1.       Site and Application Summary
 Applicant
 Applicant:                                  Geoff Hussin C/- Brennan Planning Pty Ltd
 Contact Details:                            Marcus Brennan
                                             Mob: 0423 952 928
                                             Email: [email protected]
 Registered Landowner(s):                    Geoff Hussin



 Application
                                             Development Permit for Operational Works - Filling and
 Development Application:
                                             Excavation
 Level of Assessment:                        Code Assessable

 Referral Agencies:                          Nil
 SEQRP:                                      Regional Landscape and Rural Production Area


 Subject Site
 Address:                                    36 Tunba Court, Cooroy Mountain

 Lot Description:                            Lot 13 on SP133492

 Area:                                       9.426ha

 Easement(s):                                Yes - Electricity Infrastructure
 Covenants                                   Nil

 Local Plan Area:                            Nil

 Zone:                                       Rural Zone
 Applicable Overlays:                        + Landslide Hazard Overlay
                                                - Moderate hazard area



2. Proposal
The proposal involves retrospective approval and rectification works for filling and excavation that has
occurred at the premises for the purpose of a shed pad.

The pad has been position in the south east corner of the site and has a finished surface level of
approximately RL134.5 to 134.

The existing earthworks for the pad level provide a maximum cut of approximately 3.2m and a maximum fill
of approximately 2.3m relative to the natural ground surface as detailed in Figures 1 and 2 below.

                                                                                                     Page 3 of 13
Log in to download the original file

Town Planning Assessment Report.pdf · 2.9 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.