 – C02               B        Sediment & Erosion Control Plan –          27/5/08
                                    Barlow Gregg
 M3087 – C03               F        Carpark Layout Plan – Barlow Gregg         19/8/08
 M3087 – C04               C        Standard Details – General – Barlow        27/5/08
                                    Gregg
 M3087 – C05               F        Stormwater Layout Plan                     19/8/08
 M3087 – C06               D        Stormwater Longitudinal Sections &         19/8/08
                                    Details – Barlow Gregg
 BM003087 – 00 – 03        F        Basement Slab Relief Drainage System       19/8/08
                                    Layout – Barlow Gregg
 BM003087 – B – 04         C        Basement Footing Details Sheet 2       –   15/7/08
                                    Barlow Gregg
 W-02-02                   O        Ground     Floor     Plan    –    CORE     28.07.07
                                    Architecture
 W-01-01                   H        Site Plan – CORE Architecture              28.07.07

                                                                                      Page 7 of 11

Page 8

                                                                                            2008/831



7      ADVISORY NOTES
The following Advisory Notes are for information purposes only and do not form conditions of
approval:
1.      Should any changes or modifications to the approved plans be required as a result of
        construction constraints, a “Request to change an existing approval” (Form 2 Development
        Application) under the Integrated Planning Act 1997 must be made. Amended plans clearly
        indicating the changes must be lodged with this application along with the appropriate fees.
2.      All hydraulic drawings shall be submitted to Councils Plumbing Department for assessment for
        a Plumbing Compliance Permit.
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003.
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries
out an activity must take all reasonable and practicable measures to ensure the activity does not
harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial
monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions
may also be issued by the Land and Resources Tribunal, and the Minister administering the Act can
also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural heritage or
the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Co-ordination Unit on 07 3238 3838 to discuss any
obligations under the ACH Act.

8      PROPERTY NOTES
Not applicable

9      PRELIMINARY APPROVAL OVERRIDING SCHEME

Not applicable
10     FURTHER DEVELOPMENT PERMITS REQUIRED

 Type of Development Permit required            Subject of the required Development Permit
 Nil

11     SELF ASSESSABLE CODES

Not applicable
12     SUBMISSIONS

Not applicable

13     REASONS / GROUNDS FOR APPROVAL DESPITE CONFLICT WITH SCHEME
Not applicable

14     RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Integrated Planning Act 1997 is attached.



                                                                                        Page 8 of 11

Page 9

                                                                                      2008/831



During the appeal period, you as the applicant may make written representations to Council about
the conditions contained within the development approval. If Council agrees or part agrees with the
representations, a “negotiated decision notice” will be issued. Only one “negotiated decision notice”
may be given. Taking this step will defer your appeal period, which will continue after Council makes
its decision. (Refer to sections 3.5.17 and 3.5.18 of the Integrated Planning Act 1997).

15     OTHER DETAILS
Should you wish to obtain more information about Council’s decision electronic copies are available
on line at www.sunshinecoast.qld.gov.au, or at Council Offices.

Yours faithfully,




Tracy Jones
SENIOR PLANNING OFFICER




                                                                                   Page 9 of 11

Page 10

                                                                                               2008/831




                                                 Appeal Rights
                                                INTEGRATED PLANNING ACT 1997 & 1998 REGULATION




                                                               (5) If an application is processed under section
The following is an extract from the Integrated            6.1.28(2), appeal rights for submitters for the
Planning Act (Chapter 4).                                  application are available only for the aspects of the
Division 8 - Appeals to court relating to                  development that would have required public
development applications                                   notification under the repealed Act.
Appeals by applicants
                                                               (6) If an application involves assessment
4.1.27.(1) An applicant for a development                  against a concurrence agency code, appeal rights
application may appeal to the court against any of         for submitters for the application are not available
the following-                                             against the part of the approval that represents the
(a) the refusal, or the refusal in part, of a              concurrence agency’s response for the code.
    development application;                               Appeals by advice agency submitters
(b) a matter stated in a development approval,             4.1.29.(1) An advice agency may, within the limits
    including any condition applying to the                of its jurisdiction, appeal to the court about the
    development, and the identification of a code          giving of a development approval for a
                         1
    under section 3.1.6;                                   development application if-
(c) the decision to give a preliminary approval            (a) the development application involves impact
    when a development permit was applied for;                 assessment; and
(d) the length of a currency period;                       (b) the advice agency told the applicant and the
(e) a deemed refusal.                                          assessment manager to treat its response to
    (2) An appeal under subsection (1)(a) to (d)               the application as a submission for an appeal.
must be started within 20 business days (the                   (2) The appeal must be started within 20
“applicant’s appeal period”) after the day the             business days after the day the decision notice or
decision notice or negotiated decision notice is           negotiated decision notice is given to the advice
given to the applicant.                                    agency as a submitter.
    (3) An appeal under subsection (1)(e) may be           Appeals for matters arising after approval given
started at any time after the last day a decision on       (co-respondents)
the matter should have been made.                          4.1.30.(1) For a development approval given for a
Appeals by submitters                                      development application, a person to whom any of
4.1.28.(1) A submitter for a development                   the following notices have been given may appeal
application may appeal to the court about-                 to the court against the decision in the notice-
(a) the giving of a development approval, including        (a) a notice giving a decision on a request for
    any conditions (or lack of conditions) or other            extension of the currency period for an
    provisions of the approval; or                             approval;
(b) the length of a currency period for the approval.      (b) a notice giving a decision on a request to make
                                                               a minor change to an approval.
    (2) The appeal must be started within 20
business days (the “submitters appeal period”)                 (2) The appeal must be started within 20
after the day the decision notice or negotiated                    business days after the day the notice of the
decision notice is given to the submitter.                         decision is given to the person.
    (3) If a person withdraws a submission before              (3) Subsection (1)(a) does not apply if the
the application is decided, the person may not                     approval resulted from a development
appeal the decision.                                               application (superseded planning scheme)
                                                                   that was assessed as if it were an
    (4) If an application involves both impact                     application under a superseded planning
assessment and code assessment, appeal rights                      scheme.
for submitters are available only for the part of the
application involving impact assessment.                       (4) Also, a person who has made a request
                                                                   mentioned in subsection (1) may appeal to
                                                                   the court against a deemed refusal of the
                                                                   request.
1
     Section 3.1.6 (Preliminary approval may override
    local planning instrument)
                                                                                           Page 10 of 11

Page 11

                                                                                              2008/831

     (5) An appeal under subsection (4) may be          For Building Works Only
         started at any time after the last day the     Rights of appeal conferred by Section 4.2.9 of the
         decision on the matter should have been        Integrated Planning Act 1997 as follows:
         made.
                                                        Division 3 – Appeals to tribunals relating to
                                                        development applications
Division 9 - Appeals to court about other
matters                                                 Appeals by applicants
Appeals for matters arising after approval given
(no co-respondents)
                                                        4.2.9(1) An applicant for a development application
4.1.31.(1) A person to whom any of the following        may appeal to the Building and Development
notices have been given may appeal to the court         Tribunal against any of the following-
against the decision in the notice-
                                                        (a) the refusal, or the refusal in part, of a
(a) a notice giving a decision on a request to              development application;
    change or cancel a condition of a development
    approval.                                           (b) a matter stated in a development approval,
                                    2                       including any condition applying to the
(b) a notice under section 6.1.44 giving a decision         development, and the identification of a code
    to change or cancel a condition of a                    under section 3.1.6;
                                                                                  3
    development approval.
                                                        (c) the decision to give a preliminary approval when a
    (2) The appeal must be started within 20                  development permit was applied for;
        business days after the day the notice of the
                                                        (d) the length of a period mentioned in section 3.5.21
        decision is given to the person.
                                                              currency period;
    (3) Also, a person who has made a request
                                                        (e) a deemed refusal.
        mentioned in subsection (1)(a) may appeal
        to the court against a deemed refusal of the       (2) An appeal under subsection (1)(a) to (d) must
        request.                                        be started within 20 business days (the “applicant’s
                                                        appeal period”) after the day the decision notice or
    (4) An appeal under subsection (3) may be           negotiated decision notice is given to the applicant.
        started at any time after the last day the
                                                            (3) An appeal under subsection (1)(e) may be
        decision on the matter should have been         started at any time after the last day a decision on the
        made.                                           matter should have been made.
Appeals against decisions to change approval            The Registrar for the Building and Development
conditions under the repealed Act                       Tribunal may be contacted at the website
4.1.33A.(1) A person who is dissatisfied with a         http://www.localgovernment.qld.gov.au/
decision made on an application to change the
conditions attached to an approval given under
section 2.19(3)or section 4.4 of the repealed Act
may appeal to the court against-
(a) the decision; or
(b) a deemed refusal of the application.
    (2) An appeal under subsection (1)(a) must be
started within 20 business days after the day notice
of the decision is to be given to the person.
    (3) An appeal under subsection (1)(b) may be
started at any time after the last day a decision on
the matter should have been made.
Appeals against local laws
4.1.33B.(1) An applicant who is dissatisfied with a
decision of a local government or the conditions
applied under a local law about the use of premises
or the erection of a building or other structure
permitted by the planning scheme may appeal to
the court against the decision or the conditions
applied.
    (2) The appeal must be started within 20
business days after the day notice of the decision
is given to the applicant.


2
     Section 6.1.44 (Conditions may be changed or
                                                        3
    cancelled by assessment manager or concurrence           Section 3.1.6 (Preliminary approval may override
    agency in certain circumstances)                        local planning instrument)
                                                                                          Page 11 of 11

Used in these records

About this file

File size
72 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - 010.2008.00000831.001 [As Published].pdf · 72 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.