SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 10 MAY 2022
6. REPORTS FOR NOTING FOR THE COMMITTEE
2 CAPITAL PROGRAM DELIVERY STATUS – 31 MARCH 2022
Author Infrastructure Planning, Design and Delivery Manager, Craig Eldridge
Infrastructure Services Department
Index ECM/ Subject/ 2021-2022 Annual Capital Works Program
Attachments 1. Capital Projects Delivery Status – 31 March 2022
EXECUTIVE SUMMARY
• This report provides a status update for the Capital Works program as at 31 March 2022.
• With Budget Review 2 completed in January 2022, the revised total expenditure for capital
works for the 2021/2022 financial year is $48m; expenditure in direct control of Infrastructure
Delivery ($41.9m) and other such as community projects, ICT and fleet represents ($6.1m).
• As at 31st March Council has expended a total of 49.6% of the 2021/2022 financial year
budget with $19m in commitments.
• As a result of the February 2022 flood event, 4 major projects along with 130 Council assets
have been impacted. Additionally, internal resources have been redirected to disaster
management and now recovery activities. This redirection of resources has further impacted
the project delivery and design teams. Resulting impacts, both budget and schedule, will be
felt throughout next quarter and carry over into 2022/2023.
• Current Covid virus impacts are resulting in disruption to internal and external resources; the
number of impacted staff have reduced capacity of the Infrastructure Planning, Design and
Delivery team and external contractors.
• The reduced availability of labour, equipment and materials and a ‘hot’ construction industry
is proving challenging however works are currently being managed within overall budget
limitations where feasible.
• The road reseal program has expended $3.9m of the $5.3m budget for the 2021/2022
financial year and has all identified projects programmed for completion by 30 June 2022.
• Council has a current forecast of grant funding revenue of $19m while Council’s contribution
to projects with grant funding is at $16.2m and non-grant capital projects amounts to $12.8m.
• The Design Services team are currently supporting the design of 13 projects with multiple
sub-projects with an estimated design value of $970,000 and estimated construction value
of $19m. The Design Services team continues to support the Delivery team in the
construction of over $20m worth of infrastructure and the disaster recovery effort.
• There are currently 26 multi-year projects in various stages of completion.
RECOMMENDATION
That Council note the report by the Infrastructure Planning, Design & Delivery Manager to the
Services & Organisation Committee Meeting 10 May 2022 providing an update on the delivery of
the 2021/2022 capital program as at 31 March 2022.
Page 7 of 22
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.