Council archive · source document
Attachment E - Secondary Dwelling (Exisitng Dwelling Plans from BA) · MCU22/0135
Plans and drawings: the text below has words only, no drawings.
ATTACHMENT 2 – CERTIFICATES FOR PERMIT No. 8971
The following tables provide a list of the certificates that are likely to be required before a Final Inspection Certificate
(Form 21) can be issued for the building work. This list is subject to confirmation by Urban Certifiers after carrying
out a final inspection, and additional certificates may be required. Certificates must be from an approved competent
person or a QBCC licensee.
Certificates are required to be in the approved form (Form 15 or 16 as appropriate). In some cases it will be
necessary for these certificates to be supported by evidence of suitability.
STAGE CERTIFICATES
No. Stage Notes
This certificate can only be issued by a building certifier, but can be
a) Footing Stage based on a structural aspect certificate from a registered engineer and a
setout aspect certificate from a cadastral surveyor is provided.
b) Frame Stage From Urban Certifiers or a competent person (e.g. a registered engineer)
c) Final Stage This certificate can only be issued by a building certifier.
ASPECT CERTIFICATES
No. Type Description
a) Roof trusses Form 15 from the manufacturer of the roof trusses confirming
compliance with AS1684.2-2010 and/or AS1720.5-2015 and other
relevant Australian Standards. A copy of the truss layout plan and
tiedown report should also be provided.
b) Termite management Form 16 from a QBCC licensed termite protection contractor, confirming
the building has been provided with a termite management system in
accordance with BCA Part 3.1.3 and AS3660.1-2014. A copy of the
treatment plan/diagram should also be provided.
c) Roofing Form 16 from a QBCC licensed contractor, confirming the roof
installation complies with NCC Part 3.5.1 and AS1562.1-1992.
d) Gutters Form 16 from a QBCC licensed contractor, confirming the gutter
installation complies with NCC Part 3.5.2 and AS/NZS3500.3-2015 or
section 5 of AS/NZS3500.5-2012.
e) Glazing – windows Form 15 from the window manufacturer confirming the windows supplied
for the project comply with AS2047-2014- and AS1288-2006.
f) Glazing – shower screen Form 15 from the shower screen manufacturer confirming the glass
supplied for the shower screens comply with AS1288-2006.
g) Smoke alarms Form 16 from the electrician confirming the smoke alarm comply with the
Building Regulation 2006 and the NCC Part 3.7.2 (refer to conditions of
approval for more detailed location requirements).
h) Bushfire construction Form 16 from the builder and relevant contractors/suppliers (e.g. window
glazing) confirming the materials and method of construction complies
with the BAL requirements specified und AS3959-2009.
i) Wet area waterproofing Form 16 from a QBCC licensed waterproofing contractor confirming the
wet areas within the building have been waterproofed in accordance with
AS3740-2010.
j) Insulation Form 16 from the builder or installer that insulation has been installed in
accordance with the approved energy efficiency report.
49 DONNELLYS ROAD, RIDGEWOOD
PERMIT NO 8971 PAGE 5 OF 6
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment E - Secondary Dwelling (Exisitng Dwelling Plans from BA)Related documentApplication case desk ↗
About this file
- File size
- 8.8 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.