2017-08-14 General Committee Meeting Notes
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING 14 AUGUST 2018
Damage to Services and Assets
27. Any damage caused to existing services and assets as a result of the development
works must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety,
immediately; or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and
assets must first be referred to the relevant service authority for approval.
Community Management Statement
28. Any proposed Community Management Statement required for the development
pursuant to the Body Corporate and Community Management Act 1997 must be
submitted to Council for endorsement at the same time as submission of the Building
Format Plan (or similar) to Council for compliance assessment.
RECONFIGURING A LOT
Plan No. Rev. Plan/Document Name Date
16-4325AA Plan showing details of Lot 102 on C5604 drawn 20.12.2016
by Max Waterson and Associates
16-4325AB Plan of proposed Reconfiguration of Lot 102 on 30.03.2017
C5604 (Community Title Scheme) drawn by
Max Waterson and Associates
29. Unless otherwise stated, all works required by the conditions of this Decision Notice
must be completed prior to submission of the subdivision plan to Council for plan
sealing.
OPERATIONAL WORKS
APPROVED PLANS
30. Development undertaken in accordance with this approval must generally comply with
the approved plans of development. The approved plans are listed in the following table
unless otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
1622-01 C Site Plan prepared by Callaghan and Toth for that part June 2017
within the subject site
1622-02 C Driveway Layout & Sediment Control Plan prepared by June 2017
Callaghan and Toth for that part within the subject site
1622-03 C Driveway Detail Plan prepared by Callaghan and Toth for June 2017
that part within the subject site
1622-06 C Structural Detail Plan prepared by Callaghan and Toth for June 2017
that part within the subject site
1622-07 C Driveway Longitudinal Section prepared by Callaghan June 2017
and Toth for that part within the subject site
T42L1 Landscape Plan 15.03.2017
Page 4 of 25