Figure 2.3: Excerpt of the Catchment Plan from Design Drawing (catchment 1/3)
TABLE 4.8: WBNM SUB-CATCHMENT FRACTION IMPERVIOUS VALUES – DEVELOPED SCENARIO
WBNM Sub-Catchment Area (ha) Design Impervious (%) Proposed Impervious (%)
Townhouse 0.506 50 90
Balance 0.181 50 50
Total 0.687 - -
4.2.1 Results
The aim of this assessment is to size a detention tank within the townhouse site to ensure peak flows in the 10% AEP are reduced to be below
the TOD 10% AEP pipe capacity, from which the drainage network was designed (that is going from 50% to 90% impervious). The drainage
design flows reporting from Catchment 1/3 are 0.24m3/s in the 10% AEP, which align with estimates from the WBNM model (0.26m3/s).
A summary of the storage size and outlet configuration and key details provided below:
• Detention Tank Summary:
– Size = 50m3
– Outlet 1 = 2 x 225mm at RL0.0m.
– Outlet 2 = 3m weir at RL1.30 (this allows for surcharge of the tank back to the driveway in events larger than the 1% AEP).
– Flow Depth in 10% AEP = RL1.0m
73 EUMUNDI - NOOSA ROAD, NOOSAVILLE I BBNE00529_0002_0001-REP-001-2 17
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.