                                                       Editor's note—Basements should have flood immunity
                                                       above the 1%AEP defined flood event with alternative
                                                       means to mechanical pumping used to achieve such
                                                       immunity.
                                                                                  Disaster management
PO7                                                    AO7.1

Development supports, and does not unduly burden,      Development is located to support self-evacuation of                  The development is sufficiently above the DFE to
disaster management response or recovery capacity or   people and ensure sufficient warning time for the nature of           allow for a shelter-in-place strategy. The access
capabilities.                                          the use.                                                              driveway has also been designed to achieve the
                                                                                                                       Y     immunity and trafficability of Jirrima Cr.

                                                       AO7.2
                                                       Development does not:

                                                       1. increase the number of people calculated to be at risk
                                                       from flooding;                                                  N/A   The proposed new lot is outside of the DFE

                                                       2. increase the number of people likely to need evacuation;
                                                                                                                       N/A   The proposed new lot is outside of the DFE
                                                       3. shorten flood warning times for other uses in the                  Flood warning times are not impacted by the
                                                       floodplain; or                                                  Y     development
                                                                                                                             The proposal is for a single new lot which is not
                                                       4. impact on the ability of traffic to use evacuation routes,
                                                                                                                             considered to impact ability of traffic to use
                                                       or unreasonably increase traffic volumes on evacuation
                                                                                                                             evacuation routes or result in unreasonable
                                                       routes.
                                                                                                                       Y     increase to traffic volumes



                                                       AO7.3
                                                       Materials stored on site:

                                                       1. are readily able to be moved in a flood event to a flood           The proposal does not result in materials stored on
                                                       free area; or                                               N/A       site
                                                       2. are contained in order to minimise movement in times of            The proposal does not result in materials stored on
                                                       flood.                                                      N/A       site



                                                       Editor's Note— Businesses should ensure that necessary
                                                       emergency and continuity plans are in place to account for
                                                       the potential need to evacuate personnel and to relocate
                                                       property prior to a flood event.
                                                                                Essential network infrastructure
PO8                                                    AO8
Log in to download the original file

Reference Documents RAL21 0035.pdf · 7.8 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.