07/1294 - Op Works - Stormwater, Drainage & Frontage Works - Robert Selkirk [As Published] · 142007.1294

of 41

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

Very large file (10.4 MB): the original may take a few minutes to open or download. The page text below is quick to read.

INTEGRATED PLANNING ACT 1997

State-controlled road matters

For more information refer to Guide 3.

Uniess you answered “none of the above’ to Q2,
the application triggers referral to the Department
of Main Roads (DMR) as a referral agency.

In certain circumstances DMR will be an advice
agency, while in other circumstances DMR will
be a conciirence agency.

Schedule 2 of the IP Requlation will assist you to
determine where DMR is an advice or
concurrence agency for the application.

2.

IDAS Assessment Checklist, Version 20, 2 April 2007
The application involves: (tick applicable box/es)
(1 (i) development on land contiguous* to a State controlled road and for -
(1) (a) material change of use assessable against the planning scheme;

(1 (b) reconfiguring a tot unless -
e the total number of lots is not increased; and
« the fotal number of lots abutting the State-controlled road is not increased;

C1 (c) operational work (not associated with a material change of use assessable against the

planning scheme or reconfiguring a fot mentioned in (b) above)-

« associated with access to a State-controlled road; or

« for filling or excavation; or

« involving the redirection or intensification of site stormwater from the land, through a
pipe with a cross-sectional area greater than 625 cm? that directs stormwater to a
State-controlied road,

Ci (ii) development on land not contiguous to a State-controlled road and -

O(a) material change of use ~
« assessable against the local government's planning scheme; and
« mentioned in schedule 5 of the IP Regulation and exceeding the thresholds set by
that schedule; .
C1 (b) reconfiguring a fot for a purpose mentioned in schedule 5 of the IP regulation
and exceeding the thresholds set by that schedule:
(1) operational work (not associated with a material change of use assessable against ® .
planning scheme or reconfiguring a lot mentioned in (b) above)~
assessable against the local government's planning scheme; and
« mentioned in schedule § of the IP Regulation and exceeding the thresholds set by
that schedule.

(iii) none of the above -

 

Clearing vegetation

For more information refer to Guide 12.
- Unless you answered “none of the above" to Q3,
the application requires assessment by the

I Re ind Wi
(NRW).
if an agency other than NRW is the assessment
Manager for the application, NRW is a
concurrence agency for the application in relation
to this matter.
Ifyou ticked Q3()) or (ii), your application requires}
referral to NRW for assessment regardless of
whether vegetation clearing is proposed or not.

The application involves: (tick applicable box/es)
C1 (i) material change of use -
(a) assessable against the planning scheme;
{b) on a lot containing -
* acategory 1, 2 or 3 area shown on a property map of assessable vegetation; or
« if there is no property map of assessable vegetation for the lot - remnant vegetation;
(c) where the existing use of the land is a rural or environmental use; and
(d) where the size of the land is 2 hectares or larger - complete Part J of Form 1
reconfiguring a lot-
(a) on alot containing a category 1, 2 or 3 area shown on a property map of
assessable vegetation or, if there is no property map of assessable vegetation for
the lot, remnant vegetation;
where the size of the lot before the reconfiguration is 2 hectares or larger;
(c) where 2 or more lots are created; and
(dc) where the size of any lot created is 25 hectares or smaller - complete Part J of Form 1
operational work -
(a) for the clearing of native vegetation where the vegetation clearing is made
assessable under Schedule 8 of the IPA; and
(b) not associated with a material change of use assessable against the planning
scheme mentioned in (i) or reconfiguring a lot mentioned in (li) - complete Part J of

Diii

(b)

Di

Form 1
(iv) none of the above.

 

Strategic port land :

For more information refer to Guide 11.

Hf you ticked (i) - the relevant Port Authority is the
assessment manager for the application.

Hfyou ticked (i) Queenstand Transport is a
concurrence agency for the application.

 

The application involves:

CA (i) development on strategic port land as defined in the Transport Infrastructure Act 1994 (TI
Act) - complete Part { of Form 1

C1 (ii) a material change of use that is inconsistent with the land use plan approved under the
TI Act for the strategic port land - complete Part | of Form 1

£X] (ii) none of the above

 

4 Land contiguous to a State-controlled road is defined i in schedule 14 of the IP Regulation to mean land - if part of the land is within 100m of the State-controlled road; or that is part of a future State-

controlled road.

Page 2

Used in these records

About this file

File size
10.4 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

07_1294 - Op Works - Stormwater, Drainage & Frontage Works - Robert Selkirk [As Published].pdf · 10.4 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.