Code Assessment - 12 Eenie Creek Rd (RESOLVED DRAFT)
12 NOOSA PLAN 2020, SECTION 8.2.1
Acid Sulfate Soils Overlay Code
Applies because: The site is affected by the Acid Sulfate Soils overlay.
Performance Outcome Acceptable Outcome Response
PO1 AO1.1, AO1.2, AO1.3
Complies with PO
Development: (a) does not disturb The disturbance of ASS is avoided
The overall outcome of this code is that
ASS; or (a) (b) is managed to avoid by: undertaking an ASS
the release of acid and metal
or minimise the release of acid and investigation and soil analysis
contaminants is avoided, either by not
metal contaminants, where according to the National Acid
disturbing acid sulfate soils or by
disturbance of ASS is (b) Sulfate Soils Guidance; not
managing any disturbance.
unavoidable. (c) (d) (i) (ii) (a) (b) (c) excavating or otherwise removing
(a) (b) (c) Performance outcomes soil or sediment containing ASS;
The principal works are internal to the
not permanently or temporarily
existing building. External works are,
extracting groundwater that results
however, proposed: construction of the
in the aeration of previously
accessible parking space and shared area
saturated ASS; and not undertaking
to AS/NZS 2890.6 including grading,
filling on land at or below 5 metres
bollard footings, a new garden bed to the
AHD that results in: actual ASS
frontage, and any associated pavement
being moved below the water table;
works. The extent of soil disturbance
or previously saturated ASS being
associated with these is to be confirmed at
aerated. Guidelines is a reference to:
detailed design, but it is expected to be
National Acid Sulfate Soils
shallow and localised, and confined to
Guidance: National acid sulfate soils
surface material on a site that is already
sampling a
fully developed and sealed. No bulk
earthworks, no filling of land and no
extraction of groundwater are proposed.
The applicant offers, as conditions of any
approval, that where excavation or filling
below natural ground level is required, an
acid sulfate soils investigation conforming
to the National Acid Sulfate Soils
Guidance be undertaken in accordance
with AO1.1(a), and that any potential or
actual acid sulfate soils identified be
managed in accordance with an acid
sulfate soils management plan in
accordance with AO1.3. On that basis the
performance outcome is satisfied whether
the works disturb acid sulfate soils or not.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.