2022-05-10 Services and Organisation Committee Meeting Agenda

of 22

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

SERVICES & ORGANISATION COMMITTEE MEETING AGENDA                                         10 MAY 2022


Capital Works Program Delivery Status of Multi Year Projects


                                                                                                                                    Project % of       Project %
                                                                        21/22 BR2     21/22 Remaining Total Project Total Project   Total Budget      Complete
                  Finance Project Number - Description                   Budget            Budget        Actuals       Value         Expended      (schedule work)
500551 - Noosa Hinterland Priority Playground - Planning & Design         4,160,752          518,301     5,766,526  6,284,827           92%             98%
500622 - Noosa Heads Noosa Parade Road Corridor                           1,847,167          952,998     1,147,001  8,125,975           14%             47%
500777 - Noosaville Noosa Waters Lock & Weir Renewal                         50,000           48,350         1,650  1,260,000           0.1%            20%
500820 - Renewal of Gympie Terrace Revetment walls                           20,000            7,986        75,961    460,000           17%             50%
500864 - Tewantin Doonella Bridge Renewal                                   360,000          228,820       288,710  5,360,000            5%             25%
500888 - Cooroy Maple Street Raised Pedestrian Crossing - LGGSP             883,407           37,380       918,345    955,726           96%             100%
500905 - Rufous St - Stage 3 Community House, Car Park & Landscape        3,481,193        1,411,736     3,697,368  5,213,994           71%             95%
500942 - Cooran Tablelands Road Bridge Renewal - BRP                      1,179,361           57,894     1,339,430  1,397,323           96%             100%
500946 - Kin Kin Wahpunga Lane Bridge Renewal Annual - BRP                2,587,132        1,858,051       907,706  2,733,577           33%             38%
510029 - Noosa Heads Dog Beach SEMP                                         100,547           74,858        84,142  1,200,000            7%             25%
510033 - NDSC McKinnon Drive Community facility - (Former Navy Cadets) W4Q 204,391           202,357        17,643    220,000            8%             15%
510035 - Whole of Shire Mobile Library Service Solution                     696,916          689,037        10,963    750,000            1%             60%
510039 - Sunrise Beach Sobraon Street Slope Stabilisation - W4Q &LRCI       669,677           36,106       879,239    915,346           96%             100%
510042 - Noosaville Eumundi Road Landfill Outbound Weighbridge              264,000          260,941        29,174    290,115           10%             60%
510043 - Noosaville Eumundi Road Landfill Liner, Cell capping design      4,595,000        3,774,888       997,650  4,772,538           21%             65%
510044 - Noosaville Eumundi Road Landfill Expansion of Resource Recov        25,008           16,286        39,995     56,281           71%             25%
510047 - Tewantin Bypass Stage 1                                          7,313,379        4,917,870     2,882,130  9,800,000           29%             75%
510065 - Cooroy Belli Creek Road Bridge Renewal                             143,000           23,069       175,096 TBA                #VALUE!           45%
510066 - Noosa Heads Garth Prowd Bridge Renewal                             480,000          362,232       163,454  3,500,000            5%             15%
510067 - Black Mountain Lawnville Road Bridge Renewal                       123,000            2,268       172,646 TBA                #VALUE!           15%
510068 - Trail 5 Upgrade                                                    534,165          418,507       162,219  1,680,725           10%             25%
510074 - Living Fire Tech Lab - Disaster Rec Cat D                          450,000          234,325       243,767  1,963,000           12%             50%
510083 - Noosa Heads Bus Station Options Analysis and Concept Design        200,000           96,730       104,292    200,000           52%              3%
510084 - Cooroy Gumtree Drive Pedestrian Bridge Construction                 35,000            8,805        26,195    130,000           20%             33%
510091 - Noosaville Foreshore Park Stormwater Renewals SEQCSP2124            30,000           20,790         9,210    600,000            2%              5%
510120 - Public Amenities Renewal Program SEQCSP2124                        200,000           66,408       133,592    500,000           27%             60%
510128 - Noosa Heads, Noosa Drive Halse Lane to Sunshine Beach Rd           270,000          247,176        22,824    455,000            5%             10%

Due to scale and complexity, 27 projects are being delivered over multiple financial years.


                                                                                        Page 17 of 22
Log in to download the original file

2022-05-10 Services and Organisation Committee Meeting Agenda(PDF, 4MB).pdf · 4.6 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.