2022-05-10 Services and Organisation Committee Meeting Agenda
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 10 MAY 2022
New community house and green space
d. Sunshine Beach Ross Cres, Slope Emergent Works
These works were in response to a landslip in late 2021; the land slip was as a result of ongoing
erosion at the creek edge. Contractors successfully diverted the creek away from the slope
erosion site and then installed soil nails and armouring on the slope to protect the slope from
further erosion. As a result of the February 2022 weather event the slope suffered additional site
damage due to the contractor’s scope works not completed at time of flooding.
• Project cost $405,000 of emergent works
• Additional costs post flood event $205,000
This emergent works project will be eligible for Queensland Recovery Assistance funding (QRA).
Page 14 of 22
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.