Capital Works Program Delivery Status of Multi Year Projects
Project % of Project %
21/22 BR2 21/22 Remaining Total Project Total Project Total Budget Complete
Finance Project Number - Description Budget Budget Actuals Value Expended (schedule work)
500551 - Noosa Hinterland Priority Playground - Planning & Design 4,160,752 518,301 5,766,526 6,284,827 92% 98%
500622 - Noosa Heads Noosa Parade Road Corridor 1,847,167 952,998 1,147,001 8,125,975 14% 47%
500777 - Noosaville Noosa Waters Lock & Weir Renewal 50,000 48,350 1,650 1,260,000 0.1% 20%
500820 - Renewal of Gympie Terrace Revetment walls 20,000 7,986 75,961 460,000 17% 50%
500864 - Tewantin Doonella Bridge Renewal 360,000 228,820 288,710 5,360,000 5% 25%
500888 - Cooroy Maple Street Raised Pedestrian Crossing - LGGSP 883,407 37,380 918,345 955,726 96% 100%
500905 - Rufous St - Stage 3 Community House, Car Park & Landscape 3,481,193 1,411,736 3,697,368 5,213,994 71% 95%
500942 - Cooran Tablelands Road Bridge Renewal - BRP 1,179,361 57,894 1,339,430 1,397,323 96% 100%
500946 - Kin Kin Wahpunga Lane Bridge Renewal Annual - BRP 2,587,132 1,858,051 907,706 2,733,577 33% 38%
510029 - Noosa Heads Dog Beach SEMP 100,547 74,858 84,142 1,200,000 7% 25%
510033 - NDSC McKinnon Drive Community facility - (Former Navy Cadets) W4Q 204,391 202,357 17,643 220,000 8% 15%
510035 - Whole of Shire Mobile Library Service Solution 696,916 689,037 10,963 750,000 1% 60%
510039 - Sunrise Beach Sobraon Street Slope Stabilisation - W4Q &LRCI 669,677 36,106 879,239 915,346 96% 100%
510042 - Noosaville Eumundi Road Landfill Outbound Weighbridge 264,000 260,941 29,174 290,115 10% 60%
510043 - Noosaville Eumundi Road Landfill Liner, Cell capping design 4,595,000 3,774,888 997,650 4,772,538 21% 65%
510044 - Noosaville Eumundi Road Landfill Expansion of Resource Recov 25,008 16,286 39,995 56,281 71% 25%
510047 - Tewantin Bypass Stage 1 7,313,379 4,917,870 2,882,130 9,800,000 29% 75%
510065 - Cooroy Belli Creek Road Bridge Renewal 143,000 23,069 175,096 TBA #VALUE! 45%
510066 - Noosa Heads Garth Prowd Bridge Renewal 480,000 362,232 163,454 3,500,000 5% 15%
510067 - Black Mountain Lawnville Road Bridge Renewal 123,000 2,268 172,646 TBA #VALUE! 15%
510068 - Trail 5 Upgrade 534,165 418,507 162,219 1,680,725 10% 25%
510074 - Living Fire Tech Lab - Disaster Rec Cat D 450,000 234,325 243,767 1,963,000 12% 50%
510083 - Noosa Heads Bus Station Options Analysis and Concept Design 200,000 96,730 104,292 200,000 52% 3%
510084 - Cooroy Gumtree Drive Pedestrian Bridge Construction 35,000 8,805 26,195 130,000 20% 33%
510091 - Noosaville Foreshore Park Stormwater Renewals SEQCSP2124 30,000 20,790 9,210 600,000 2% 5%
510120 - Public Amenities Renewal Program SEQCSP2124 200,000 66,408 133,592 500,000 27% 60%
510128 - Noosa Heads, Noosa Drive Halse Lane to Sunshine Beach Rd 270,000 247,176 22,824 455,000 5% 10%
Due to scale and complexity, 27 projects are being delivered over multiple financial years.
Page 17 of 22
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.