Decision Notice - Change to an Existing Approval - 010.2007.00000836.002 [As Published] · 142007.836.02
-4- 2007/836
21. Suitable sediment control devices ("in pit” pollution control devices) shall be
temporarily installed into the first existing external downstream stormwater structure.
These devices are to be checked and cleaned on a regular basis and specifically after
each rain event.
These devices are to remain in place during the civil works and construction phases
of the development.
The location and type of device to be installed shall be established at the “pre start”
meeting with Council’s Construction Technical Officer and shall be installed prior to
the commencement of any works.
22. Council’s Construction Technical Officer (ph 0410 512 505), shall be given seven (7)
days’ notice of intention to commence works to arrange a “pre start” meeting
regarding the civil works.
23. The principal contractor must have all the appropriate insurance and public liability
documentation to carry out the works. The principal contractor is also responsible to
ensure that any sub contractors also have the appropriate insurance and public
liability documentation.
24. Prior to the “pre start” meeting, the principal contractor must be provided with
a copy of Council’s signed approved drawings and conditions by the applicant.
25. The Consulting Engineers for the project shall be currently Registered Professional
Engineers of Queensland (RPEQ). The consulting engineers are responsible for
arranging all inspections, with Council’s Construction Technical Officer or nominated
staff.
26. Prior to works commencing, Council is to be advised of the Engineer (RPEQ)
supervising the project. (This person will be the contact for the project).
27. Council standards shall apply to these works unless otherwise modified herein.
28. The person acting on this permit shall ensure that its consultants and contractors take
all reasonable care during the construction of the engineering works to ensure that
Council property, road pavements or facilities (such as underground drainage, water
supply, sewerage, footpaths, kerbing, landscaping, street furniture etc.) are protected
against any damage or interference whatsoever.
If any Council property or facilities should be damaged by the Applicant or any of its
Consultants or Contractors through any cause whatsoever in the course of, directly or
indirectly, carrying out the engineering works, the Applicant and/or its Contractors
shall forthwith notify the Manager Land Development and shall forthwith rectify the
damage to that property or facility at its cost and to the satisfaction of the Manager
Land Development.
All rectification works are to be completed prior to the commencement of the use or,
alternatively, the Applicant may request the Council to carry out the rectification work
at the Applicant’s cost, such cost being paid by the Applicant to the Council prior to
the commencement of the use.
In the case of any emergency the Council shall be entitled to rectify such damage at
the cost of the Applicant, such cost being paid prior to the commencement of the use.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - Change to an Existing Approval - 010.2007.00000836.002 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 63 KB (small file)
- File type
No other editions are linked here.