Skip to the record
The gold standard in government transparency.

Original source · versioned page text

2017-01-16 General Committee Agenda

of 146

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (15.2 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

GENERAL COMMITTEE MEETING AGENDA                                                16 JANUARY 2017


      Pedestrian and Bicycle Facilities
28.   Pedestrian and bicycle facilities must be provided for the development. The works must be
      undertaken in accordance with an Operational Works approval and must include in particular:
      a.   a 1.8 metre wide footpath within the road verge for the entire length of the site’s
           frontage to Pelican Street and Doonella Street. The path must be extended to the
           existing full width path in Memorial Avenue
      b.   signage and lighting at strategic locations to direct people to building entries
      c.   a total of 13 bicycle parking spaces
      Stormwater Drainage
29.   The site must be provided with a stormwater drainage system connecting to a lawful point of
      discharge. The works must be undertaken in accordance with an Operational Works
      approval and must include in particular:
      a.   a stormwater drainage system that collects and discharges runoff such that there is no
           net increase in stormwater runoff from the site.
      b.   the use of gravity stormwater drainage and not surcharge pits.
      Stormwater Quality Management
30.   A stormwater quality treatment system must be provided for the development. The works
      must be undertaken in accordance with an Operational Works approval and achieve the
      pollution reduction targets of the State Planning Policy Appendix 2 Water Quality and be
      modelled in accordance with the Water by Design MUSIC modelling guidelines or the Water
      by Design deemed to comply solutions
31.   Stormwater quality treatment devices must be routinely checked, serviced and cleaned in
      accordance with the manufacturer’s recommendations or Water by Design “Maintaining
      Vegetated Stormwater Assets” guidelines. Records of all maintenance activities undertaken
      must be kept and made available to Council upon request. Where replacement cartridges or
      other necessary components for the system become unavailable, an alternative system is
      required to be retrofitted into the development to achieve an equivalent pollutant reduction
      outcome.
32.   All primary stormwater quality treatment devices must be routinely checked, serviced and
      cleaned in accordance with the manufacturer’s recommendations. Records of all
      maintenance activities undertaken must be kept and made available to Council upon request.
33.   The ongoing maintenance plan for the development must include the operations and
      maintenance manual for the water quality device/s and must include the full cost of
      maintaining the system. This maintenance plan must be provided as part of the subsequent
      operational works
      Easements
34.   Unless otherwise agreed in writing by the relevant service provider, any public or third party
      infrastructure located on the subject site must be placed within an easement registered
      against the title of the property.
35.   All easements must be designed in accordance with the planning scheme and granted at no
      cost to the Grantee. Where the Grantee is Council or a service authority, the easement
      documentation must be in accordance with the Grantee’s standard easement terms. Draft
      easement documentation must be submitted to Council for endorsement.
36.   All works must be kept clear of any existing or proposed easements on the subject land,
      unless agreed otherwise in writing by the Grantee.




                                                                                      Page 9 of 146
Log in to download the original file

2017-01-16 General Committee Agenda(PDF, 15MB).pdf · 15.2 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.