Log in to see the plans as drawnCorporate Plan Theme – Excellence as a Council Operational Plan 22/23
Corporate Plan Key Operational Initiatives Outcomes Responsible Areas Update Q1 Status
Focus Areas
5.1 Maintain a focus Review Council’s To review standards of customer service and Director Executive Project being scoped, planned commencement Dec 22. Not
on excellence in Customer Service deliver improved customer service aligned to Services started
Customer Service Charter community expectations
and improved
service delivery
5.2 Maximise Continue to To facilitate economic growth and in Property Planning, investigation, and analysis work to commence Not
financial investigate consideration of alternative revenue sources early in the 2023 calendar year. started
opportunities for industrial land
Council land development
holdings for the opportunities
purpose of
maximising non-rate
revenue
5.3 Further develop Continue the Integration of council’s systems to streamline ICT Progressing the implementation of new animals, Behind
systems to promote transition to T1 Ci operations, increase flexibility, increase infringement, and debtor systems with a planned go-live Schedule
continuous Anywhere for productivity, and cost efficiencies in April 2023 including online animal registration.
improvement Council’s Implementation was delayed due to resignation of the
enterprise ICT Program Coordinator and an ICT Analyst. However,
management Council is still the first in Australia to undertake the
system staged transition to the newer CI Anywhere version of
TechnologyOne property and rating systems.
5.4 Embed corporate Employee Increased employee satisfaction CEO Detailed survey postponed to early 2023. Not
values into the satisfaction started
organisational survey
culture
5.5 Improve online Review customer Increased customer satisfaction ICT, various Work to integrate customer requests and Cleanaway Behind
customer interface service systems branches waste systems, and the Snap Send Solve mobile Schedule
services and processes application was delayed due to resignation of the ICT
Program Coordinator and ICT Analyst and is not
expected to complete until late 2022.
Online portals for rates, debtors and applications are in
the CI Anywhere project with planned completion late
2023.