SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 10 MAY 2022
Finance
The year-to-date capital delivery expenditure to 31st Mar 2022 is $23.8m or 49.6% of the Capital
Program (CWP) total. Figures 3 and 4 below demonstrate the year-to-date budget, actual
expenditure and percentage of program delivered including commitments, broken down for Capital
and Other Capital. Other Capital includes Asset Management, Information Communication and
Technology, Fleet, and the Planning Scheme expansion.
CWP Baseline BR2 Budget 21/22 $ 41,989,831 $ 6,089,192 $ 48,079,023
Other Capital
Capital Total Capital Works
(ICT, Fleet)
Budget Year to Date $ 26,756,994 $ 4,439,329 $ 31,196,322
Actuals Year To Date $ 20,773,723 $ 3,061,146 $ 23,834,868
*Remaining
$ 17,868,447 $ 1,189,720 $ 19,058,166
Commitments/contract values
Figure 3 – Capital Finance data as at 31 March 2022
$35,000,000
$30,000,000
$31,196,322
$26,756,994
$23,834,868
$25,000,000
$20,773,723
$20,000,000
$19,058,166
$17,868,447
$15,000,000
$4,439,329
$3,061,146
$1,189,720
$10,000,000
$5,000,000
$-
Capital Other Capital Total Capital Works
(ICT, Fleet)
Budget Year to Date Actuals Year To Date Commitments
Figure 4 – Budget Status of Capital Works as at 31 March 2022
Page 16 of 22
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.